Vehicles begin to arrive at a parking lot at 6:00am at a rate of 8 per minute. Due to an
accident on the access highway, no vehicles arrive from 6:20 to 6:30am. From
6:30am on, vehicles arrive at the rate of two per minute. The parking lot attendant
processes incoming vehicles (collects parking fees) at the rate of four per minute
throughout the day. Assuming D/D/1 queuing, draw a queuing (arrival-departure)
diagram to present the events described and determine total vehicle delay.
Can you write more clearly? If it is not clear, some symbols I may not know.