Question

In: Accounting

3. Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for...

3. Cost of Units Completed and in Process

The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production.

Work in Process—Assembly Department
Bal., 8,000 units, 45% completed 19,920 To Finished Goods, 184,000 units ?
Direct materials, 188,000 units @ $1.5 282,000
Direct labor 327,300
Factory overhead 127,260
Bal. ? units, 75% completed ?

a. Based on the above data, determine the different costs listed below.

If required, round your interim calculations to two decimal places.

1. Cost of beginning work in process inventory completed this period. $
2. Cost of units transferred to finished goods during the period. $
3. Cost of ending work in process inventory. $
4. Cost per unit of the completed beginning work in process inventory, rounded to the nearest cent. $

b. Did the production costs change from the preceding period?

c. Assuming that the direct materials cost per unit did not change from the preceding period, did the conversion costs per equivalent unit increase, decrease, or remain the same for the current period?

4. Process Costing for a Service Company

Madison Electric Company uses a fossil fuel (coal) plant for generating electricity. The facility can generate 900 megawatts (million watts) per hour. The plant operates 600 hours during March. Electricity is used as it is generated; thus, there are no inventories at the beginning or end of the period. The March conversion and fuel costs are as follows:

Conversion costs $40,500,000
Fuel 10,800,000
  Total $51,300,000

Madison also has a wind farm that can generate 100 megawatts per hour. The wind farm receives sufficient wind to run 300 hours for March. The March conversion costs for the wind farm (mostly depreciation) are as follows:

Conversion costs $2,700,000

a. Determine the cost per megawatt hour (MWh) for the fossil fuel plant and the wind farm to identify the lowest cost facility in March.

Cost Per Mega-watt Hour
Fossil plant $ per MWh
Wind farm

b. Why are equivalent units of production not needed in determining the cost per megawatt hour (MWh) for generating electricity?

c. What advantage does the fossil fuel plant have over the wind farm? Which of the following is true.

  1. Fossil fuel is easily available.
  2. Fossil fuel plant has a cost advantage over wind farm.
  3. The wind farm is subject to the presence of wind and thus, not reliable.
  4. The fossil fuel plant can be turned on and off on a schedule, while the wind farm is subject to the varieties of nature.

Solutions

Expert Solution

3.

Equivalent units
Whole units Material Conversion
Beginning work in process 8,000 0 4,400 (8,000*55%)
Units started and completed 176,000 (184,000-8,000) 176,000 176,000
Units transferred out 184,000
Ending work in process 12,000 (8,000+188,000-184,000) 12,000 9,000 (12,000*75%)
Total equivalent units 196,000 188,000 189,400

Cost per equivalent unit:

Material Conversion
Cost added during the period $282,000 $454,560
Equivalent units 188,000 189,400
Cost per equivalent units $1.5 $2.4

1. Cost of beginning work in process:

Beginning balance $19,920
Add: Cost incurred during the period (4,400*$2.4) 10,560
Cost of beginning work in process: $30,480

2. Cost of units transferred to finished goods:

Beginning work in process $30,480
Cost of units started and completed:
Direct material (176,000*$1.5) 264,000
Conversion (176,000*$2.4) 422,400
Total cost of units transferred to finished goods $716,880

3. Cost of ending work in process:

Direct material (12,000*$1.5) $18,000
Conversion (9,000*$2.4) 21,600
Total cost of ending work in process $39,600

4. Cost per unit of completed beginning work in process = $30,480/8,000 = $3.81 per unit

b. Yes the production cost is changed from preceding period.

c. The conversion cost per unit has increased for the current period


Related Solutions

Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 9,000 units, 65% completed 31,635 To Finished Goods, 207,000 units ? Direct materials, 212,000 units @ $1.5 318,000 Direct labor 492,900 Factory overhead 191,685 Bal. ? units, 45% completed ? a. Based on the above data, determine the...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 3,000 units, 75% completed 9,450 To Finished Goods, 69,000 units ? Direct materials, 71,000 units @ $1.8 127,800 Direct labor 93,700 Factory overhead 36,450 Bal., ? units, 35% completed ? Cost per equivalent units of $1.80 for Direct...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 7,000 units, 70% completed 28,210 To Finished Goods, 161,000 units ? Direct materials, 165,000 units @ $2 330,000 Direct labor 363,100 Factory overhead 141,270 Bal. ? units, 60% completed ? a. Based on the above data, determine the...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 6,000 units, 70% completed16,140To Finished Goods, 138,000 units? Direct materials, 141,000 units @ $1.5211,500   Direct labor178,700   Factory overhead69,430   Bal., ? units, 45% completed?   Cost per equivalent units of $1.50 for Direct Materials and $1.80 for Conversion Costs. a....
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 6,000 units, 75% completed 25,500 To Finished Goods, 138,000 units ? Direct materials, 141,000 units @ $1.7 239,700 Direct labor 372,400 Factory overhead 144,860 Bal. ? units, 70% completed ? a. Based on the above data, determine the...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 7,000 units, 45% completed 16,660 To Finished Goods, 161,000 units ? Direct materials, 165,000 units @ $1.3 214,500 Direct labor 306,800 Factory overhead 119,340 Bal., ? units, 55% completed ? Cost per equivalent units of $1.30 for Direct...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 6,000 units, 70% completed16,140To Finished Goods, 138,000 units? Direct materials, 141,000 units @ $1.5211,500   Direct labor178,700   Factory overhead69,430   Bal., ? units, 45% completed?   Cost per equivalent units of $1.50 for Direct Materials and $1.80 for Conversion Costs. a....
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 2,000 units, 75% completed 10,000 To Finished Goods, 46,000 units ? Direct materials, 47,000 units @ $2 94,000 Direct labor 139,600 Factory overhead 54,330 Bal. ? units, 20% completed ? a. Based on the above data, determine the...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 6,000 units, 35% completed 13,590 To Finished Goods, 138,000 units ? Direct materials, 141,000 units @ $1.6 225,600 Direct labor 200,200 Factory overhead 77,900 Bal. ? units, 35% completed ? Cost per equivalent units of $1.60 for Direct...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a...
Cost of Units Completed and in Process The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 7,000 units, 65% completed 24,150 To Finished Goods, 161,000 units ? Direct materials, 165,000 units @ $1.5 247,500 Direct labor 380,700 Factory overhead 148,100 Bal. ? units, 80% completed ? Cost per equivalent units of $1.50 for Direct...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT