In: Finance
A project that costs $2,800 to install will provide annual cash flows of $630 for the next 6 years. The firm accepts projects with payback periods of less than 4 years. |
a-1. | What is this project's payback period? (Round your answer to 3 decimal places.) |
Payback period | years |
a-2. | Will the project be accepted? | ||||
|
b-1. |
What is project NPV if the discount rate is 2%? (Do not round intermediate calculations. Round your answer to 2 decimal places.) |
NPV | $ |
b-2. | Should this project be pursued? | ||||
|
b-3. |
What is project NPV if the discount rate is 12%? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) |
NPV | $ |
b-4. | Should this project be pursued? | ||||
|
b-5. | Will the firm’s decision change as the discount rate changes? |
Answer a-1.
Payback Period = Initial Investment / Annual Cash Flows
Payback Period = $2,800 / $630
Payback Period = 4.444 years
Answer a-2.
The firm accepts projects with payback periods of less than 4 years. So, the firm should not accept this project.
Answer b-1.
Discount Rate = 2%
NPV = -$2,800 + $630/1.02 + $630/1.02^2 + $630/1.02^3 +
$630/1.02^4 + $630/1.02^5 + $630/1.02^6
NPV = -$2,800 + $630 * (1 - (1/1.02)^6) / 0.02
NPV = -$2,800 + $630 * 5.601431
NPV = $728.90
Answer b-2.
The NPV of the project is positive. So, the firm should accept this project.
Answer b-3.
Discount Rate = 12%
NPV = -$2,800 + $630/1.12 + $630/1.12^2 + $630/1.12^3 +
$630/1.12^4 + $630/1.12^5 + $630/1.12^6
NPV = -$2,800 + $630 * (1 - (1/1.12)^6) / 0.12
NPV = -$2,800 + $630 * 4.111407
NPV = -$209.81
Answer b-4.
The NPV of the project is negative. So, the firm should not accept this project.
Answer b-5.
Yes, the firm’s decision will change as the discount rate changes.