Question

In: Operations Management

3a. Explain to the Contractor the content requirements of the programme under the NEC4 ECC Option...

3a. Explain to the Contractor the content requirements of the programme under the NEC4 ECC Option B and the consequences of not meeting them.

3b.By reference to Clauses in the contract mentioning the Contractor’s programme, outline its contractual significance.

Solutions

Expert Solution

Content requirements of the programme under NEC4 ECC Option B

It is used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.

Under Option B, the bill of quantities is a ‘traditional’ bill of quantities, i.e. a document prepared by the cost consultant (often a quantity surveyor) that provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender documentation.

From the employer’s specified quantities the contractor prices its rates accordingly, and bears the risk of carrying out the work at the agreed prices.

The contractor is entitled to interim payments, certified at assessment dates by the project manager as set out in the contract. The price for the work done to date is the quantity of completed work for each BoQ item multiplied by the relevant rate and a proportion of any lump sum item in the BoQ. The proportion of the lump sum items to be paid is determined by the extent to which they have been completed.

The contract contains core and secondary option clauses, the shorter schedule of cost components, and contract data.

Clauses in the contract mentioning the Contractor’s programme

This clause lists the matters which are to be shown on a revised programme. It should record the actual progress achieved on each operation and the reprogramming of future operations. It should also show the effects of implemented compensation events. If a compensation event affects the timing of future operations, the consequent alterations to the programme are to be submitted as part of the Contractor’s quotation (Clause 62.2). The revised programme should also show proposals for dealing with delays, Defects and any changes the Contractor wishes to make. Failure by the Contractor to submit revised programmes is of considerable disadvantage to the Contractor in that if a compensation event occurs, the Project Manager may assess it entirely on the basis of his own judgement. Thus it is in the Contractor’s interests to keep the programme up to date and maintain the existence of an Accepted Programme (Clause 64.2).


Related Solutions

Explain how the requirements of the statute of frauds under the UCC are different from those...
Explain how the requirements of the statute of frauds under the UCC are different from those under the common law.
Advise when a contractor will not be in breach of a construction contract as defined under...
Advise when a contractor will not be in breach of a construction contract as defined under the Housing Grants Construction and Regeneration Act 1996, if he wants to stop work on a project due to non-payment.
Q68 A branch of BNP-Paribas has an attractive credit programme. Customers meeting certain requirements can obtain...
Q68 A branch of BNP-Paribas has an attractive credit programme. Customers meeting certain requirements can obtain a credit card called “BNP Wunder”. Local merchants in surrounding communities accept this card. The advantage is that with this card, goods can be purchased at a 2% discount and further, there is no annual cost for the card. Past data indicates that 35% of all card applicants are rejected because of unsatisfactory credit. Assuming that credit acceptance, or rejection, is a Bernoulli process,...
Explain the criteria which should be employed to asses a privatization programme.
Explain the criteria which should be employed to asses a privatization programme.
6.3 3a.  Find an approximation of the area of the region R under the graph of the...
6.3 3a.  Find an approximation of the area of the region R under the graph of the function f on the interval [−1, 2]. Use n = 6 subintervals. Choose the representative points to be the left endpoints of the subintervals.  f(x) = 6 − x2    _________square units b. Find an approximation of the area of the region R under the graph of the function f on the interval [1, 3]. Use n = 4 subintervals. Choose the representative points to...
1a) Explain the procedure for dealing with a compensation event under the NEC4 ECC, Option B....
1a) Explain the procedure for dealing with a compensation event under the NEC4 ECC, Option B. 1b) A Contractor is engaged under a contract incorporating NEC4 ECC Option B. All of the design of the works has been provided by the Client’s consultants. The works require 3000 cubic metres of concrete. The Contractor has noticed the following problem: whilst it is stated in the drawings in the Scope that the concrete must be Grade C30, it is stated in the...
ASSIGNMENT PNB Berhad is considering the purchase of a new production machine under its expansion programme....
ASSIGNMENT PNB Berhad is considering the purchase of a new production machine under its expansion programme. It costs RM500,000 and requires installation costs of RM50,000. The old stamping machine has zero terminal book value and five years of useful life remaining. It is being depreciated using the straight-line method. It was purchased five years ago for RM250,000, and can be sold today for RM100,000. With the use of the new machine, sales in each of the next five years are...
Discuss the preferential treatment policy under the Citizen economic empowerment programme of CEEC using the citizen...
Discuss the preferential treatment policy under the Citizen economic empowerment programme of CEEC using the citizen motherland owned business category. [10 Marks]
we explore the form and content requirements of financial statements of not-for-profit entities, as described by...
we explore the form and content requirements of financial statements of not-for-profit entities, as described by Financial Accounting Standards Board (FASB) Statement No. 117 Identify and research one (1) not-for-profit organization and provide the Web link to the most recent financial report of the organization. The organization identified should include business and investment activities. Contrast the treatment of business type activities in the financial report of the not-for-profit entities and governments.Identify one (1) significant difference in accounting for investments by...
Explain the countercyclical capital buffer implemented under Basel 3 standards for minimum capital requirements of global...
Explain the countercyclical capital buffer implemented under Basel 3 standards for minimum capital requirements of global banks.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT