Question

In: Operations Management

using the data below create a time-phased budget for the project. Show how much daily and...

using the data below create a time-phased budget for the project. Show how much daily and cumulative costs of a project is, just as monthly and cumulative costs are shown in figure 10.

WBS

Activity

Intermediate

Predecessor

Duration in

Weeks

Resource

Hourly

cost

Hours per

week

1

Operational definition

1.1

Research literature

3

Becky

$35

30

1.2

Identify and define terms

1.1

1

Ann

$60

30

1.3

Obtain approval of definition

1.2

2

Clive

$50

30

2

Target selection

2.1

Solicit partners for pilot.

2

Ann

2.2

Hold brainstirming meeting

2.1

2

Becky

2.3

Identify characteristics of targets.

2.2,3.1

1

Ann

2.4

Obtain approval of partners

2.3,1.2,3.4

1

Clive

3

Question Set

3.1

Identify Process group

members

2

Clive

3.2

Develop question set

2.3

4

Ann

3.3

Prototype and valid question set

3.2

3

Becky

3.4

Add partners

3.1,2.1

3

Becky

Solutions

Expert Solution

Important Formula:

Total Cost per week=Hourly cost*Hours week

WBS Activity Intermediate Duration in Resource Hourly Hours per Total Cost per week=Hourly cost*Hours week
Predecessor Weeks cost week
1 Operational definition
1.1 Research literature 3 Becky $35 30 $1,050
1.2 Identify and define terms 1.1 1 Ann $60 30 $1,800
1.3 Obtain approval of definition 1.2 2 Clive $50 30 $1,500
1 B C D E F G H I
2 Activiy Duration 1 2 3 4 5 6
3 Research literature 3 1050 1050 1050
4 Identify and define terms 1 1800
5 Obtain approval of definition 2 1500 1500
6 Cost per Week 1050 1050 1050 1800 1500 1500
7 Cumulative cost per week 1050 2100 3150 4950 6450 7950

Formula:

1 B C D E F G H I
2 Activiy Duration 1 2 3 4 5 6
3 Research literature 3 1050 1050 1050
4 Identify and define terms 1 1800
5 Obtain approval of definition 2 1500 1500
6 Cost per Week =SUM(D3:D5) =SUM(E3:E5) =SUM(F3:F5) =SUM(G3:G5) =SUM(H3:H5) =SUM(I3:I5)
7 Cumulative cost per week =D6 =D7+E6 =E7+F6 =F7+G6 =G7+H6 =H7+I6

Line graph is produced using MS Excel: Step: Insert > Line

we have selected row of Cost per Week and Cumulative cost per week for each week, presented on the below Graph


Related Solutions

Part (A): Using R to show how to decompose the seasonal time series data and then...
Part (A): Using R to show how to decompose the seasonal time series data and then subtract that effect from the data. This assignment is to practice using R to learn how to decompose seasonal time series data. Please use the data set in “A Little of R for Time Series” Section 2.4 (p.20): • > births <-scan("http://robjhyndman.com/tsdldata/data/nybirths.dat") > birthstimeseries <-  ts(births, frequency=12, start=c(1946,1)) > birthstimeseries • Then you can use the following to show how you can decompose the time...
The data below show sales of daily ice cream in thousands of dollars and the temperature...
The data below show sales of daily ice cream in thousands of dollars and the temperature in Fahrenheit for 21 consecutive days in an ice cream shop. Assuming there is a linear relationship between the two, find the regression coefficients using the formulae for αhat and βhat (not the Excel regression tool).                         Daily High                  Sales Per Store                         Temperature                (Thousands of Day                 (Degrees F)                 Dollars)                     1                      63                                1.52 2                      70                                1.68 3                      73                                1.80 4                      75                                2.05 5                      80                               ...
Prompt: Using the following assumptions, create the project budget. Note that this is a two -...
Prompt: Using the following assumptions, create the project budget. Note that this is a two - year budget, so you will need to show both years. Also, calculate the initial ROI for this project. You do not have to consider the time value of money In this problem. § § Assume that Blazer reevaluates the sales potential of this project, and realizes that it will likely only sell half as many new units per year than it initially expected when...
Pivot Tables - Please explain how to acheive the following: Using the data below, create a...
Pivot Tables - Please explain how to acheive the following: Using the data below, create a Pivot Table that answers the question “Which salesperson sold the most in any particular month.” A manager wants to click on the Pivot Table and choose a month and have the name of that person appear with his or her amount for that month. Sales Data Salesperson May June July Aug. Sept. Oct. Albertson, Kathy $3,947.00 $557.00 $3,863.00 $1,117.00 $8,237.00 $8,690.00 Allenson, Carol $4,411.00...
Question 4: People decide how to “budget” their time in much the same way that they...
Question 4: People decide how to “budget” their time in much the same way that they decide how to budget for different goods. Each person decides how much they “value” their leisure time versus their work time. The more people work, the more they tend to value their remaining leisure time. This is the justification for paying overtime to people working over 40 hours per week. How might we model this trade-off economically using the basic labor supply model by...
-Using MySQL Workbench Data Modeler, create three (3) models from the tables below. Show Table 1...
-Using MySQL Workbench Data Modeler, create three (3) models from the tables below. Show Table 1 in 3rd Normal Form. Show Table 2 in 3rd Normal Form. Merge the 3rd Normal Forms of Table 1 and Table 2 into a single 3rd Normal Form model. Note that you only can model table and column names and data types. The data shown is for your reference to determine functional, partial, and transitive dependencies. -Provide a summary of the steps you took...
Using the below information open an excel file and create a Sales Budget, a Cash Receipt...
Using the below information open an excel file and create a Sales Budget, a Cash Receipt Schedule and a Production Budget for Fiwrt for the months of Oct, Nov, and Dec. Make sure to use proper format including dollar signs and headers - this will count in the grade. Upload the excel file as your response. Fiwrt Corporation manufactures and sells stainless steel coffee mugs. Expected mug sales (in units) are expected to be as follows: September – 32,000, October...
Complete your own budget using the attached the Family Monthly Budget sheet below. Use Time Value...
Complete your own budget using the attached the Family Monthly Budget sheet below. Use Time Value of Money techniques to calculate the following: How much money do you need to accumulate to retire at age 40 (with a life expectancy of 90)? How much money do you need to accumulate to retire at age 65 (with a life expectancy of 90)? If you had $2,000,000 and retired at age 65, how much would you be able to receive monthly with...
Create a 5-year capital budget for the project below assuming the following. 1.$500,000 initial outlay for...
Create a 5-year capital budget for the project below assuming the following. 1.$500,000 initial outlay for purchase of new machine for a 5-year contract the company was awarded from a customer. 2.The company will have to rent new space for $50,000/year to put machine in. 3.A one-time, year 1 cost to set up the machine and get it running will be $200,000. 4.The machine is expected to generate revenue beginning in year 2. The machine will generate around $150,000 in...
Using Node.js with Express, show how you would create the following routes, using these URL's, as...
Using Node.js with Express, show how you would create the following routes, using these URL's, as examples: ~ http:#localhost:4200/books/isbn/978123487999/author This URL will return an author's full name from array of names, mapped by ISBN. ~ http:〃localhost:4200/books This returns all the books (just the book names) from the database.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT