In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to percentage of completion. Required:
Year 2018:
Up-to-date cost = 2,044,000
Estimated cost = 5,256,000
Total cost = 2,044,000 + 5,256,000 = 7,300,000
Percentage of completion = (Up-to-date cost / Total cost) × 100
= (2,044,000 / 7,300,000) × 100
= 28%
Amount of revenue = Total contract price × Rate of completion
= 10,000,000 × 28%
= $2,800,000 (Answer)
Gross profit = Amount of revenue – Cost incurred
= 2,800,000 – 2,044,000
= $756,000 (Answer)
Year 2019:
Up-to-date cost = 2,044,000 + 2,628,000 = 4,672,000
Estimated cost = 2,628,000
Total cost = 4,672,000 + 2,628,000 = 7,300,000
Percentage of completion = (Up-to-date cost / Total cost) × 100
= (4,672,000 / 7,300,000) × 100
= 64%
Amount of revenue = (Total contract price × Rate of completion) – Revenue of 2018
= (10,000,000 × 64%) – 2,800,000
= 6,400,000 – 2,800,000
= $3,600,000 (Answer)
Gross profit = Amount of revenue – Cost incurred
= 3,600,000 – 2,628,000
= $972,000 (Answer)
Year 2020:
Up-to-date cost = 2,044,000 + 2,628,000 + 2,890,800 = 7,562,800
Estimated cost = 0 (since this is the project completion year)
Total cost = 7,562,800
Percentage of completion = (Up-to-date cost / Total cost) × 100
= (7,562,800 / 7,562,800) × 100
= 100%
Amount of revenue = (Total contract price × Rate of completion) – Revenue of 2018 – Revenue of 2019
= (10,000,000 × 100%) – 2,800,000 – 3,600,000
= 10,000,000 – 6,400,000
= $3,600,000 (Answer)
Gross profit = Amount of revenue – Cost incurred
= 3,600,000 – 2,890,800
= $709,200 (Answer)