Question

In: Civil Engineering

Assume you are the Design/Build Contractor for a CVS Pharmacy in Logan, OH. The building is...

Assume you are the Design/Build Contractor for a CVS Pharmacy in Logan, OH. The building is 11,945 square feet in size with construction scheduled to commence on January 18, 2017. Use the progress completion schedule from a similar CVS Pharmacy in Athens, OH, to organize the overall schedule for the project by weekly progress for a completion date (turn over to owner) on May 23, 2017.
1. Progress in one week: awnings, landscaping, permanent electrical power, gas service
2. Progress in two weeks: compactor pad poured with concrete, drive through poured with concrete, water line, dumpster pad
3. Progress in two weeks: drywall finishing, painting, electrical rough-in, glass and glazing
4. Progress in two weeks: pharmacy window and pneumatic tube, flooring, lights, ceiling tiles
5. Progress in three weeks: demolition, clear and grub site, excavation and erosion control
6. Progress in two weeks: block cleaning, transformer set, base coat of paving
7. Progress in two weeks: exterior wall block, irrigation, grading, demo for turning lanes
8. Progress in one week: footers, column pads, curb layout, parking lot layout, site grading
9. Progress in two weeks: interior framing, doors and hardware, window frames, electrical rough-in, plumbing rough-in
10. Progress in two weeks: interior slab, block work, storm sewer
11. Progress in one week: landscaping, exterior signage, parking lot striping, site clean-up, project completion
12. Progress in one week: millwork, lights, electrical finish, plumbing finish, HVAC finish
13. Progress in two weeks: sanitary pump station, service panels set, sidewalks poured, stone base for pavement
14. Progress in two weeks: steel erection, exterior framing, HVAC roof curbs, roofing, concrete curb, sanitary sewer, relocate telephone lines, parking lot light conduit

Solutions

Expert Solution

As a contractor for CVS Pharmacy, I will do the activities in the following order.:

1.  Progress in two weeks: exterior wall block, irrigation, grading, demo for turning lanes - Initially we need to give a boundary of the site so that all the activities take place with the boundary and no legal problem arises, We also have to watch out for water supplies required for various activites taking place in site and also make way for the vehicles like truck for stoppage and truning activities.

2.  Progress in three weeks: demolition, clear and grub site, excavation and erosion control - Now we need to demolish the remains of any previous construction, if available, henceforth we can start with our planned excavation.

3.  Progress in two weeks: block cleaning, transformer set, base coat of paving - After excavation and block clearing, we need to set a tranformer at the site to satisfy the electrical requirements of the construction equipments to be used hereafter.

4. Progress in one week: footers, column pads, curb layout, parking lot layout, site grading - Once the base coat and the electrical appliances are ready we can move forward with the casting of the foundations.

5. Progress in two weeks: compactor pad poured with concrete, drive through poured with concrete, water line, dumpster pad - Once the foundationdations are ready, we can work with the water-liner and the sumpster pad.

6. Progress in two weeks: interior slab, block work, storm sewer

7. Progress in two weeks: interior framing, doors and hardware, window frames, electrical rough-in, plumbing rough-in

8. Progress in two weeks: drywall finishing, painting, electrical rough-in, glass and glazing

9.  Progress in two weeks: steel erection, exterior framing, HVAC roof curbs, roofing, concrete curb, sanitary sewer, relocate telephone lines, parking lot light conduit

10. Progress in two weeks: sanitary pump station, service panels set, sidewalks poured, stone base for pavement

11.  Progress in one week: millwork, lights, electrical finish, plumbing finish, HVAC finish - All electrical, air-conditioning work is complete upto this point and after the supply of electrical power everything will start working. Hence after that we will be able to bring the pharmaceutical tubes.

12. Progress in one week: awnings, landscaping, permanent electrical power, gas service

13. Progress in two weeks: pharmacy window and pneumatic tube, flooring, lights, ceiling tiles

14.Progress in one week: landscaping, exterior signage, parking lot striping, site clean-up, project completion

I have tried to answer this question based on my knowledge and experiance. Have a look at the order and revert back for any querry. Thank you.


Related Solutions

You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Torque and Energy You are working with your friend to build a brick fireplace. The contractor...
Torque and Energy You are working with your friend to build a brick fireplace. The contractor dropped 1000 - 1 kg bricks at the base of your driveway which must be carted to the build site in wheelbarrows. Your wheelbarrow has handles that are a total of 2 m long (from the wheel to your hands), with the barrow located at 1 m (from the wheel to the center of mass of the barrow). Your friend has a wheelbarrow where...
You are currently working as a contractor building state of the art airports. One of the...
You are currently working as a contractor building state of the art airports. One of the managerial accountants of the company you work for comes to talk to you about the budget for a project on which you have taken the lead. He wants to know your estimate for the cost of the project. You know that your future with the company depends on your performance in relation to this budget. Your best guess for this project is that it...
You are field manager for the general contractor on a multi-story office building under construction. The...
You are field manager for the general contractor on a multi-story office building under construction. The project has risen all 15 floors above the foundation. The roof is on and the exterior façade of the structure, consisting of alternating blue glass ribbon windows and red granite panels, has “dried in” the project many weeks ago. On the third, seventh and fifteenth floors, the executive offices located on the corners of the building have blue glass doors that lead outside to...
5. Paint the ceiling You want to build yourself a house. The building company you hired...
5. Paint the ceiling You want to build yourself a house. The building company you hired can only build houses with sides from their specific set s. That means they can build you a square house or a rectangular one but if and only if its length and width belong to the set s. This month, they have a special promotion: they will paint the ceiling of a new house for free...but only if its area is not more than...
Design the beams in circular building having 40 feet radius. We need to assume all the...
Design the beams in circular building having 40 feet radius. We need to assume all the missing data.
you bought some land for $1,200,000 your plan is to build an apartment building for $1,300,000...
you bought some land for $1,200,000 your plan is to build an apartment building for $1,300,000 which will provide you with rental revenue of $500,000 per year depreciation is straight line with a 30 year life and no salvage The tax rate is 34% an ordinary income and 20% on capital gains what will you need to sell the apartment for before taxes in 15 years to earn a 15% after tax return?
How would you build a CSIRT? What are the components to building an effective team? DQ...
How would you build a CSIRT? What are the components to building an effective team? DQ requirement: Note that the requirement is to post your initial response no later than Thursday and you must post one additional post during the week. I recommend your initial posting to be between 200-to-300 words. The replies to fellow students and to the professor should range between 100-to-150 words. All initial posts must contain a properly formatted in-text citation and scholarly reference.
Suppose you build bird houses. One day, you double the time you spend building and double...
Suppose you build bird houses. One day, you double the time you spend building and double the wood, nails, paint, and all the other inputs in order to build twice as many bird houses. What kind of production function is this? Question 6 options: increasing returns to scale constant returns to scale decreasing returns to scale zero returns to scale Question 7 (1 point) If a country's saving rate increases, what happens in the long run? Question 7 options: Income...
a building design was complete and is under construction. You had selected a window with a...
a building design was complete and is under construction. You had selected a window with a U-value of 1.6 and a solar heat gain coefficient (SHGC) of 0.25. The window manufacturer informs you that they no longer carry that window model, but that they can give you a window with a U-value of 1.6 and SHGC of 0.4. How would this new window impact your building's modeled heating and cooling energy consumption?