Question

In: Accounting

As director of capital budgeting, you are reviewing three potential investment projects with the following cost...

As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections.

Cash Flow

Project A

Project B

Project C

Investment Cost

($400,000)

($375,000)

($400,000)

Year One Cash Flow

$200,000

$75,000

$50,000

Year Two Cash Flow

$50,000

$75,000

$120,000

Year Three Cash Flow

$75,000

$85,000

$140,000

Year Four Cash Flow

$50,000

$225,000

$125,000

Year Five Cash Flow

$125,000

$60,000

$125,000

1.Calculate the Internal Rate of Return (IRR) for each project.

2.Assuming your capital investment budget of $500,000 will only allow selection of one project (thus the projects are now mutually exclusive), which project should you fund?

Solutions

Expert Solution

Correct Answer:

1.

IRR

Project A

9%

Project B

16%

Project C

11%

2.

Which project should you fund ?

Project B, because it has the highest IRR of 16% in all the three projects.

Working:

Project A

year

Cash Inflow (outflow)

Discount rate @ 5%

Present value

Discount Rate @ 10 %

Present value

0

$     (400,000)

1

$ (400,000.00)

1

$        (400,000)

1

$        200,000

0.952381

$    190,476.19

0.909091

       181,818.18

2

$          50,000

0.907029

$      45,351.47

0.826446

          41,322.31

3

$          75,000

0.863838

$      64,787.82

0.751315

          56,348.61

4

$          50,000

0.822702

$      41,135.12

0.683013

          34,150.67

5

$        125,000

0.783526

$      97,940.77

0.620921

          77,615.17

Net Present Value 1

NPV 2

$      39,691.38

$            (8,745)

IRR = R1 + ((NPV1/(NPV1-NPV2))*(R2-R1))

A

R1 =

0.05

B

R2 =

0.1

C

NPV 1

$            39,691.38

D

NPV2

$                  (8,745)

E

NPV1-NPV2 =

               48,436.43

F

NPV1/(NPV1-NPV2)

0.81945294

G

R2-R1 =

0.05

H

F * G

0.040972647

(A+H)

Project a IRR =

9%

Project B

year

Cash Inflow (outflow)

Discount rate @ 15%

Present value

Discount Rate @ 20 %

Present value

0

$     (375,000)

1

$ (375,000.00)

1

$        (375,000)

1

$          75,000

0.869565

$      65,217.39

0.833333

          62,500.00

2

$        120,000

0.756144

$      90,737.24

0.694444

          83,333.33

3

$        140,000

0.657516

$      92,052.27

0.578704

          81,018.52

4

$        125,000

0.571753

$      71,469.16

0.482253

          60,281.64

5

$        125,000

0.497177

$      62,147.09

0.401878

          50,234.70

Net Present Value 1

NPV 2

$        6,623.15

$          (37,632)

IRR = R1 + ((NPV1/(NPV1-NPV2))*(R2-R1))

A

R1 =

0.15

B

R2 =

0.20

C

NPV 1

$              6,623.15

D

NPV2

$               (37,632)

E

NPV1-NPV2 =

               44,254.97

F

NPV1/(NPV1-NPV2)

0.149658941

G

R2-R1 =

0.05

H

F * G

0.007482947

A+H

Project B IRR =

16%

Project C

year

Cash Inflow (outflow)

Discount rate @ 8%

Present value

Discount Rate @ 14 %

Present value

0

$     (400,000)

1

$ (400,000.00)

1

$        (400,000)

1

$          50,000

0.925926

$      46,296.30

0.877193

          43,859.65

2

$        120,000

0.857339

$    102,880.66

0.769468

          92,336.10

3

$        140,000

0.793832

$    111,136.51

0.674972

          94,496.01

4

$        125,000

0.73503

$      91,878.73

0.59208

          74,010.03

5

$        125,000

0.680583

$      85,072.90

0.519369

          64,921.08

Net Present Value 1

NPV 2

$      37,265.10

$          (30,377)

IRR = R1 + ((NPV1/(NPV1-NPV2))*(R2-R1))

A

R1 =

0.08

B

R2 =

0.14

C

NPV 1

$            37,265.10

D

NPV2

$               (30,377)

E

NPV1-NPV2 =

               67,642.22

F

NPV1/(NPV1-NPV2)

0.550914817

G

R2-R1 =

0.06

H

F * G

0.033054889

A+H

Project C IRR =

11%

End of answer.

Please give thumbs up, it will be highly appreciated.

Thanks.


Related Solutions

As director of capital budgeting, you are reviewing three potential investment projects with the following cost...
As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections. Cash Flow Project A Project B Project C Investment Cost ($400,000) ($375,000) ($400,000) Year One Cash Flow $200,000 $75,000 $50,000 Year Two Cash Flow $50,000 $75,000 $120,000 Year Three Cash Flow $75,000 $85,000 $140,000 Year Four Cash Flow $50,000 $225,000 $125,000 Year Five Cash Flow $125,000 $60,000 $125,000 1.Calculate the Payback Period for each project. 2.If the discount rate for...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING NET CASH FLOWS: COST OF CAPITAL IS 12% YEAR 0 1 2 3 4 X $-2,000 $250 $380 $480 $2,000 Y $-1,800 $1,600 $600 $200 $420 Calculate Project X's DISCOUNT PAYBACK PERIOD (DPB) A. 1.57 B. 1.78 C. 3.47 D. 3.89 E. 5.22
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows...
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows for the two projects are given. For both projects, the required rate of return is 12%. Year Project A Project B 0 ($40,000) ($40,000) 1 $14,400 $0 2 $14,400 $0 3 $14,400 $0 4 $14,400 $70,000 Find the following: 1. The Net Present Value (NPV) . 2. The Internal Rate of Return (IRR) . 3. Use Excel to draw a graph of the NPV...
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows. The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000 Which project would you choose? Project X since it has higher IRR Project Y since it has higher NPV Project X since it has higher NPV Neither...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows: Project E Project F Year Cash Flow Cash Flow 0 -$100,000 -$100,000 1 50,000 10,000 2 40,000 30,000 3 30,000 40,000 4 10,000 60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
Exercise Example - Capital Budgeting Project Analysis - Chapter 5 As director of capital budgeting, you...
Exercise Example - Capital Budgeting Project Analysis - Chapter 5 As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections.   Cash Flow Project A Project B Project C Investment Cost ($500,000) ($375,000) ($475,000) Year One Cash Flow $200,000 $175,000 $250,000 Year Two Cash Flow $180,000 $50,000 $200,000 Year Three Cash Flow $100,000 $50,000 $75,000 Year Four Cash Flow $80,000 $50,000 $30,000 Year Five Cash Flow $140,000 $300,000 $30,000 Calculate the...
The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and...
The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and S, with the following expected net cash flows: Expected Net Cash Flows Year Project L Project S 0 ($100) ($100) 1 10 70 2 60 50 3 80 20 Both projects have a cost of capital of 12 percent. What is Project S's MIRR? What is Project L's MIRR?
magine your department is responsible for evaluating potential capital investment projects and you must establish the...
magine your department is responsible for evaluating potential capital investment projects and you must establish the method and criteria by which projects will be selected. Further assume that your boss thinks NPV analysis is too complicated for most lower management decisions and has directed you to use a method other than NPV. Select one of the other evaluation techniques (Investment Rules) and discuss its merits. In your discussion, address how you might minimize any of the "drawbacks" of your selected...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT