In: Operations Management
Use the information below to work the problems in this section.
Develop a master production schedule.
Answer: steps for MPS
step 1 | IOH= | PIOH of last week | |
step 2 | Requirement= | GR+SS-IOH | CO will be taken instead of GR when CO>GR |
step 3 | NR= | is equal to requirement (if requirement>0) OR 0 (if requirement is negative) | |
step 4 | MPS= | more than or equal to NR in multiples of lot size | |
step 5 | PIOH= | IOH+MPS-GR | CO will be taken instead of GR when CO>GR |
MPS
safety stock SS= | 0 | |||||||
Q = lot size= | 150 | |||||||
beginning inventory= | 0 | |||||||
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements GR | 50 | 50 | 50 | 50 | 75 | 75 | 75 | 75 |
Customer orders CO | 50 | 38 | 22 | 18 | 6 | 2 | 0 | 0 |
inventory on hand IOH | 0 | 100 | 50 | 0 | 100 | 25 | 100 | 25 |
Requirement | 50 | -50 | 0 | 50 | -25 | 50 | -25 | 50 |
Net requirements NR | 50 | 0 | 0 | 50 | 0 | 50 | 0 | 50 |
Master production schedule MPS | 150 | 0 | 0 | 150 | 0 | 150 | 0 | 150 |
Projected on hand inventory POHI | 100 | 50 | 0 | 100 | 25 | 100 | 25 | 100 |