Question

In: Finance

HH Companies has identified two mutually exclusive projects. Project A has cash flows of −$40,000, $21,200,...

HH Companies has identified two mutually exclusive projects. Project A has cash flows of −$40,000, $21,200, $16,800, and $14,000 for Years 0 to 3, respectively. Project B has a cost of $38,000 and annual cash inflows of $25,500 for 2 years. At what rate would you be indifferent between these two projects? Select one: a. 6.34 percent b. −1.72 percent c. 9.41 percent d. −4.38 percent e. 8.28 percent

Solutions

Expert Solution

Calculation of incremental cash flow
Year Cash Flow-A Cash Flow-B Differential cash flow
0 $          (40,000.00) $ (38,000.00)               (2,000)
1 $           21,200.00 $ 25,500.00               (4,300)
2 $           16,800.00 $ 25,500.00               (8,700)
3 $           14,000.00 $               -                 14,000
Calculation of cross over rate -5% -4%
Year Cash flow-1 PV factor, 1/(1+r)^t PV factor, 1/(1+r)^t PV@-5% PV@-4%
0 $                 (2,000)           1.0000               1.0000 $      (2,000.00) $ (2,000.00)
1 $                 (4,300)           1.0526               1.0417 $      (4,526.32) $ (4,479.17)
2 $                 (8,700)           1.1080               1.0851 $      (9,639.89) $ (9,440.10)
3 $                14,000           1.1664               1.1303 $     16,328.91 $ 15,823.93
NPV $          162.71 $       (95.34)
IRR =Lower rate + Difference in rates*(NPV at lower rate)/(Lower rate NPV-Higher rate NPV)
IRR '=-5%+ (-4%--5%)*(162.71/(162.71+95.34)
IRR -4.38%

Related Solutions

Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows...
Suppose that you have two mutually exclusive projects. A and B. Project A has cash flows of CF0, CF1, CF2, CF3, CF4, CF5. (Years 0-5). Project B has cash flow of CF0, CF1, CF2, CF3. The discount rate for the projects is 10.5%. a) Analyze these two projects and recommend a project to accept. b) Carefully outline all your analysis and reasoning and discuss your methodologies for arriving at your solution in detail. Project A Project B CF0 (4,650.00) (8,300.00)...
An investor has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash...
An investor has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$39,000        –$39,000        1 19,200        5,800        2 14,700        12,300        3 12,200        18,800        4 9,200        22,800          Required: (a) What is the IRR for Project A?    (b) What is the IRR for Project B?    (c) If the required return is 9 percent, what is the NPV for Project A?    (d)...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,200 -7,800 1 1,325 1,325 2 2,148 2,148 3 3,640 7,360 The required return for both projects is 8%. 1. What is the IRR for project A? 2. What is the IRR for project B? 3. Which project seems better according to the IRR method? 4. What is the NPV for project A? 5. What is the NPV for project B?...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,700 -8,550 1 1,325 1,325 2 2,148 2,148 3 4,325 8,384 The required return for both projects is 8%. What is the IRR for project A? What is the IRR for project B? Which project seems better according to the IRR method? Project A Project B What is the NPV for project A? What is the NPV for project B? Which...
ABC Inc. has a choice between two mutually exclusive projects, Project I has cash flows of...
ABC Inc. has a choice between two mutually exclusive projects, Project I has cash flows of −$48,000, $20,200, $20,500, and $19,000 for Years 0 to 3, respectively. Project II has a cost of $45,000 and annual cash inflows of $18,500 for 3 years. At what rate would you be indifferent between these two projects? Which project will you take if the required return is 10%. (1+1 points) Answer ABC Inc. needs 150,000 boxes of parts per year over the next...
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Consider the cash flows from two mutually exclusive projects
Use the following information to answer the next three questions. Consider the cash flows from two mutually exclusive projects: Cash FlowYearProject AProject B0-$420,000-$420,0001$140,000$400,0002$230,000$110,0003$331,000$140,000The appropriate discount rate is 8.5%.Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR.
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT