Question

In: Operations Management

Angels Inc. is considering bringing the garage fabrication process (which is currently outsourced) in-house. If garage...

Angels Inc. is considering bringing the garage fabrication process (which is currently outsourced) in-house. If garage fabrication were brought in-house, the factory would be structured as follows. Roofs are punched in a roof punching press (10 minutes per roof) and then formed in a roof forming press (5 minutes per roof). Bases are punched in a base punching press (10 minutes per base) and then formed in a base forming press (15 minutes per base), and the formed base is welded in a base welding machine (5 minutes per base).

The base sub-assembly and the roof then go to final assembly where they are welded together (10 minutes per garage) on an assembly welding machine to complete the garage. Assume one operator at each station.

(a)What is the minimum time required to produce a garage (from starting an order to finishing it)?

(b)What is the capacity of the factory in terms of garages per hour?

(c)If you want to increase the capacity, what is the stage that you would put some additional resources?

Solutions

Expert Solution

The precedence diagram of the garage fabrication process is as follows :

Punching of roof

Punching of base

Forming of roof

Forming of base

Welding of base

Welding of base subassembly and roof sub assembly

Throughput time required for roof preparation process

= time required for punching of roof + Time required for forming of roof

= 10 + 5

= 15 minutes

Throughput time required for base preparation process

= Time required for punching of base + Time for forming of base + Time for welding of base

= 10 + 15 + 5

= 30 minutes

Since above 2 processes are parallel and time required for base preparation process is more, effective throughput time of base and roof preparation process = 30 minutes

Time required for welding and roof subassembly = 5 minutes

Therefore , total throughput time of the full process = 30 minutes + 5 minutes = 35 minutes

  1. Hence , Minimum time required to produce a garage = 35 minutes
  2. Capacity of the factory in terms of garages per hour = 60 / 35 = 1.714 garages per hour
  3. For the capacity to increase .

The throughput time of the base preparation process should be < = 15 minutes ( i.e. same or less than equal to throughout time required for roof preparation process )

Therefore , additional resources may be put on Punching of base/ Forming of base / Welding of base


Related Solutions

Which of the following business process activities is least likely to be outsourced? A Insurance B...
Which of the following business process activities is least likely to be outsourced? A Insurance B Benefits Administration C Payroll D Accounts Payable E Research and Development
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently...
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently have a tow truck, and the $60,050 price tag for a new truck would represent a major expenditure. Jane Austen, owner of the garage, has compiled the estimates shown below in trying to determine whether the tow truck should be purchased. Initial cost $60,050 Estimated useful life 8 years Net annual cash flows from towing $8,010 Overhaul costs (end of year 4) $5,970 Salvage...
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently...
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently have a tow truck, and the $60,050 price tag for a new truck would represent a major expenditure. Jane Austen, owner of the garage, has compiled the estimates shown below in trying to determine whether the tow truck should be purchased. Initial cost $60,050 Estimated useful life 8 years Net annual cash flows from towing $8,010 Overhaul costs (end of year 4) $5,970 Salvage...
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently...
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently have a tow truck, and the $60,050 price tag for a new truck would represent a major expenditure. Jane Austen, owner of the garage, has compiled the estimates shown below in trying to determine whether the tow truck should be purchased. Initial cost $60,050 Estimated useful life 8 years Net annual cash flows from towing $8,010 Overhaul costs (end of year 4) $5,970 Salvage...
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently...
Jane’s Auto Care is considering the purchase of a new tow truck. The garage doesn’t currently have a tow truck, and the $60,000 price tag for a new truck would represent a major expenditure. Jane Austen, owner of the garage, has compiled the estimates shown below in trying to determine whether the tow truck should be purchased. Initial cost $60,000 Estimated useful life 8 years Net annual cash flows from towing $7,990 Overhaul costs (end of year 4) $5,990 Salvage...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT