Question

In: Accounting

Analyze and rate the production job for Preble for the month of March (ie. great job,...

Analyze and rate the production job for Preble for the month of March (ie. great job, good job, average, poor job, etc) explain why.

Preble Company
Operating Data
For the Month Ended March 31
Actual Results Flexible Budget Planning Budget
Units 32,000 32,000 35,000
Price [$/lbs] $9.50 $9.50 $10
Quantity 245,000 255,000 224,000
Hours worked 102,400 102,400 96,000
Work rate[$/h] $14.50 $14.50 $14
Variable manufacturing overhead $580,000 $576,000 $630,000
Raw materials cost $2,327,500 $2,240,000 $2,450,000
Labor cost $1,484,800 $1,344,000 $1,470,000
$4,392,300 $4,160,000 $4,550,000

Solutions

Expert Solution

Rating: Poor Job. The reasons are as follows:

a. Let us consider the quantity of materials required . As per the planning budget, it was 224,000 for 35,000 units or 6.4 per unit. If 32,000 units were actually produced and sold, the quantity required should have been 32,000 x 6.4 = 204,800. But the quantity actually used was way higher at 245,000, indicating very unfavorable materials quantity variance.

b. Let us now look at the hours worked. 35,000 units should have required 96,000 hours as per the planning budget. Therefore, 32,000 units should have used 32,000 / 35,000 x 96,000 = 87,771 hours. But the actual hours used to produce 32,000 units was way higher at 102,400, indicating very unfavorable labor efficiency variance.

Therefore, on the production front, it was a poor job.

The materials price variance are the responsibility of the purchase department.

The labor rate variance is the responsibility of the HR or recruitment department.


Related Solutions

Below is budgeted production and sales information for Octofic Cans, Inc. for the month of March:...
Below is budgeted production and sales information for Octofic Cans, Inc. for the month of March:   Aluminum     Tin Estimated beginning inventory 12,000 units 6,000 units Desired ending inventory 15,000 units 4,000 units Region I, anticipated sales 380,000 units 85,000 units Region II, anticipated sales 125,000 units 25,000 units The unit selling price for aluminum cans is $0.15 and for tin cans is $0.20. Budgeted sales for the month are: a. $97,550. b. $82,750. c. $81,550. d. $123,000.
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $5,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,000 $6,400 direct labor .................. 5,000 3,900 4,000 Madtack applies overhead to jobs at a rate of 80% of direct materials used. During March,...
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $5,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,000 $6,400 direct labor .................. 5,000 3,900 4,000 Madtack applies overhead to jobs at a rate of 80% of direct materials used. During March,...
Daniel J Company uses a job-order costing system and started the month of March with three...
Daniel J Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Daniel J applies overhead to jobs based on a percentage of direct materials used. During...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Propane Company uses a job-order costing system and started the month of March with three jobs...
Propane Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Propane applies overhead to jobs based on a percentage of direct materials used. During March, Propane...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT