A project involves excavation of a 30m by 30m raft foundation to a depth of 2m,...

A project involves excavation of a 30m by 30m raft foundation to a depth of 2m, with the earth to be transported up to 30m from the edge within 15 days.

Estimate the total cost for excavation considering Manual operation and the following;
Man hours/unit: 2 hours/unit

Assume 8 hour/day of work

Cost of labor/day: $150

2. Estimate the total cost for excavation considering Mechanical Operations with one excavators and 2 tippers and the following;

2 operators per excavator and 2 operators per truck

Productivity of equipment: 30 m3/hour

Assume 8 hour/day of work

Cost of excavator/day: $3000

Cost of tipper/day: $1500

Cost of labor/day: $150

Solutions

Expert Solution


Related Solutions

A 4.5m4.5m foundation carries a load of 3000 kN. The foundation rests at a depth of...
A 4.5m4.5m foundation carries a load of 3000 kN. The foundation rests at a depth of 1.5m below the ground surface. The bearing soil is an extended sand with a saturated unit weight (γsat) of 19 kN/m3 , modulus of elasticity (E) of 35 MPa, and Poisson’s ratio (µ) of 0.3. The water level coincides with the ground surface. a) Determine the effective vertical stresses (σ̍v) for points underneath the corner and center of the foundation and located at a...
A corner of a five-story commercial building resting on a raft foundation settled down a few...
A corner of a five-story commercial building resting on a raft foundation settled down a few inches in the last few years of its construction due to a pocket of loose soil underneath. As a result of undesirable settlement, the usage of building was affected, and the owner seeks the help of a consultant to suggest the proper method of underpinning to avoid any further settlement. Soil investigation reports showed that the hard rock stratum is available at a depth...
explain step by step, how do you design a mat or raft foundation? when do you...
explain step by step, how do you design a mat or raft foundation? when do you opt for raft foundation?
A square foundation 1.5? × 1.5? is founded at a depth of 1.5 m below the...
A square foundation 1.5? × 1.5? is founded at a depth of 1.5 m below the ground surface in sand soil having a cohesion ? ′ = 0 ?? ?2 ⁄ and angle of shearing resistance∅ ′ = 33° . The water table is at a depth of 6 m below ground level. The unit weight of soil above the water table is ? = 18 ?? ?3 ⁄ and the saturated unit weight of the soil ???? = 19...
An irrigation canal with trapezoidal cross-section has the following elements: bottom width = 2m, depth of...
An irrigation canal with trapezoidal cross-section has the following elements: bottom width = 2m, depth of water = 0.9m, side slope 1.5H to 1V, slope of canal bed = 0.001, n = 0.025. The canal will serve clay-loam rice land. What is the hydraulic radius in meters? What is the mean velocity in m/s? If the canal will serve a clay-load rice land, determine the area in hectares it can serve if the duty of water per hectare is 3L/s.
Q5: Which type of pile foundation in adopted for the below conditions: a. the Depth should...
Q5: Which type of pile foundation in adopted for the below conditions: a. the Depth should be 3 to 5 m b. Should be clayey soil Also Describe about that type with neat sketch    Write by microsoft word ( text )
The Problem involves building a 12 – foot diameter sewer at a bottom depth of 40...
The Problem involves building a 12 – foot diameter sewer at a bottom depth of 40 feet in loose sand with a water table at a depth of 8 feet. The alignment is along city streets. The project needs to be completed in 800 days. Determine the amount and types of equipment you feel should be used on this project. The sewer is ten miles in length.
foundation Pile on rock (resting and socket) Design pile on rock depth 10 meter and load...
foundation Pile on rock (resting and socket) Design pile on rock depth 10 meter and load 1000 ton Find the diameter of this pile
foundation Pile on rock (resting and socket) Design pile on rock depth 10 meter and load...
foundation Pile on rock (resting and socket) Design pile on rock depth 10 meter and load 1000 ton how much the diameter of this pile I want the solution
Give design criteria or basis for designing a foundation project
Give design criteria or basis for designing a foundation project
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT