Question

In: Civil Engineering

develop a sample of Scope of Work for constructing a steel-structure chalet

develop a sample of Scope of Work for constructing a steel-structure chalet

Solutions

Expert Solution

SAMPLE OF SCOPE OF WORK FOR CONSTRUCTION OF STEEL STRUCTURE CHARLET.

DESCRIPTION OF WORK

Sl.

No.

Task Code

Task Description

Frequency

UNIT

Rate (Rs.)

Total Basic Price(Rs.)

Completion Period (Days)

1

24.8.7

Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.

50000

kg

100

500000

365

2

14.54.1

Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade :One or more coats

on old work

12500

Sqm

51.2700

640875.0

0

365

3

13.50.3

Applying priming coat :With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works

3000

Sqm

28.5400

85620.00

365

4

5 and so on…..

Total Basic Price of all Tasks:- Rs.10000000 (Rs Ten million)only.

TERMS AND CONDITIONS

PRICE BASIS: Firm till execution of the contract.

COMMERCIAL TERMS: Taxes and Duties will be paid extra as applicable as per the prevailing rates and other charges as follows :

Commercial Terms Description

Task Description

Government Tax @18 (Present applicable rate 18% )

For All Tasks

PAYMENT TERMS:

Payment Terms Description

Task Description

90% of contract price shall be paid against Running Account bills after satisfactory completion of work and certified by Engineer-in-charge of Client.

10% shall be retained by Client as Security Deposit and will be released after the expiry of Guarantee/Warranty Period.

For All Tasks

LD CLAUSE:

(i) Client reserves the right to recover a sum equivalent to 0.5% of the delayed work for each week of delay or part thereof subject to maximum of 5% of the total value of the order as Liquidated Damage due to delay in completion of work attributable to the contractor.

Contract Period : 365 days from the date of commencement of work.

SAFETY

The contractors shall provide necessary safety equipment to the workers at the site at his own cost. The contractor shall be solely and wholly responsible for any accident that may occur during execution of the work and also for injury to person/persons or damage to the property of any description whatsoever has caused during the execution of the work. In the event of any such

Accident, the contractor shall be responsible and shall pay proper compensation for the same as per Workmen compensation Act. CLIENT IN NO WAY SHALL BE RESPONSIBLE FOR SAFETY OF THE CONTRACTORS WORKMEN.

EPF & ESI

No payment will be done without clearance of EPF &ESI from CLIENT.

TERMINATION

If work will not be done as per specification then contractor may be terminated.

CONTROLLING OFFICER

Engineer in charge or his representative will be controlling officer for this work.

AGREEMENT

You are requested to execute an Indemnity Bond on a Non-Judicial Stamp paper of Rs. 20/- and thereafter to execute an agreement in Client form with a Non-Judicial Stamp of appropriate value within 30 days from the date of issuance of work order.

Please note that no payment will be made before execution of the agreement

  GUARANTY/WARRANTY

Guarantee /warranty period will be six months after completion of job.

PAYING AUTHORITY: Senior Manager (Finance) of Client .

Structural Steel Requirements:

All structural steel members are to be true and straight, manufactured too industry standards .

All elevation surveying during steel erection installation by Contractors to indicated plan elevations.

All steel and accessories installed will be as specified above to approved plan.

All structural steel will be verified prior to installation of members.

All scaffolding being utilize will be of an acceptable required quality.

Erection of Column and Beams :

Erect all columns and beams as per the approved plans to the specified dimensional distances and elevations.

- Installation of all lower parking unit structural steel, lobby area structural steel and corner columns as per standard specification.

WORKING HOURS

Normal working hours are (5 days ) ten hour daily (Monday to Friday) or as directed by the Engineer in charge.

Note- (i) Indian currency has been used for this sample.

          (ii)You may prepare on the basis of your country currenc

    (iii)Applicable rate of taxes is different for every country.


Related Solutions

Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should...
Develop a work breakdown structure for an iPhone with expandable storage. Your work breakdown structure should include at least three tasks with at least three subtasks each.
In Defining Project(Scope) : 1 -what are Scope statement and Statement of work 2 - explain...
In Defining Project(Scope) : 1 -what are Scope statement and Statement of work 2 - explain what are WBS/OBS 3 - Project Responsibility Matrix ? 4 - what Project Priority Matrix ? 5 - What / how Communication Plan ?
reinforced concrete structure the roles of concrete and steel.
reinforced concrete structure the roles of concrete and steel.
briefly comment on the application of geotechnical engineering in constructing the gigantic structure on the Arabian...
briefly comment on the application of geotechnical engineering in constructing the gigantic structure on the Arabian gulf
what concrete components does the scope of the concrete work include
what concrete components does the scope of the concrete work include
Demonstrate your grasp of the Unix file system by constructing a directory structure as follows: In...
Demonstrate your grasp of the Unix file system by constructing a directory structure as follows: In your home ( ~ ) directory, create a directory named “UnixCourse”. This directory will be used in the remaining assignments of this course, as well as this one. Several of the commands that you will issue in this course will examine files in this directory and, in some cases, send me a listing of those files or even copies of those files for grading...
Project Scope Management Questions Only On a project to develop an inventory control system, the project...
Project Scope Management Questions Only On a project to develop an inventory control system, the project manager is working on creating the scope management plan. He realizes that this plan must include items such as how the WBS will be created and how the scope of work will be accomplished and measured. All of the following statements are true about the scope management plan except: A. It will not change after approval. B. It may be based on organizational forms...
What would be the project scope ? We have been hired to develop a sales training...
What would be the project scope ? We have been hired to develop a sales training course for 250 sales associates that will be working the floor of an electronics shop. This will be our first endeavor in retail training, sowe must adapt one of our existing training models and customize it to meet the needs of the customer. The company’s electronic shop department has a high volume of sales. As a result they need to develop a training course...
should a country develop a new market structure?
should a country develop a new market structure?
Case Study – 4 Awtab Steel Structure LLC, is one of the leading "Pre-Engineered Steel Building...
Case Study – 4 Awtab Steel Structure LLC, is one of the leading "Pre-Engineered Steel Building Company" in Sultanate of Oman. The Company uses latest automatic equipment in plant to produce better steel buildings for the clients. The Company received a special Pre- Engineered Steel Building project from a customer and the cost accountant provided the following cost estimates for fixing the price of the project. Direct Materials : Steel Frames @ RO 2000 per Kg Metal Roof Sheets @...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT