In: Accounting
Question 2
Norio Manufacturing uses powdered plastics (PPS) to manufacture a high-pressure board used in a digital equipment product, Flex 10. Information concerning its operation in June is as follows:
Budgeted units of Flex 10 for June | 6,800 | |||
Budgeted usage of PPS | 61,200 | pounds | ||
Actual number of units of Flex 10 manufactured | 5,800 | |||
PPS purchased | 72,960 | pounds | ||
PPS used | 57,000 | pounds | ||
Total actual cost of PPS used | $ | 368,220 | ||
Direct materials usage variance | $ | 36,480 | unfavorable | |
Assume that Norio does not maintain an inventory of materials, so that the amount of materials used is equal to the amount of materials purchased. The cost of PPS in the flexible budget for the number of units manufactured this period (rounded to nearest dollar) is:
Multiple Choice
$396,720.
$392,160.
$554,496.
$465,120.
$516,800.
Lucky Company's direct labor information for the month of February is as follows:
Actual direct labor hours worked (AQ) | 57,600 | |||
Standard direct labor hours allowed (SQ) | 60,000 | |||
Total payroll for direct labor | $ | 720,000 | ||
Direct labor efficiency variance | $ | 27,840 | ||
The total standard direct labor cost allowed for February, rounded to the nearest dollar, was:
Multiple Choice
$668,160.
$682,560.
$696,000.
$710,400.
$720,000.
(i) | Calculation of cost of PPS in flexible budget for unit manufactured:- | ||||||||
Material Usage Variance | =( Standard Qty - Actual Qty ) X Standard Rate | ||||||||
-36,480 | = ( 52,200 - 57,000 ) X Standard Rate | ||||||||
-36,480 | = - 4,800 X Standarad rate | ||||||||
Standard Rate | = -36,480 / -4,800 | ||||||||
Standard Rate | = $ 7.6 per unit | ||||||||
Cost of flexible Budget | = Standard Qty X Standard Rate | ||||||||
= 52,200 X 7.6 | |||||||||
=$ 396,720 | |||||||||
Option 1 is correct i.e. $ 396,720 | |||||||||
(ii) | Calculation of standard direct labor cost | ||||||||
Direct labour efficiency variance = (Standard hours - Actual Hours ) X Standard Rate | |||||||||
27,480 | = (60,000 - 57,600 ) X Standard Rate | ||||||||
27,480 | = 2,400 X Standard Rate | ||||||||
Standard Rate | = 27,480 /2,400 | ||||||||
Standard Rate | = S 11.60 per hour | ||||||||
Standard direct labor cost | = Standard Hour X Standard Rate | ||||||||
= 60,000 X 11.60 | |||||||||
= $ 696,000 | |||||||||
Option 3 is correct i.e. $ 696,000 | |||||||||