Question

In: Operations Management

Using? PERT, Adam Munson was able to determine that the expected project completion time for the...

Using? PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 ?months, and the project variance is 9.

?a) The probability that the project will be completed in 13 months? = nothing ?(round your response to four decimal? places).

?b) The probability that the project will be completed in 21 months? = nothing ?(round your response to four decimal? places).

?c) The probability that the project will be completed in 25 months? = nothing ?(round your response to four decimal? places).

?d) The probability that the project will be completed in 31 months? = nothing ?(round your response to four decimal? places).

?e) The due date that yields a? 95% chance of completion? = nothing months ?(round your response to two decimal? places).

Solutions

Expert Solution

Given are following data :

Expected project completion time = m = 22 months

Project standard deviation = Sd = square root ( Variance ) = Square root ( (9 ) = 3

  1. M + Z value of probability of completion in 13 months x Sd = 13

Or, 22 + 3.Z = 13

Or, 3.Z = 13 – 22

Or, 3.Z = - 9

Or, Z = - 9/3 = - 3

Corresponding probability for Z =- 3 as derived from standard normal distribution table = 0.00135 ( 0.0014 rounded to 4 decimal places)

PROBABILITY THAT THE PROJECT WILL BE COMPLETED IN 13 MONTHS = 0.0014

  1. M + Z value for probability that project will be completed in 21 months x Sd = 21

Or, 22 + 3.Z = 21

Or, 3.Z = 21 – 22

Or, 3.Z = - 1

Or, Z = - 0.33

Corresponding probability for Z = - 0.33 as derived from standard normal distribution table = 0.3707

PROBABILITY THAT THE PROJECT WILL BE COMPLETD IN 21 MONTHS = 0.3707

  1. M + z value that probability that project will be completed in 25 months x Sd = 25

Or, 22 + 3.Z = 25

Or, 3.Z = 3

Or, Z = 1

Corresponding probability for Z = 1 as derived from standard normal distribution table = 0.84134

PROBABILITY THAT THE PROJECT WILL BE COMPLETED IN 25 MONTHS = 0.84134

  1. M + z value that the project will be completed in 31 months x Sd = 31

Or, 22 + 3.Z = 31

Or, 3.Z = 9

Or, Z = 3

Corresponding probability for Z = 3 as derived from standard normal distribution table = 0.99865

PROBABILITY THAT THE PROJECT WILL BE COMPLETED IN 31 MONTHS = 0.99865

  1. 95% chance of completion mean probability of 0.95 of completion

Corresponding Z value for probability of 0.95 = NORMSINV ( 0.95 ) = 1.6448

The due data that yields 95 % chance of completion

= m + Z x Sd

= 22 + 1.6448 x 3

= 22 + 4.934

= 26.9344 ( 26.93 months rounded to 2 decimal places )

ANSWER :26.93 MONTHS


Related Solutions

PERT networks use a simple statistical method to determine the most likely task completion times. Describe...
PERT networks use a simple statistical method to determine the most likely task completion times. Describe how expected activity times and variances can be computed in a PERT network. Describe a situation in which a project manager would choose PERT for her project.
Will the time frame of a project affect the completion design? Discuss.
Will the time frame of a project affect the completion design? Discuss.
The Time Numbers represent weeks a. Find the mean time for completion of the project b....
The Time Numbers represent weeks a. Find the mean time for completion of the project b. Find the probability that the project will be completed two weeks earlier than the mean time. Preceding Optimistic Most Likely Pessimistic Activity Activity Time Time Time A. Write Book 10 13 17 B. Design Book Cover A 1 1 1 C. Edit Manuscript A 3 6 9 D. Check Editing C 2 3 6 E. Accept Design B 1 1 1 F. Copy Edit...
How does one determine “slack time/float time” from a PERT analysis? What does it mean when...
How does one determine “slack time/float time” from a PERT analysis? What does it mean when a task activity has no “slack time/ float time”
Write a brief report on a real-life project that can be organized using PERT. Books on...
Write a brief report on a real-life project that can be organized using PERT. Books on operations research and project management often have sections on PERT which is sometimes called the critical path method or CPM. Find references on the internet for commercial software that draws PERT diagrams and describe sine of these products and their applications.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
Provide at least 2 examples of a Project Schedule using Gantt Chart and PERT / CPM.
A project completion time can be assumed to be represented by a normal distribution curve The...
A project completion time can be assumed to be represented by a normal distribution curve The project is expected to complete in 36 weeks with a path variance of 6.67 Base on the information provided, calculate: a. Calculate the probability that the project will be completed in 39 weeks or less b. The probability that the project will be completed in between 33.5 and 38 weeks c. With 95 percent probability, calculate the date the project can be completed.
Summarize the qualitative risks of on‐time project completion considering the current employment and work environment in...
Summarize the qualitative risks of on‐time project completion considering the current employment and work environment in the U.S. Several members of your programming team live and work throughout the U.S., and are subject to the laws of those states. Additionally, some of the programming tasks could be modified and possibly sub‐contracted to India, Bulgaria, China, Argentina, and Indonesia.Discuss how the project manager should address cost/time trade‐offs associated with international outsourced completion of programming tasks. What criteria should be used to...
Using excel, determine: The present value of a five (5) year project, with expected annual cash...
Using excel, determine: The present value of a five (5) year project, with expected annual cash flows given below, assuming the cost of capital of 12.5% p.a.                                                                (1 Mark) Year Cash flow 1 75,600.00 2 58,800.00 3 50,400.00 4 42,000.00 5 36,500.00 ii. The future value of $ 12,200 received annually over a period of four (4) years, interest paid quarterly at the rate of 14% p.a.                                    
In order to evaluate an evidence-based practice project, it is important to be able to determine...
In order to evaluate an evidence-based practice project, it is important to be able to determine ... Question: In order to evaluate an evidence-based practice project, it is important to be able to determine ... In order to evaluate an evidence-based practice project, it is important to be able to determine the effectiveness of your change. Discuss one way you will be able to evaluate whether your project made a difference in practice. Note: my project is on Central line...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT