Question

In: Operations Management

1. Please Analyze the following case study on the subject of Procurement that involved significant and...

1. Please Analyze the following case study on the subject of Procurement that involved significant and costly mistakes?

Mini case study – Scottish Parliament: the £431m question

Scotland’s new parliament building cost more than 10 times the original estimate and opened three years behind schedule.                

Official cost estimates changed 10 times and ballooned from the initial £40 million estimate to a final £431 million.

The procurement model chosen for Holyrood in early 1998 has emerged as the root of the problem. A fast-track contracting method known as construction management was used to build the parliament. It works by splitting a large building job into numerous smaller packages that are designed, tendered and let independently of one another.

Its main advantage is to speed up construction, because the overall design does not have to be complete before basic building work can begin.

It does not allow a client to know the total cost of a project until well after work has begun. It is considered risky for the client, which is responsible for running each individual package – in this case more than 60.

The project cost escalated from about £40 million in 1997 to £109 million in 1999, £241 million in 2001 and £294 million in 2002, and finally £431 million in February 2004. There were 18,000 design change orders over the five years of construction, combining

to form a three-year delay. Requests for design freezes on three occasions were ignored. The reality is that construction management was the only contract option for a client

wanting to make an early start on a project that was still at the design concept stage.
It is also clear that this was a classic case of procurement expertise being bypassed. The procurement department at the Scottish Office was not involved in the project. It was

not consulted over the procurement model.
There is nothing wrong with construction management as a procurement route. It is

best suited to high-quality, potentially high-cost projects, where the client is fully engaged, has a clear goal and works closely with the supply side team.

Some estimates put the money lost to delays and backtracking over design changes at as much as £100 million. If one trade contractor has a problem, it tends to ripple through all the others and cause delay and changes. The contracts are with the client, so the client picks up the cost of that.

However, between the extremes of fixed speedy construction management, a host of options exist under the heading of ‘conventional’ procurement. Their structures affect the risk and control over the final design that falls to the client.

The ‘design and build’ route would have seen the project management team drawing up a detailed design brief, which the main contractor then builds. It leaves the contractor footing the bill for cost overruns, but freezes the design as well.

A middle-of-the-road option, prime contracting, keeps design more open, but cuts the risk of costs going up if things go wrong. This is because a contractor joins the client’s project management team, and brings its entire supply chain of proven builders and suppliers along.

Then there is management contracting, where the client retains the design brief fully and splits up the project into small packages to be individually let, as in construction management. However, a professional intermediary runs all of the contractors on a daily basis, although they are still contracted to the client, which pays for design alterations.

Management contracting may, it seems, have given a more stable framework to the project by introducing an industry expert to run the many contractors.

Construction management was not the most suitable procurement vehicle. Sir Michael Latham, whose influential 1994 report, ‘Constructing the Team’, called on the construction industry to move towards partnering in the supply chain, says that full partnering should have been used to share the risk between client and contractor.

Solutions

Expert Solution

1) In the given case the obtainment model utilized was development the executives. This included separating of the general task into littler undertakings which were totally regarded autonomous of one another as an independent units. Anyway the choices were taken by the individual venture groups and focal acquirement was not a piece of the decision making process.

2) The wide procedure followed was the separation of the structure venture into a few little individual bundles which were managed autonomously. Fundamentally the structure likewise implied that as a major aspect of the procedure a focal acquisition group was not counseled in choosing exchange contracts.

3) The acquisition group not being counseled on exchange choices implies that their skill as far as haggling better expenses was not used by any means. This brought about task costs swelling from 40 MM to practically 11x of that at 431 MM in 2004 when undertaking was finished. Additionally, the utilization of development the board system inferred that structure changes were excessively continuous and this brought about exorbitant deferrals of more than 3 years.

4) Improvements to take a gander at would stand out contracting is completed. Its embodiment is to have more noteworthy command over the undertaking even while separating autonomous errands. The ways to deal with be utilized could be a blend of prime contracting which use the contractual worker's stockpile group by making the temporary worker a piece of the undertaking supervisory group; and the executives contracting, where an expert middle person arranges with the contractual workers of the autonomous units - much like a CEO capacities with an initiative group.


Related Solutions

Analyze how deontology would inform the conduct the healthcare professional involved in the case study.
Janine works as palliative care nurse at a regional health facility and relates the following conundrum. Janine describes looking after Jack who recently returned to the palliative care service after a further unexpected exacerbation of his respiratory lung cancer. Jack is rapidly deteriorating with little tolerance for any activity and cannot undertake any activities of daily living. Shirley, his wife is constantly at his side offering as much support as possible. Jack is highly dependent and has several HCP ‘s...
i have a case study : a case study of HP. subject : managing diversity at...
i have a case study : a case study of HP. subject : managing diversity at workplace please answer those two questions : a) what is meant by diversity and what are the different diemensions of diversity mentioned in the case study. (explain with example) b) what are the challenges faced in diversity management? How has HP successfully managed diversity? please visit this websites to read the case study: https://papers.ssrn.com/sol3/papers.cfm?abstract_id=1944511
Read and review chapter 31 Analyze the following case study and answer the question bellow CASE...
Read and review chapter 31 Analyze the following case study and answer the question bellow CASE STUDY Mrs. Angstrom is an 83-year-old patient who was admitted to the hospital after she fell outside her home and broke her hip. She has been living alone in her apartment since her husband died 4 years ago. Mrs. Angstrom has no long-term history of mental illness, but she has recently shown signs of cognitive impairment and dementia, according to her neighbor Jeanine Finch,...
There is not a case study involved with this question. This is my second attempt to...
There is not a case study involved with this question. This is my second attempt to have this question answered. This question is in reference to the healthcare industry. Briefly describe what happens to each of the following as volume increases. Assume all values stay within their relevant range. Total fixed cost? Total variable cost? Fixed cost per unit? Variable cost per unit? Explain the relationship between step-fixed costs and the relevant range. References would be a bonus! This question...
Read the following case study carefully and analyze it by answering the three Questions for Discussion.   ...
Read the following case study carefully and analyze it by answering the three Questions for Discussion.    Hot-Shot Pix is a global digital camera manufacturer headquartered in the U.S.  The company designs, manufacturers and sells various digital camera models at different price points through various channels.  Design is carried out at the company’s R&D labs located in England and the U.S.  The company manufactures cameras at four different locations:  one factory is located in Singapore and supplies the Asia-Pacific region; another factory is located in...
Please give creative examples for each system for the following case study. Case study: Your grandpa...
Please give creative examples for each system for the following case study. Case study: Your grandpa has been diagnosed with high blood pressure. It’s serious (if he wants to be healthy), and he needs to take medicine, as well as modify his diet to reduce the amount of sodium he eats (and ideally, cut back on his alcohol). What are the variable/factors that may make it hard for him to follow these guidelines? What are variables/factors that might make it...
please nswer Case Study Exercises 1, 2, and 5 CASE STUDY INFLATION CONSIDERATIONS FOR STOCK AND...
please nswer Case Study Exercises 1, 2, and 5 CASE STUDY INFLATION CONSIDERATIONS FOR STOCK AND BOND INVESTMENTS Background The savings and investments that an individual maintains should have some balance between equity (corporate stocks that rely on market growth and dividend income) and fixed-income investments (bonds that pay dividends to the purchaser and a guaranteed amount upon maturity). When inflation is moderately high, bonds offer a low return relative to stocks because the potential for market growth is not...
1. Medical clearance and risk stratification case study practice. Please carefully read the following case studies,...
1. Medical clearance and risk stratification case study practice. Please carefully read the following case studies, answer the questions and ultimately determine the need for medical clearance and appropriate risk stratification. A. Joe is a 49 years old male who stands tall at 5’11” andweighs 240 pounds. He currently smokes one half pack ofcigarettes a day and indicates no history of regular physicalactivity over the past 10 years. He also has a sedentaryoccupation and travels frequently for work. His latestphysical...
For each case study, discuss the ethics involved in the study using the ethical framework presented...
For each case study, discuss the ethics involved in the study using the ethical framework presented in your reading. Case No. 1: A developmental psychologist is conducting research on physiological correlates of orienting responses in newborn infants. What is his obligation with respect to sharing each child's data with the child's parents? Does it make a difference if the data suggest the presence of neurological abnormality in some participants? Case No. 2: A local business is interested in making better...
Analyze the following procurement documents. Include the key characteristics of each document, and explain the differences...
Analyze the following procurement documents. Include the key characteristics of each document, and explain the differences between a statement of work and a request for proposal. Request for Quotation (RFQ). Request for Information (RFI). Request for Proposal (RFP). Statement of Work (SOW). Identify the appropriate application of each of these procurement documents. Consider the purpose and characteristics of the various documents. Describe how you would justify your selection of any particular document.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT