In: Finance
The correct answer is option D ie. - the project’s npv must be positive.
A- the project’s required rate of return must be greater than 7.25%. - Incorrect
The required rate of return is the weighed average cost of capital which is 6.67%
Particulars | Weight | Cost | Weight x Cost |
Debt/Bonds | 33.33% | 4.00% | 1.33% |
Preffered stock | 33.33% | 7.00% | 2.33% |
Common stock | 33.33% | 9.00% | 3.00% |
Cost of capital | 6.67% |
Thus statement A is incorrect.
B- the project’s net present value (npv) must be $0. -Incorrect
Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive
C- the project’s npv must be negative.-Incorrect
Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive
D- the project’s npv must be positive.-Correct
Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive
E- there is insufficient information to assess either the required rate or the npv of the project.-Incorrect
Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive
Thumbs up Please! Thank You