Compare Step Counting method and detailed factorial method (Hand method) in terms of calculation constraints, calculation accuracy, design details availability and cost data availability. Then determine the best method to employ in this case.
FACTOIRIAL METHODE
Comparasion
Detailes factorial methode
The direct-cost items that are incurred in the construction of a plant, in addition to the cost of equipment are:
The contribution of each of these items to the total capital cost is calculated by multiplying the total purchased equipment by an appropriate factor.
“Lang factor”, these factors are best derived from historical cost data for similar processes.
Step counting methods
For a rapid cost estimation step counting mehode play important role.
Step counting estimating methods provide a way of making a quick. in order of :
The technique is based on the premise that the capital cost is determined by a number of significant processing steps in the overall process.
Factors are usually included to allow for the
A number of workers have published correlations based on a step counting approach.
Like TALOR, WILSON
Their equation based on plant capacities under 60,000 tonne per year.
C = 150,000 N (Q/s)^0.30
and above 60,000
C = 170 N (Q/s)^0.675.
where,
C = capital cost in pounds sterling
N = Number of functional units
Q = plant capacity, tonne per year
s = reactor conversion.
THE BEST METHODE
THE STEP COUNTING METHODE GIVES