Question

In: Finance

1. project initial cost (incurred at beginning of year 1) Project life Salvage value Positive annual...

1.

project initial cost (incurred at beginning of year 1) Project life Salvage value Positive annual cash flow (received at the end of each year)
A $200000 16 years $0 $28000
B $56000 14 years $0 $9783

B is higher than the Internal Rate of Return of project A.

Required:

A) Is the NPV for Project A higher than, equal to, or lower than, the NPV for Project

B, assuming a 10% discount rate?

B) Is the Payback Period for Project A better than, equal to, or worse than, the

Payback Period for Project B?

C) Is the Accounting Rate of Return for Project A higher than, equal to, or lower

than, the Accounting Rate of Return for Project B, assuming straight-line

depreciation?

D) If the discount rate is 11% instead of 10%, which project has the higher NPV?

E) If the discount rate is 10%, and both projects have a salvage value of $66,000

(i.e., the equipment for Project B actually appreciates), which project would have

the higher NPV?

2.: A merchandising company expects to sell 300 units in April, 400 units in May, and

500 units in June. The company plans to have 30% of each month’s sales, plus an

additional 50 units, on hand in inventory at the beginning of each month. How many

units should the company plan to purchase in May?

Solutions

Expert Solution

A) Statement showing NPV

Particular Project A Project B
Annual cash flow 28000 9783
PVIFA(10%,16 years) 7.8237
PVIFA(10%,14 years) 7.3667
Present value of cash inflow 219064 72068
Initial cost 200000 56000
NPV 19064 16068

Thus project A has higher NPV

B) Payback period

Particular Project A Project B
Initial cost 200000 56000
Annual cash flow 28000 9783
Payback peiod(initial investment/annual cash flow) 7.14 5.72

Thus payback period of project B is less than that of A

C) Accounting return

Particular Project A Project B
Annual cash flow 28000 9783
Less: Depreciation 12500 4000
Profit 15500.00 5783.00
Initial cost 200000 56000
Accounting rate of return(profit/initial cost) 7.75% 10.33%

B has higher accounting rate of return

D) Statement showing NPV where r = 11%

Particular Project A Project B
Annual cash flow 28000 9783
PVIFA(11%,16 years) 7.379
PVIFA(11%,14 years) 6.9818
Present value of cash inflow 206615 68303
Initial cost 200000 56000
NPV 6615 12303

Thus project B should be selected

E) Statement showing NPV

Particular Project A Project B
Annual cash flow 28000 9783
PVIFA(10%,16 years) 7.8237
PVIFA(10%,14 years) 7.3667
Present value of cash inflow 219064 72068
Add: PV Salvage value
66000*PVIF(10%16th year) 14362
66000*PVIF(10%14th year) 17380
Total cash inflow 233425 89448
Initial cost 200000 56000
NPV 33425 33448

Project B has higher NPV

2) Units to be purchased = (400*70%) - 50

=280-50

230 units


Related Solutions

Pump A Initial Cost: 7000 Salvage Value:1200 Useful Life:12 Pump B Initial Cost: 5000 Salvage Value:...
Pump A Initial Cost: 7000 Salvage Value:1200 Useful Life:12 Pump B Initial Cost: 5000 Salvage Value: 1000 Useful Life: 6 Two pumps are being considered for purchase. If interest is 9%, which pump should be bought?
Given an asset with initial cost of $20,000, useful life of 5 years, salvage value =...
Given an asset with initial cost of $20,000, useful life of 5 years, salvage value = 0, find the depreciation allowances and the book values using the    a. Straight-Line Method b. MACRS
A project has a first cost P, annual savings A and a salvage value of $500...
A project has a first cost P, annual savings A and a salvage value of $500 at the end of its 10-year service life. It is also known that the IRR for this project is 11 %, and the payback period is 8 years. What is the project's first cost? (Don't use the $ sign and coma in your answer!)
Consider a project with a 6-year life. The initial cost to set up the project is...
Consider a project with a 6-year life. The initial cost to set up the project is $450,000. This amount is to be linearly depreciated to zero over the life of the project. The firm expects to be able to sell the equipment for $90,000 after 6 years. The price per unit is $380, variable costs are $304 per unit and fixed costs are $45,000 per year. The project has a required return of 12% and a tax rate of 28%....
Consider a project with a 6-year life. The initial cost to set up the project is...
Consider a project with a 6-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 6 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 63,000 units per year at a price of $160 each. The...
Consider a project with a 4-year life. The initial cost to set up the project is...
Consider a project with a 4-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 4 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 52,000 units per year at a price of $177 each. The...
Consider a project with a 4-year life. The initial cost to set up the project is...
Consider a project with a 4-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 4 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 52,000 units per year at a price of $177 each. The...
Consider a project with a 4-year life. The initial cost to set up the project is...
Consider a project with a 4-year life. The initial cost to set up the project is $1,200,000. This amount is to be linearly depreciated to zero over the life of the project. You expect to sell the equipment for $240,000 after 4 years. The project requires an initial investment in net working capital of $120,000, which will be recouped at the end of the project. You estimated sales of 77,000 units per year at a price of $137 each. The...
Consider a project with a 5-year life. The initial cost to set up the project is...
Consider a project with a 5-year life. The initial cost to set up the project is $100,000. This amount is to be linearly depreciated to zero over the life of the project and there is no salvage value. The required return is 13% and the tax rate is 34%. You've collected the following estimates: Base case Pessimistic Optimistic Unit sales per year (Q) 8,000 6,000 10,000 Price per unit (P) 50 40 60 Variable cost per unit (VC) 20 35...
Cost $75,000; Salvage value: $10,000; Useful life: 10 Calculate annual depreciation on this machi... Cost $80,000;...
Cost $75,000; Salvage value: $10,000; Useful life: 10 Calculate annual depreciation on this machi... Cost $80,000; Salvage value: $10,000; Useful life: 10 Calculate annual depreciation on this machinery using doublr-declining balance method. Be careful not to exceed the salvage value. If the salvage value is zero, switch to straightline in the year when straight-line yields higher depreciation. (use the remaining valye as the starting point when you change)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT