Question

In: Accounting

Lotus Company uses a job order cost system and applies overheads to production on the basis...

Lotus Company uses a job order cost system and applies overheads to production on the basis of direct labour costs. In establishing the predetermined overhead rates for 2015, the following estimates were made for the year: Manufacturing Overhead $960,000 Direct Labour Cost $800,000 Machine Hours 30,000 Labour Hours 50,000 During the month of October, the job cost sheet showed the following costs and production data for Job # 458: Direct Materials Used $120,000 Direct Labour Cost $80,000 Direct Labour Hours 5,000 Machine Hours 3,000 Required: a. Calculate the company’s predetermined overhead application rate. b. Calculate the amount of manufacturing overheads applied to Job # 458 c. Calculate the total cost of Job # 458 d. For 2015, the actual direct labour cost of all jobs was $1,200,000 and the actual manufacturing overhead incurred was $2,150,000. Compute the under-or-over applied for the year.

Solutions

Expert Solution

  • All working forms part of the answer
  • Requirement ‘a’

A

Estimated Manufacturing Overhead

$                960,000.00

B

Estimated Direct Labor Cost

$                800,000.00

C = (A/B) x 100

Predetermined Overhead application rate [as % of direct labor cost]

120%

  • Requirement ‘b’

A

Direct Labor Cost for Job #458

$                  80,000.00

B

Predetermined Overhead application rate [as % of direct labor cost]

120%

C = A x B

Manufacturing Overheads applied to Job #458

$                  96,000.00

  • Requirement ‘c’

Direct Material

$                120,000.00

Direct Labor

$                  80,000.00

Manufacturing Overheads applied to Job #458

$                  96,000.00

Total Cost of Job #458

$                296,000.00

  • Requirement ‘d’

A

Actual Direct Labor Cost

$            1,200,000.00

B

Predetermined Overhead application rate [as % of direct labor cost]

120%

C = A x B

Manufacturing Overhead applied

$            1,440,000.00

D

Actual Manufacturing Overhead incurred

$            2,150,000.00

Overheads are

UNDER - APPLIED, as applied overhead are LESS than actual overheads

E = D - C

Under - Applied by

$                710,000.00


Related Solutions

Hershey Company uses a job order costing system and applies manufacturing overheads on the basis of...
Hershey Company uses a job order costing system and applies manufacturing overheads on the basis of direct labor cost. Total manufacturing overhead was estimated to be $142,595 for the year; direct labor was estimated to total $150,100. (1/1) (12/31) Raw Materials Inventory $ 14,200 $ 9,400 Work in Process Inventory $ 20,000 $ 22,700 Finished Goods Inventory $ 42,500 $ 31,300 The following transactions have occurred during the year. Raw materials purchases $ 111,000 Direct materials used $ 104,500 Direct...
Hershey Company uses a job order costing system and applies manufacturing overheads on the basis of...
Hershey Company uses a job order costing system and applies manufacturing overheads on the basis of direct labor cost. Total manufacturing overhead was estimated to be $142,595 for the year; direct labor was estimated to total $150,100. (1/1) (12/31) Raw Materials Inventory $ 14,200 $ 9,400 Work in Process Inventory $ 20,000 $ 22,700 Finished Goods Inventory $ 42,500 $ 31,300 The following transactions have occurred during the year. Raw materials purchases $ 111,000 Direct materials used $ 104,500 Direct...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,600, direct labor $13,560, and manufacturing overhead $18,080. As of January 1, Job 49 had been completed at a cost of $101,700 and was part of finished goods inventory. There was a $16,950...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 25,000, direct labor $ 15,000, and manufacturing overhead $ 20,000. As of January 1, Job No. 49 had been completed at a cost of $ 112,500 and was part of finished...
ABC Company uses a job order cost system and applies overhead to production on the basis...
ABC Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2014, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job No. 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 22,000, direct labor $ 13,200, and manufacturing overhead $ 17,600. As of January 1, Job No. 49 had been completed at a cost of $ 99,000 and was part of finished...
Oriole Company uses a job order cost system and applies overhead to production on the basis...
Oriole Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,000, direct labor $12,600, and manufacturing overhead $16,800. As of January 1, Job 49 had been completed at a cost of $94,500 and was part of finished goods inventory. There was a $15,750...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,400, direct labor $13,440, and manufacturing overhead $17,920. As of January 1, Job 49 had been completed at a cost of $100,800 and was part of finished goods inventory. There was a $16,800...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 22,400 , direct labor $ 13,440 , and manufacturing overhead $ 17,920 . As of January 1, Job No. 49 had been completed at a cost of $ 100,800 and was...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $24,600, direct labor $14,760, and manufacturing overhead $19,680. As of January 1, Job No. 49 had been completed at a cost of $110,700 and was part of finished goods inventory. There was...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT