Question

In: Finance

The executives of Garner-Wagner Inc. are considering a project that will cost $85 million. The cost...

The executives of Garner-Wagner Inc. are considering a project that will cost $85 million. The cost of capital for this type of project is 10 percent and the risk-free rate is 5 percent. There is a 50 percent chance of high demand, with future cash flows of $50 million per year for 3 years. There is a 40 percent chance of average demand, with cash flows of $30 million per year for 3 years. If demand is low (a 10 percent chance), cash flows will be only $20 per year for 3 years

a. What is the expected NPV?

b. If Garner-Wagner Inc makes the investment today, then it will have the option to replicate the project at the end of project life if the demand is high. The cash flow will be repeated (i.e., the demand will continue to be high).

Use decision-tree analysis to calculate the expected NPV of this project, including the option to replicate.

c. If Garner-Wagner Inc wants to use Black-Sholes formula to estimate the value of this real option, What would be the value of P in the Blacksholes formula?

d. Estimate the variance in the Black-Sholes formula.

Solutions

Expert Solution

No of Years Nature of Demand Probability Quantity of Cash Flow PV factor for 10% of expected return
1 50% of High 0.50 $50 Millions 0.909
2 50% of High 0.50 $50 Millions 0.826
3 50% of High 0.50 $50 Millions 0.751
4 40% of High 0.40 $30 Millions 0.683
5 40% of high 0.40 $30 Millions 0.621
6 40% of high 0.40 $30 Millions 0.564
7 10%of High 0.10 $ 20 Millions 0.513
8 10% of high 0.10 $20 Millions 0.467
9 10% of high 0.10 $20 Millions 0.424

Cost of Capital(Ke) = 10% and Risk free return (Rf) = 5%

1) Total Years cash flow= 0.50(50)+0.50(50)+ 0.50(50)+0.40(30)+0.40(30)+0.40(30)+0.10(20)+0.10(20)+0.10(20)

Present value of cash flows =25(0.909)+25(0.826)+25(0.751)+12(0.683)+12(0.621)+12(0.564)+2(0.513)+2(0.467)+2(0.424)

= 22.725+20.65+18.775+8.196+7.452+6.768+1.026+0.934+0.848

=$87.374

Expected NPV= Expected Cash flow - Initial Outlay= $87.374-$85= $2.347

2) Risk free rate of return is


Related Solutions

QUESTION 11 Garner-Wagner Manufacturing Inc. is considering some new equipment whose data are shown below. The...
QUESTION 11 Garner-Wagner Manufacturing Inc. is considering some new equipment whose data are shown below. The equipment has a 3-year tax life and would be fully depreciated by the straight-line method over 3 years, but it would have a positive pre-tax salvage value at the end of Year 3, when the project would be closed down. Also, some new working capital would be required, but it would be recovered at the end of the project's life. Revenues and other operating...
ABC Inc. is considering a project that will cost $60 million. The cost of capital for...
ABC Inc. is considering a project that will cost $60 million. The cost of capital for this type of project is 10%, and the risk-free rate is 6%. The project will generate the following cash flows every year for the next two years. Assume that there is a 30% chance of high demand with associated future cash flows of $45 million per year. There is also a 40% chance of average demand with cash flows of $30 million per year...
1. Hiram Finnegan Inc. is considering a capital investment project. This project will cost $10 million...
1. Hiram Finnegan Inc. is considering a capital investment project. This project will cost $10 million today. Managers expect that net cash flows will be $15 million at the end of year 1 and $40 million at the end of year 2. After year 2, the project will be finished. The appropriate annual discount rate for projects of this risk is 12% per year. What is the net present value of this project? Should the firm accept this project? (Choose...
Beta Industries is considering a project with an initial cost of $6.9 million. The project will...
Beta Industries is considering a project with an initial cost of $6.9 million. The project will produce cash inflows of $1.52 million a year for seven years. The firm uses the subjective approach to assign discount rates to projects. For this project, the subjective adjustment is +2.2 percent. The firm has a pretax cost of debt of 9.1 percent and a cost of equity of 17.7 percent. The debt-equity ratio is .57 and the tax rate is 34 percent. What...
Alpha Industries is considering a project with an initial cost of $8.1 million. The project will...
Alpha Industries is considering a project with an initial cost of $8.1 million. The project will produce cash inflows of $1.46 million per year for 9 years. The project has the same risk as the firm. the firm has a pretax cost of debt of 5.64% and a cost of equity of 11.29%. The debt-equity ratio is .61 and the tax rate is 39 percent. A. Should the Firm accept the project? B.Calculate the Firms WACC
Alpha Industries is considering a project with an initial cost of $7.5 million. The project will...
Alpha Industries is considering a project with an initial cost of $7.5 million. The project will produce cash inflows of $1.55 million per year for 7 years. The project has the same risk as the firm. The firm has a pretax cost of debt of 5.46 percent and a cost of equity of 11.17 percent. The debt–equity ratio is .55 and the tax rate is 39 percent. What is the net present value of the project? $263,559 $482,364 $463,811 $397,552...
Alpha Industries is considering a project with an initial cost of $8.2 million. The project will...
Alpha Industries is considering a project with an initial cost of $8.2 million. The project will produce cash inflows of $1.93 million per year for 6 years. The project has the same risk as the firm. The firm has a pretax cost of debt of 5.67% and a cost of equity of 11.31%. The debt-equity ratio is 0.62 and the tax rate is 40%. What is the net present value of the project? Hint: You'll need to calculate the appropriate...
Heinlein Inc is considering investing in a project with a cost of $100k. The project is...
Heinlein Inc is considering investing in a project with a cost of $100k. The project is expected to produce cash flows of $50 in year 1, 80 in year 2, and 215 in year 3. If the discount rate is 0.09 what is the discounted payback period.  
Your firm is considering a project that will cost $3 million in initial investments. The project...
Your firm is considering a project that will cost $3 million in initial investments. The project will earn cash flows of $750,000 for 6 years then terminate with no salvage value. If the WACC is 8%, what is the Net Present Value of the investment? $467,160 $487,993 $472,627 $503,679 A project calls for $5.5 million in initial investments. The project will return the following cash flows. What is the modified IRR if the WACC of 7% is applied as the...
Q 28 Your company is considering an expansion project that will cost $1.5 million. The project...
Q 28 Your company is considering an expansion project that will cost $1.5 million. The project will generate after-tax cash flows of $175,000 per year for 6 years. Your company is expected to pay an annual dividend in the amount of $2.50 per share next year and the current price of share is $15. The dividend growth rate is 2.5%. The bonds carry an 8 percent coupon, pay interest annually, and mature in 4 years. The bonds are selling at...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT