Question

In: Civil Engineering

Explain a detailed step-by-step method to install a Slurry Wall SOE. Assumptions and given data: The...

Explain a detailed step-by-step method to install a Slurry Wall SOE.

Assumptions and given data:

  1. The SOE is constructed in an urban setting with an excavation depth of 60ft and it will be a permanent structure.
  2. The water table is located 20ft below the ground surface.
  3. Topmost 40ft of excavation is entirely sand (N value < 30)
  4. Below this sand is a soft-to-medium clay to a depth of 60ft and below it is the Bedrock.
  5. The external groundwater level must be maintained.

Provide the following in the explanation:

  1. Equipment used to install the slurry wall.
  2. Procedure for excavating downstage after the slurry walls are installed.
  3. Give details about the concerned construction risks and advantages of slurry wall construction.

Solutions

Expert Solution

1. Procedure:

i). Step 1: Guide Walls

Slurry walls are typically constructed by starting with a set of guide walls, typically 1 metre (3 ft 3 in) deep and 0.5 metres (1 ft 8 in) thick. The guide walls are constructed on the ground surface to outline the desired slurry trench and guide the excavation machinery.

ii). Step 2: Excavation

While a trench is excavated to create a form for a wall, it is simultaneously filled with slurry (usually a mixture of bentonite and water). The fresh slurry is added as required during the excavation to maintain a constant level of slurry near the top for the stability of the trench. The water from the slurry suspension bleeds into the sides of the trench and leaves behind a thin densely packed layer of colloidal particles that acts as a membrane, commonly referred to as a “filter cake.” The hydrostatic force of the slurry, acting in combination with the filter cake, provides stability to the sides of the trench. The excavator digs down to design depth (or bedrock) for the first wall segment.

iii). Step 3: Panel Construction Method

The excavator is then lifted and moved along the trench guide walls to continue the trench with successive cuts as needed. The trench is at all times kept filled with slurry to prevent its collapse, but the liquid filling allows the excavation machinery and excavation spoil to be moved without hindrance.

iv) Step 4: Placing Reinforcement and concreting

Once the excavated depth is reached, the reinforcing steel cage is lowered into the panel and the slurry is displaced with concrete placed through a tremie pipe from the bottom up. The heavier concrete displaces the bentonite slurry, which is pumped out, filtered, and stored in tanks for use in the next wall segment, or recycled. A series of panels are connected together by overlapping the panels or by the use of end stops to form a continuous rigid wall. When the concrete has hardened, excavation within the now concrete-wall-enclosed area can proceed.

2. Equipment:

Generally, the excavation is done using a special clamshell-shaped digger (for soft to medium ground conditions) or a Hydromill trench cutter (for hard ground conditions such as rocks), suspended from a crane.

Since the mentioned ground are relative soft ground conditions, we will proceed with the clamshell-shapped digger or, in general terms, a grabber. As the slurry walls are installed with a grab, a two-jaw slurry wall grab suspended on a duty cycle crawler crane excavates the slurry wall panels.

Slurry wall grabs are of 2 types:

i). Mechanical Slurry Wall Grab

ii). Hydraulic Slurry wall grab.

Mechanical grabs are opened and closed via rope, hydraulic grabs via hydraulic cylinders. Hydraulic grabs can additionally be fitted with flexible guiding strips on the grab frame which allow aligning the grab within the trench.

3. Downstage Excavation Sequence:

As the slurry is has finished construction, excavation to downstage commences. The excavation is typically done in different stages. The depth of excavation of each stage depends on a variety of factors. One of the major factor is the temporary support systems such as tiebacks or internal crossbeams are which installed to prevent the slurry wall from collapsing during downstage excavation. When completed, the structure built within the walled-off area supports the wall, so that tiebacks or other temporary bracing may be removed. Usually, in case of temporary support, the depth of excavation in each stage is kept slightly above or below the consecutive tie installation level. Once the ties are installed using local excavation, the corresponding stage is completely excavated.

The stage depth also depends on groundwater conditions, since GWT is at a depth of 20 ft below Existing Ground Level, till 20ft the stage depth can be more and thereafter it will depend on the dewatering capacity at the site. Each stage has to be completely dewatered before proceeding further. That is, if the pump capacity is such that it can dewater, say 2m, in 4 hrs but the excavators can dig upto 4m in 4 hrs, then the stage depth should be limited to 2m.

Another contributing factor would be muck removal capacity. The faster the muck can be removed and placed, more can be the stage depth and vice versa.

Taking account of all the factors generally, a stage depth of 8ft to 10 ft is adopted.

4. Construction Risks:

Principal unique hazards associated with the slurry walls include:

a. Physical Hazards

(i) Physical injury of workers due to site open excavations, equipment movements etc.

(ii) Noise hazard to workers due to excessive noise during operations.

(ii) Fire, electrocution, or explosion hazards may exist during installation of the slurry wall, should a backhoe rupture an underground utility, such as sewers, pipelines, or electrical or gas lines.

(iii) During mixing operations, workers may be exposed to inhalation/ingestion/dermal hazards from airborne dusts, volatile organic compounds (VOCs), or metals from soil/bentonite mixtures and waste materials. Eye exposure may occur resulting in scratching and scarring of eyes.

(iv) The heavy equipment (small and large) used for site operations may roll over on steep slopes or unstable ground, seriously injuring the operator. Trucks loaded with backfill can back up too far and become stuck in the trench.

b. Chemical Hazards

During the excavation/installation activities, workers may be exposed to caustic irritants such as Portland cement. This material may become airborne during application and can cause skin burns and act as a lung irritant. Other agents such as bentonite used in slurry walls may contain free silica. Workers may also be exposed to waste materials such as organics and heavy metals. These materials may become airborne during excavation and expose workers via ingestion/inhalation/dermal contact routes.

c. Radiological Hazards

Radiological materials may have been buried, or naturally occurring radioactive material (NORM) may be present in soils, sludge and groundwater. Some radioactive materials may present an external hazard. All radioactive materials may present an internal exposure hazard through inhalation or ingestion. It should be noted that this may be a rare hazard to encounter using this remediation technology.

d. Biological Hazards

At those sites involving medical wastes or sewage sludge, microorganisms in the soil may pose exposure hazards during the soil mixing and waste stabilization activities. Workers may be exposed to inhalation/ingestion/dermal contact with pathogens, such as Coccidioides sp., Histoplasma sp., and Mycobacterium sp. if contaminated specks of dust become airborne.

e. Geological Factors:

If the soil profile varies considerably along a short length the design may have to be revised to incorporate any excess loads coming onto the slurry wall. This can risk the integrity of the wall as a continuous rigid member.

5. Advantages:

Slurry walls offer the following advantages:

i. Low cost

ii. High productivity

ii. Very low permeability

iii. Verifiable continuity and depth

iv. Excellent resistance to contaminated groundwater

v. Ability to easily flex with ground movements, even some earthquakes

vi. The slurry remains fluid, allowing time for penetrating difficult layers or obstacles

vii. Re-use of most of the excavated materials


Related Solutions

How do I calculate this? Please include detailed step by step method to solve. The Springvale...
How do I calculate this? Please include detailed step by step method to solve. The Springvale Seaside owners see the change in profits from the price decrease in May and the projection for June. They decide to go back to a price of $81.00 and have sales of 35,000 boxes in June. The May production required staff to work 2 weekends and there were many complaints. No one wanted to work weekends during vacation season in Maine and there was...
Compare Step Counting method and detailed factorial method (Hand method) in terms of calculation constraints, calculation...
Compare Step Counting method and detailed factorial method (Hand method) in terms of calculation constraints, calculation accuracy, design details availability and cost data availability. Then determine the best method to employ in this case.
Explain what are the requirements for Retaining Wall Design. Need explanation and step by step solution...
Explain what are the requirements for Retaining Wall Design. Need explanation and step by step solution and without plagrism
The procedure of using the Conjugate Beam Method: Please explain step by step and follow the...
The procedure of using the Conjugate Beam Method: Please explain step by step and follow the steps to get the final answer correctly. [Need the full procedure.]
Assumptions guides (be sure to explain how your data meets these assumptions and perform the applicable...
Assumptions guides (be sure to explain how your data meets these assumptions and perform the applicable tests. Applicable Tests: T-tests /Chi-Square / Correlation / Regression / ANOVA / Mann-Whitney U / Wilcoxon Signed Rank / Kruskal-Wallis Create a document explaining the data you have decided to use and what statistical test you intend to use. Be sure to use the decision tree provided in this activity. Analyze your data to insure that it meets the assumptions of the test (for...
please explain step by step. see if the given matrix A is diagonalizable, if so, give...
please explain step by step. see if the given matrix A is diagonalizable, if so, give a diagonal matrix similar to A as well as a matrix P so that P⁻¹AP is the diagonal matrix below. 3 1 -1 0 0 -2 0 1 2
Prepare the statement of cash flow, Indirect Method Explain step by step Spartan Company reports $25,000...
Prepare the statement of cash flow, Indirect Method Explain step by step Spartan Company reports $25,000 net income for the year ended December 31, 2016. Also: 1. Accounts Receivable increased by $7,500 during the year and Accounts Payable increased by $10,000 during the year. No other current assets or current liabilities were changed during 2016. 2. During 2016, Spartan reported $2,500 of Depreciation Expense. 3. During 2016, Spartan reported $2,000 gain on sale of equipment. 4. Given: Property, Plant &...
Arrange the following data into a frequency distribution table and explain the solution step-by-step : 41...
Arrange the following data into a frequency distribution table and explain the solution step-by-step : 41 60 72 72 65 64 48 90 60 75 53 48 63 49 58 39 39 75 55 62 53 59 58 38 72 62 60 59 68 60 70 60 56 80 65 85 71 45 70 55 Find measure central tendency. Find measure dispersion. Arrange the following data into a frequency distribution table and explain the solution step-by-step : 41 60 72...
Use Euler's method with the given step size to estimate y(1.4) where y(x) is the solution...
Use Euler's method with the given step size to estimate y(1.4) where y(x) is the solution of the initial-value problem y′=x−xy ,y(1)=3.
Consider the following data. 15,−4,−10,8,14,−10,−2,−11 Step 1 of 3: Determine the mean of the given data...
Consider the following data. 15,−4,−10,8,14,−10,−2,−11 Step 1 of 3: Determine the mean of the given data Step 2 of 3: Determine the median of the given data. Step 3 of 3: Determine if the data set is unimodal, bimodal, multimodal, or has no mode. Identify the mode(s), if any exist. Separate multiple modes with commas, if necessary.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT