Question

In: Finance

A city has identified two options for developing solar power capacity. The investment basis for comparison...

A city has identified two options for developing solar power capacity. The investment basis for comparison is 8 years, with interest fixed at 12% per year.

Option A is to build a photovoltaic array at 50% capacity now, at a cost of $1 million, with an operating cost of $200,000 at the end of each year for 4 years. At the end of year 4, the array will be expanded to 100% capacity, at a cost of $900,000. After the expansion, operating costs will become $350,000 per year.

Option B is to build a full-scale solar thermal electric generation plant now at a cost of $1.5 million, with end-of-year operating costs of $250,000.

Which option should be chosen?

Solutions

Expert Solution

To decide the option, we need to calculate the Present Value (PV) of all costs for each option.

Option A: Operating cost (1st 4 years) = 200,000

PV of Op.cost: PMT = 200,000; N = 4; rate = 12%, CPT. PV = 607,469.87

Operating cost (2nd 4 years) = 350,000

PV of Op.cost at the end of 4 years: PMT = 350,000; N = 4; rate = 12%, CPT PV.

PV = 1,063,072.27

PV of this cost today = 1,063,072.27/(1+12%)^4 = 675,601.65

Total PV of operating costs over 8 years = 607,469.87 + 675,601.65 = 1,283,071.52

PV of expansion cost in 4 years = 900,000/(1+12%)^4 = 324,549.02

Total PV of costs = initial cost + PV of operating costs + PV of expansion cost

= 1,000,000 + 1,283,071.52 + 324,549.02 = 2,607,620.54

Option B: PV of operating costs over 8 years is

PMT = 250,000; N = 8; rate = 12%, CPT PV.

PV = 1,241,909.94

Total PV of costs = initial cost + PV of operating costs = 1,500,000 + 1,241,909.94 = 2,741,909,94

Option A should be chosen as PV of total costs is lower than for Option B.


Related Solutions

Florida Power and Light has committed to building a solar power plant. An engineer that works...
Florida Power and Light has committed to building a solar power plant. An engineer that works in FLP, has been tasked with evaluating the three current designs. FLP uses an interest rate of 10% a 20 years horizon. Design 1: A field of “flat” solar panels angled to best catch the sun will cost $87 million initially with firstyear operating costs at $1.8 million, growing $250,000 annually. It will produce electricity worth $7.8 million the first year and will increase...
A power shovel with a dipper of two cubic yard capacity has a standard operating cycle...
A power shovel with a dipper of two cubic yard capacity has a standard operating cycle time of 80 seconds. The excavated material which has a swell factor of 05 will be disposed by a dump truck with an 8 cubic yard capacity at a dump site 6 miles away. The average speed of the dump truck is 30 mph and the dumping time is 40 seconds. Find the daily standard production rates of the power shovel and the dump...
ABC Company has 2 mutually exclusive investment options. Information on the two options is reported below:...
ABC Company has 2 mutually exclusive investment options. Information on the two options is reported below: Option A Option B Initial Investment $150,000 $350,000 Year 1 return $45,000 $100,000 Year 2 return $55,000 $110,000 Year 3 return $60,000 $125,000 Year 4 return $70,000 $110,000 Year 5 return $55,000 $75,000 Year 6 return $60,000 Year 7 return $45,000 Calculate the IRR, NPV (assume a 5% discount rate for NPV calculation), Profitability Index and Payback period for both investments and then determine...
ABC Company has 2 mutually exclusive investment options. Information on the two options is reported below:...
ABC Company has 2 mutually exclusive investment options. Information on the two options is reported below: Option A Option B Initial Investment $150,000 $350,000 Year 1 return $45,000 $100,000 Year 2 return $55,000 $110,000 Year 3 return $60,000 $125,000 Year 4 return $70,000 $110,000 Year 5 return $55,000 $75,000 Year 6 return $60,000 Year 7 return $45,000 Calculate the IRR, NPV (assume a 5% discount rate for NPV calculation), Profitability Index and Payback period for both investments and then determine...
your manager has identified two possible investment projects A and B that are expected to last...
your manager has identified two possible investment projects A and B that are expected to last for four years. The jnitial investment is $225000 for project A and $350000 for project B . the manager estimates the companys cost of capital is 9% the expected cash flow for each project over next four years are: year 1,2 ,3 ,4 projectA 60000, 80000,85000,75000 project B 130000,115000,100000,85000 Required 1. calculate the net present value for both projects 2. calculate the discounted payback...
Sarabeth Tucek is monopoly singer from New York City and has identified two types of customers...
Sarabeth Tucek is monopoly singer from New York City and has identified two types of customers that attend her concerts: adults (A); and non-adults (N). Adult demand is pA = 100 – qA and non-adult demand is pN= 50 – (1/2)qN, where p is the price per concert ticket, and q is the quantity of tickets demanded. Her marginal cost (MC = AC) of playing music to an additional patron is 10. Assume that Sarabeth practices third-degree price discrimination. ....
1) Albert is considering two options for selling land for which he has an adjusted basis...
1) Albert is considering two options for selling land for which he has an adjusted basis of $45,000 and on which there is a mortgage of $90,000. Under the first option, Albert will sell the land for S110,000 with a stipulation in the sales contract that he liquidate the mortgage before the sale is complete. Under the second option, Albert will sell the land for $20,000 and the buyer will assume the mortgage. Calculate Albert's recognized gain under both options....
The World Bank has put you in charge of developing a new charter city. Describe two...
The World Bank has put you in charge of developing a new charter city. Describe two important characteristics your charter city will have (apart from a strategic geographic location) that you believe will be crucial for it to succeed.
Waterloo North Hydro has two options for upgrading a geothermal power station to meet new government...
Waterloo North Hydro has two options for upgrading a geothermal power station to meet new government standards. Assume all interest is 4.19% compounded annually. Option 1 Waterloo North Hydro will make the upgrades themselves. This is expected to cost $46,700 per year from year 1 until the end in 21 years. At the end of the operation (in 21 years) Waterloo North Hydro expects to sell all equipment needed for the upgrade for $96,000. Option 2 Pay experienced contractors. This...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $530,640 $774,700 Estimated direct labor hours for year 12,700 Estimated machine hours for year 24,120 Actual factory overhead costs for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT