In: Finance
A city has identified two options for developing solar power capacity. The investment basis for comparison is 8 years, with interest fixed at 12% per year.
Option A is to build a photovoltaic array at 50% capacity now, at a cost of $1 million, with an operating cost of $200,000 at the end of each year for 4 years. At the end of year 4, the array will be expanded to 100% capacity, at a cost of $900,000. After the expansion, operating costs will become $350,000 per year.
Option B is to build a full-scale solar thermal electric generation plant now at a cost of $1.5 million, with end-of-year operating costs of $250,000.
Which option should be chosen?
To decide the option, we need to calculate the Present Value (PV) of all costs for each option.
Option A: Operating cost (1st 4 years) = 200,000
PV of Op.cost: PMT = 200,000; N = 4; rate = 12%, CPT. PV = 607,469.87
Operating cost (2nd 4 years) = 350,000
PV of Op.cost at the end of 4 years: PMT = 350,000; N = 4; rate = 12%, CPT PV.
PV = 1,063,072.27
PV of this cost today = 1,063,072.27/(1+12%)^4 = 675,601.65
Total PV of operating costs over 8 years = 607,469.87 + 675,601.65 = 1,283,071.52
PV of expansion cost in 4 years = 900,000/(1+12%)^4 = 324,549.02
Total PV of costs = initial cost + PV of operating costs + PV of expansion cost
= 1,000,000 + 1,283,071.52 + 324,549.02 = 2,607,620.54
Option B: PV of operating costs over 8 years is
PMT = 250,000; N = 8; rate = 12%, CPT PV.
PV = 1,241,909.94
Total PV of costs = initial cost + PV of operating costs = 1,500,000 + 1,241,909.94 = 2,741,909,94
Option A should be chosen as PV of total costs is lower than for Option B.