Question

In: Accounting

Option #1: Acquisition Costs: Land and Building You are the project manager at Janson Manufacturing. Feedback...

Option #1: Acquisition Costs: Land and Building

You are the project manager at Janson Manufacturing. Feedback from the annual employee’s survey revealed that employees were interested in having a fitness center. Thus, last week, you closed the deal and purchased land and a building for $6 million. Other expenses incurred in connection to this purchase included:

Attorney fees for the contract $10,000
Commissions 55,000
Title insurance 8,500
Pro-rated Property taxes 75,000

An independent appraisal was requested to determine the individual fair value estimates. The land appraised at $5.5 million and the building at $1.9 million.

Spending on the property started right away. Janson installed fences and completed the driveway at a cost of $45,000 and $75,000, respectively.

Required:

  1. What is the initial valuation of each asset Janson purchased in these transactions?
  2. Suppose Janson, immediately after acquiring the property, decided to tear down the building. The cost of the removal of the building was $350,000 and salvaged materials sold for $8,000. An additional $100,000 was paid to grade the land for building the new fitness center. What is the initial valuation of each asset Janson acquired in this transaction?

Answers must be submitted in an Excel file showing all calculations used to arrive at the final answers. Provide comments on the spreadsheet to explain the rationale for the amounts recorded.

Solutions

Expert Solution

Solution:

Janson Manufacturing

Determination of the initial valuation of each asset the company purchased in these transactions:

Initial Valuation of each asset:

Land

$4,513,825

Building

$1,559,675

Land Improvements

Fences

$45,000

driveway

$75,000

Computations:

Cost of land and building

Janson Manufacturing

Cost of land and building:

Purchase price

$6,000,000

Commissions

$55,000

Legal fees

$10,000

Title insurance

$8,500

Total Cost

$6,073,500

Note: the pro-rated property taxes are incurred after acquisition and hence not capitalized. Instead they are reported as prepaid taxes and expensed over a period of time.

Initial valuation of each asset acquired in the transaction:

Asset

Fair Value

Proportion

Initial Valuation

Land

$5,500,000

74.32%

$4,513,825

Building

$1.900,000

25.68%

$1,559,675

Total

$7,400,000

100%

$6,073,500

Requirement 2:

Cost of land:

Purchase price

$6,000,000

Legal Fees

$10,000

Commissions

$55,000

Title Insurance

$8,500

Total

$6,073,500

Less: demolition of old building

$350,000

Salvaged value

($8,000)

$342,000

grading costs

$100,000

Total cost of land

$6,515,500

Land Improvements:

Fencing

$45,000

Driveway

$75,000

The cost of land must comprise the costs incurred to make the land ready, including the cost of removal of old building (net of salvage value). Land is not a depreciable asset.

Cost incurred for land improvements such as landscaping, fencing and driveway also need to reported.


Related Solutions

You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
What is an option contract? How is it used in land acquisition? What should developers be...
What is an option contract? How is it used in land acquisition? What should developers be concerned with when using such options? What contingencies may be included in a land option?
You have purchased a multi-tenant office building for $15,000,000. Your acquisition costs associated with this purchase...
You have purchased a multi-tenant office building for $15,000,000. Your acquisition costs associated with this purchase are $25,000. The estimated land value is $3,000,000, of which you estimate the depreciable land portion at $1,000,000. You estimate the 7-year property at a value of $2,000,000. You have arranged a 70% LTV, 7-year mortgage at a 5.25% interest rate with 2 points and a 25 year amortization period. Your projected NOI in the next two years is $1,200,000 and 1,250,000 which includes...
Determine the project costs and Budget (Marks-20) You are a project manager of one of the...
Determine the project costs and Budget (Marks-20) You are a project manager of one of the major construction companies of the region. You got a project of “Toronto Airport” construction. Its quite challenging to complete this huge project on time, so try to devise a strategy to manage this project. Complete the following tasks in this context.
You were the project manager in charge of building a house in Ashburn, Virginia. The house...
You were the project manager in charge of building a house in Ashburn, Virginia. The house was a five-bedroom home estimated to cost $1.2 million dollars and had to be completed in 24 months. You have successfully built the house within cost and on time. You created a Project Budget, Project Schedule, Project Communication Plan, and Project Monitoring and Control Processes Plan for some unexpected schedule and cost problems. Now, develop a lessons-learned document for your organization and the project...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The...
Scenario: You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections...
1.Suppose you are considering the acquisition of an income producing property. The building is currently leased...
1.Suppose you are considering the acquisition of an income producing property. The building is currently leased for the next 4 years with annual (year-end) cashflows of $1,500,000. At the end of the current lease, you expect rents to increase to $1,800,000 (annually) for the foreseeable future. You anticipate selling the property ten years from today, at an expected multiple of 10.0 times the prevailing market rent. Market rates (OCC) are currently 5%, but given the uncertainty surrounding future rental rates...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company needs to maximize the space that it has, and the best approach is to do a staggered build-out in order to better maximize the space in the existing building. You feel that the best approach was to negotiate with multiple contractors on a fixed-price contract. Different contractors discussed other contracts with you, particularly ones to address the current market fluctuations in the raw materials...
The manager of the manufacturing unit of a company is responsible for the costs of the...
The manager of the manufacturing unit of a company is responsible for the costs of the manufacturing unit. The president is in the process of deciding whether to evaluate the manager of the manufacturing unit by the average cost per unit or the variable cost per unit. Quality and timely delivery would be used in conjunction with the cost measure to reward the manager. Required: a. What problems are associated with using the average cost per unit as a performance...
7) You purchased a commercial building and land for $305,000 on May 3rd, 2014. The land...
7) You purchased a commercial building and land for $305,000 on May 3rd, 2014. The land itself was valued at $82,000 when purchased. You sold the land and building for $480,000 on February 15th of 2016. (a) What is the allowable tax depreciation amount for the year 2014? (b) What is the allowable tax depreciation amount for the year 2015? (c) What is the allowable tax depreciation amount for the year 2016?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT