In: Finance
Your company has a project available with the following cash flows: Year Cash Flow 0 −$81,100 1 21,500 2 25,000 3 30,800 4 26,000 5 19,800 If the required return is 14 percent, should the project be accepted based on the IRR?
Internal Rate of Return (IRR) for the Project
Step – 1, Firstly calculate NPV at a guessed discount Rate, Say 15% (R1)
Year |
Annual Cash Flow ($) |
Present Value factor at 15% |
Present Value of Cash Flow ($) |
1 |
21,500 |
0.869565 |
18,695.65 |
2 |
25,000 |
0.756144 |
18,903.59 |
3 |
30,800 |
0.657516 |
20,251.50 |
4 |
26,000 |
0.571753 |
14,865.58 |
5 |
19,800 |
0.497177 |
9,844.10 |
TOTAL |
82,560.43 |
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $82,560.43 - $81,100
= $1,640.43
Step – 2, NPV at 15% is positive, Calculate the NPV again at a higher discount rate, Say 16% (R2)
Year |
Annual Cash Flow ($) |
Present Value factor at 16% |
Present Value of Cash Flow ($) |
1 |
21,500 |
0.862069 |
18,534.48 |
2 |
25,000 |
0.743163 |
18,579.07 |
3 |
30,800 |
0.640658 |
19,732.26 |
4 |
26,000 |
0.552291 |
14,359.57 |
5 |
19,800 |
0.476113 |
9,427.04 |
TOTAL |
80,632.42 |
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $80,632.42 - $81,100
= -$467.58 (Negative NPV)
Therefore IRR = R1 + NPV1(R2-R1)
NPV1-NPV2
= 0.15 + [$1,460.43 x (0.16 – 0.15)]
$1,460.43 – (-$467.58)
= 0.15 + [$14.60 / $1,928.01]
= 0.15 + 0.0076
= 0.1576 or
= 15.76%
“Internal Rate of Return (IRR) for the Project = 15.76%”
DECISION
“YES”. The Project should be accepted, since the Internal Rate of Return for the Project (15.76%) is greater than the Required Rate of Return (14%) of the Project
NOTE
The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.