Question

In: Finance

A project has an NPV of £12,632 when a discount rate of 12% is used and...

A project has an NPV of £12,632 when a discount rate of 12% is used and the same project has an NPV of (£6,935) when a discount rate of 24% is used. The approximate internal rate of return of the project is:

Select one:

a. 18.5%

b. 15.16%

c. 20.5%

d. 19.75%
An investment project costs $10,500 and will generate $4,000 in annual cash flows for five years. What is the exact internal rate of return (IRR)?

Select one:

a. 5.56%

b. 13.2%

c. 26.19%

d. 19.27%

Which of the following is a reason that makes NPV a better approach to capital budgeting on a purely theoretical basis?

Select one:

a. It measures the direct impact on investors’ wealth (value created).

b. It measures the benefits relative to the amount invested.

c. Financial decision makers are inclined to higher rates of return.

d. Interest rates are expressed as annual rates of return.

An investment project costs $13,500 and will generate $4,600 in annual cash flows for six years. What is the discounted payback period if the discount rate is 7 percent?

Select one:

a. 3.4 years

b. 4.1 years

c. 3.7 years

d. 4.8 years

What is the profitability index of a project that has an initial cash outflow of $600, an inflow of $250 for the next 4 years and a cost of capital of 10 percent?

Select one:

a. 1.036

b. 1.321

c. 0.667

d. 1.444

An investment project costs $20,000 and will generate $5,000 in annual cash flows for two years followed by $4,000 in annual cash flows for six years. What is the payback period?

Select one:

a. 5.33 years

b. 4.50 years

c. 4.67 years

d. 4.25 years

Solutions

Expert Solution

1. Internal Rate of Return = [(NPV @ 12%) / (NPV @ 12% - NPV @ 24%)] * (24%-12%) + 12%

= [12632 / (12632 - (-6935))] * 12% + 12%

= (0.6456 * 12%) + 12%

= 7.747% + 12%

= 19.747%

= 19.75%

Hence, the answer is d. 19.75%.

2.

IRR = [(NPV @ 15%) / (NPV @ 15% - NPV @ 30%)] * (30%-15%) + 15%

= [2909 / (2909 - (-758))] * 15% + 15%

= (0.7933 * 15%) + 15%

= 11.90% + 15%

= 26.90% (approximately)

Its nearer to 26.19%

Hence, the answer is c. 26.19%.

3. NPV gives importance to direct cash benefits but not in terms of rate of return.

Hence, the answer is a. It measures the direct impact on investors’ wealth (value created).

4.

From the above, it can be observed that cummulative cash inflows exceed initial investment in year 4. So, the discounted pay back period exists in between years 3 and 4. It is calculated as follows:

= [(13500 - 12072) / 3509] * 1 year + 3 years

= 0.4 year + 3 years

= 3.4 years.

Hence, the answer is a. 3.4 years.

5.

Profitability Index = 792.47 / 600

= 1.321

Hence, the answer is b. 1.321.

6. Payback period is different from discounted payback period. Here, discounting of cash inflows doesnot take place.

From the above, it can be observed that cummulative cash inflows exceed initial investment in year 5. So, the pay back period exists in between years 4 and 5. It is calculated as follows:

= [(20000 - 18000) / 4000] * 1 year + 4 years

= 0.50 year + 4 years

= 4.50 years.

Hence, the answer is b. 4.50 years.


Related Solutions

If the discount rate changes from 12% to 15%, what is the CHANGE in the NPV of the project approximately?
A project has the following cash flows: Year 0 Year 1 Year 2 Year 3 Cash flow -100.000 70.000 120.000 200.00 If the discount rate changes from 12% to 15%, what is the CHANGE in the NPV of the project approximately? Please no excel sheet, just detailed steps for someone new in finance ;)
What is the NPV of the following project if the discount rate is 10%? Round to...
What is the NPV of the following project if the discount rate is 10%? Round to the nearest cent. Investment today: $-150,000; Cash flow in year 1: $60,000; Cash flow in year 2: $75,000; Cash flow in year 3: $60,000
(a) NPV at the end of the project (discount rate 15%) (b) IRR at the end...
(a) NPV at the end of the project (discount rate 15%) (b) IRR at the end of the project.       Year (n) 0 1 2 3 4 Capex -$600,000 - - - - Income - $200,000 $200,000 $200,000 $200,000 Undiscounted cash flow P/F (15%) Discounted cash flow IRR - - - -
You are considering a project that has been assigned a discount rate of 12 percent. If...
You are considering a project that has been assigned a discount rate of 12 percent. If you start the project today, you will incur an initial cost of $280 and will receive cash inflows of $350 a year for 3 years. If you wait 1 year to start the project, the initial cost will rise to $420 and the cash flows will increase to $385 a year for 3 years. What is the value of the option to wait? O...
Calculate NPV for each project. Please workout problem.. Discount rate 10% Year Project A Project B...
Calculate NPV for each project. Please workout problem.. Discount rate 10% Year Project A Project B Project C 2018 ($3,000,000) ($3,000,000) ($3,200,000) 2019 $0 $975,000 $985,000.00 2020 $600,000 $975,000 $925,000.00 2021 $900,000 $975,000 $1,000,000.00 2022 $3,000,000 $1,000,000 $950,000.00
PLEASE SHOW CALCULATOR INPUTS A project has been assigned a discount rate of 12 percent. If...
PLEASE SHOW CALCULATOR INPUTS A project has been assigned a discount rate of 12 percent. If the project starts immediately, it will have an initial cost of $480 and cash inflows of $350 a year for three years. If the start is delayed one year, the initial cost will rise to $520 and the cash flows will increase to $385 a year for three years. What is the value of the option to wait?
What is the NPV at a discount rate of zero percent?
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 7,300 2 9,100 3 5,900 a. What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) b. What is the NPV at a discount rate of 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What is the NPV at...
1. Describe the relationship between the IRR and the discount rate when NPV=0. 2. Given the...
1. Describe the relationship between the IRR and the discount rate when NPV=0. 2. Given the following information, should a company invest in a given capital? Initial Investment $675,000 Annual Cash Inflow $158,000 Salvage Value $80,000 Years of life of the equipment and project: 6 Minimum required rate of return: 10% Depreciation $99,167 Payback Period in Years 4.3 Accounting Rate of Return 8.72% NPV $27,553.5 IRR 11.32%
With a monthly discount rate of 0.25%, help Dr. H’s wife find out the NPV of this shrimp keeping project
(Based on a true story. No fish or shrimp is harmed during the production of this question.)Cast of CharactersDr. H:               A college professor of Finance in a Private University. He believes the true path towards happiness is through studying Finance.Wife of Dr. H (WIFE):     A former college accounting major who currently works as the VP of Finance in a local tech company.TimeThe present.SETTING:         Living room at the house of Dr. H and his wife.AT RISE:           Dr. H’s wife is seated...
You are evaluating an investment project and learn the following: The project’s NPV at a discount...
You are evaluating an investment project and learn the following: The project’s NPV at a discount rate of 16% is +$35,879 The project’s NPV at a discount rate of 20% is +$12,356 The project’s NPV at a discount rate of 22% is -$1,923 Based on (i)-(iii) above you know the project’s IRR must be: a. Less than 16% b. Greater than 22% c. Between 16% and 20% d. Between 20% and 22% e. Exactly 20%
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT