In: Mechanical Engineering
slack time= latest finish time of a activity - earliest finish time of that activity &
earliest finish time=earliest starting time+time to do that activity.
if an activity has no slack time then it means that activity is critical activity. it means you can't delay that activity while completing project.if this activity delays then completing time of project would be increased.