Question

In: Finance

sparta corp. has a prospective project with an irr of 7.25%. its cost of preferred equity,...

sparta corp. has a prospective project with an irr of 7.25%. its cost of preferred equity, cost of common equity, and post-tax cost of debt are 7%, 9%, and 4%, respectively, and sparta raises equal amounts of funding from all these three sources. choose the best statement:

A- the project’s required rate of return must be greater than 7.25%.
B- the project’s net present value (npv) must be $0.
C- the project’s npv must be negative.
D- the project’s npv must be positive.
E- there is insufficient information to assess either the required rate or the npv of the project.

Solutions

Expert Solution

The correct answer is option D ie. - the project’s npv must be positive.

A- the project’s required rate of return must be greater than 7.25%. - Incorrect

The required rate of return is the weighed average cost of capital which is 6.67%

Particulars Weight Cost Weight x Cost
Debt/Bonds 33.33% 4.00% 1.33%
Preffered stock 33.33% 7.00% 2.33%
Common stock 33.33% 9.00% 3.00%
Cost of capital 6.67%

Thus statement A is incorrect.

B- the project’s net present value (npv) must be $0. -Incorrect

Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive

C- the project’s npv must be negative.-Incorrect

Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive

D- the project’s npv must be positive.-Correct

Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive

E- there is insufficient information to assess either the required rate or the npv of the project.-Incorrect

Since, IRR is the rate at which NPV is zero, and required rate is 6.67% so NPV must be postive

Thumbs up Please! Thank You


Related Solutions

1. a. Calculate the IRR for the following project if its cost was $5,000 and the...
1. a. Calculate the IRR for the following project if its cost was $5,000 and the annual expenditures and costs were: Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 2,000 2,000 2,000 2,000 -1,000 -1,000 b. Assume a firm's WACC is 10 percent. Calculate the NPV for the following project if its cost was $5,000 and the annual expenditures and costs were: Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 2,000 2,000...
A firm has a cost of equity of 13 percent, a cost of preferred of 5...
A firm has a cost of equity of 13 percent, a cost of preferred of 5 percent, an after-tax cost of debt of 3.4 percent and a tax rate of 21%. Given this, which of the following will increase the firm’s weighted average cost of capital? Increase the firm’s tax rate Issuing new bonds at par Increasing the firm’s beta Increasing the debt/equity ratio
a)Compute the Internal Rate of Return (IRR) of the prospective project: Estimated cash flows are $18,200...
a)Compute the Internal Rate of Return (IRR) of the prospective project: Estimated cash flows are $18,200 at the end of every year for 6 years. Cost today is $67,000. b) Should the company accept the project if the company's cost of capital is 7%, and why or why not? Please show all work using the TI BAII Plus Calculator like the example below: Make sure that 2nd I/Y which is P/Y is set to 1.0. Make sure that 2nd PMT...
Safeassign Corp. has a debt to equity ratio of .85. Its Weighted average cost of capital...
Safeassign Corp. has a debt to equity ratio of .85. Its Weighted average cost of capital is 9.9% and the tax rate is 35%. If Safeassign’s after-tax cost of debt is 6.8%, what is the cost of equity? ii. Safeassign Corp. has a debt to equity ratio of .85. Its Weighted average cost of capital is 9.9% and the tax rate is 35%. If Safeassign’s cost of equity is 14% what is the pre-tax cost of debt? iii. Safegaurd Inc....
what is the IRR for the following project if its initial after tax cost is $5000000...
what is the IRR for the following project if its initial after tax cost is $5000000 and it is expected to provide after tax operating cash inflows of $1800000 in yr 1, $1750000 in yr 2, $1680000 in yr 3 and $1300000 in yr 4?
Nipigon Manufacturing has a cost of debt of 7 %, a cost of equity of 12%, and a cost of preferred stock of 9%.
Nipigon Manufacturing has a cost of debt of 7 %, a cost of equity of 12%, and a cost of preferred stock of 9%. Nipigon currently has 130,000 shares of common stock outstanding at a market price of $25 per share. There are 48,000 shares of preferred stock outstanding at a market price of $38 a share. The bond issue has a face value of $950,000 and a market quote of 104. The company’s tax rate is 35%.Required:Calculate the weighted...
Suppose that XYZ Corp is considering financing a project with only equity. The project’s unlevered cost...
Suppose that XYZ Corp is considering financing a project with only equity. The project’s unlevered cost of capital is 10%. The project will require a $1000 initial investment today and pay incremental free-cash-flows of $100 in perpetuity starting the end of the next year. If the firm were to finance the project with debt so that its D/E ratio is 0.50 how will the NPV of the project change? Assume the interest rate on the new debt will be 3%,...
Suppose that XYZ Corp is considering financing a project with only equity. The project’s unlevered cost...
Suppose that XYZ Corp is considering financing a project with only equity. The project’s unlevered cost of capital is 10%. The project will require a $1000 initial investment today and pay incremental free-cash-flows of $100 in perpetuity starting the end of the next year. If the firm were to finance the project with debt so that its D/E ratio is 0.50 how will the NPV of the project change? Assume the interest rate on the new debt will be 3%,...
7. Prego Corp. has a target capital structure of 30% debt, 60% common equity, and preferred...
7. Prego Corp. has a target capital structure of 30% debt, 60% common equity, and preferred stock of 10%. The yield to maturity on the company’s outstanding bonds is 9%, and its tax rate is 21%. The cost of preferred stock is 5%. Prego’s CFO estimates that the company’s WACC is 9.96%. What is Prego’s cost of equity? 8. If the total capital structure is $90,000,000 and the debt to equity ratio is 50%, what is the dollar amount of...
Capital component weights, cost of debt, cost of preferred stock, and cost of common equity.
Capital component weights, cost of debt, cost of preferred stock, and cost of common equity. Be sure to use 4 decimal places. Current assets: 3,100 Property, plant and equipment: 3,400 Total assets: 6,500. Current liablities: 1,500 Long term debt: 1,750 Preferred stock, $100 par: 500 Common stock, no par: 1,250 Retained earnings: 1,500 Total liabilities and equities: 6,500 Growth rate 7.5% Coupon on new bonds: 7.75% Corporate tax rate: 25% Dividend on preferred: 8% Price of common stock: $24.00 Price...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT