Question

In: Accounting

The following data reflect the current month's activity for Sills, Inc.:         Actual total direct...

The following data reflect the current month's activity for Sills, Inc.:

  

  
  Actual total direct labor $ 184,080
  Actual hours worked 13,000
  Standard labor-hours allowed for actual output (flexible budget) 14,400
  Direct labor price variance $ 4,680 U
  Actual variable overhead $ 45,500
  Standard variable overhead rate per standard direct labor-hour $ 3.60


Variable overhead is applied based on standard direct labor-hours allowed.

  

Required:

Compute the labor and variable overhead price and efficiency variances. (Do not round your intermediate calculations. Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Omit the "$" sign in your response.)

  

Price Variance Efficiency Variance
  Direct labor $     (Click to select)FUNone $     (Click to select)NoneUF
  Variable overhead $     (Click to select)UNoneF $     (Click to select)UNoneF

Solutions

Expert Solution

Ans. 1. Calculation of Labor variance

Actual labor hours rate = 184080/13000 = 14.16 per hour

Direct labor price variance = (Std. rateXactual hours )-(actual hours X actual rate)

(4680) = (Std. labor cost)-(Actual labor cost )

(4680) = (Std.labor cost)-(184080)

Std. labor cost = 179400

Actual hours = 13000

Std. Rate per direct labor hours = 179400/13000 = 13.80 per hour

Direct labor price variance = 179400-184080 = 4680(U)

Direct labor efficiency variance = (std.labors hoursXstd. rate per hour)-(actual hoursXstd. rate per hours)

                                                        = (14400X13.80)-(13000X13.80) = 19320(F)

Calculation of variable overhead variance

Actual variable overhead rate = 45500/13000 = $3.5 per hours

variable overhead price variance = (std.rateXactual hours)-(actual variable o/h)

                                                            = (3.60X13000)-(45500) = 1300(F)

Variable overhead efficiency variance = (std.hoursXstd.rate)-(actual hoursXstd.rate)

                                                                    = (14400X3.60)-(13000X3.60) = 5040(F)

                                                                          Variance table

                                                    Price variance                                                   Efficiency variance

Direct labor                                  4680(UF)                                                           19320(F)

Variable overhead                       1300(F)                                                              5040(F)

                                           


Related Solutions

The following data reflect the current month’s activity for Vickers Corporation. Actual total direct labor $...
The following data reflect the current month’s activity for Vickers Corporation. Actual total direct labor $ 688,940 Actual hours worked 37,000 Standard labor-hours allowed for actual output (flexible budget) 35,700 Direct labor price variance $ 14,060 F Actual variable overhead $ 161,700 Standard variable overhead rate per standard direct labor-hour $ 4.40 Variable overhead is applied based on standard direct labor-hours allowed. Required: Compute the labor and variable overhead price and efficiency variances.
The following actual and standard cost data for direct material and direct labor relate to the...
The following actual and standard cost data for direct material and direct labor relate to the production of 2,000 units of a product: Actual Costs Standard Costs Direct material 21,450 lbs. @ $5.30 22,000 lbs. @ $5.10 Direct labor 34,100 hrs. @ $8.40 33,000 hrs. @ $8.70 Determine the following variances: Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable. Materials Variances Actual cost: $Answer...
In reviewing activity for July, the controller of Mathis, Inc., collected the following data concerning direct...
In reviewing activity for July, the controller of Mathis, Inc., collected the following data concerning direct materials. Actual production 103,000 units Direct materials purchased (actual) $ 1,642,800 Standard cost of materials purchased 1,554,000 Standard direct materials costs per unit produced 14 Standard price times actual amount of materials used 1,405,950 Assume that Mathis Company had no beginning finished goods inventory and only produced one product. Mathis sold 90,640 units during the period. Required: a. Assume Mathis writes off all variances...
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct...
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct labor variance $8,600 Unfavorable . Direct labor rate variance $4,000 Unfavorable . Standard hours allowed per unit produced 2 hours Required: Find the following unknowns. a. Direct labor efficiency variance b. Standard rate per direct labor hour c. Actual quantity produced
Material and Labor Variances The following actual and standard cost data for direct material and direct...
Material and Labor Variances The following actual and standard cost data for direct material and direct labor relate to the production of 2,000 units of a product: Actual Costs Standard Costs Direct material 4,200 lbs. @ $4.90 4,000 lbs. @ $5.20 Direct labor 5,700 hrs. @ $9.30 6,000 hrs. @ $9.50 Determine the following variances: Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable. Materials...
n reviewing activity for July, the controller of Mathis, Inc., collected the following data concerning direct...
n reviewing activity for July, the controller of Mathis, Inc., collected the following data concerning direct materials. Actual production 116,000 units Direct materials purchased (actual) $ 1,954,800 Standard cost of materials purchased 1,580,000 Standard direct materials costs per unit produced 14 Standard price times actual amount of materials used 1,431,950 Assume that Mathis Company had no beginning finished goods inventory and only produced one product. Mathis sold 102,080 units during the period. Required: a. Assume Mathis writes off all variances...
1. The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows:...
1. The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows: Actual Costs Budgeted Costs Units produced 1,500 1,500 Direct materials cost $5,680 $5,010 Direct labor cost 1,620 1,420 VOH: Maintenance 710 625 Power 300 190 FOH: Grounds keeping 1,480 1,220 Depreciation 540 540 Calculate the flexible budget variance. a.$110F b.$1,065U 2. c.$1,325U d.$260F Which of the following is true of an after-the-fact flexible budget? a.It is a budget created in advance that is based...
Inception Company produces gadgets for the coveted small appliance market. The following data reflect activity for...
Inception Company produces gadgets for the coveted small appliance market. The following data reflect activity for the year 2014​: Inception Co. uses a​ normal-costing system and allocates overhead to work in process at a rate of 2.90 per direct manufacturing labor dollar. Indirect materials are insignificant so there is no inventory account for indirect materials. Requirements 1. Prepare journal entries to record the transactions for 2014 including an entry to close out​ over- or underallocated overhead to cost of goods...
Donation Company produces gadgets for the coveted small appliance market. The following data reflect activity for...
Donation Company produces gadgets for the coveted small appliance market. The following data reflect activity for the year 2014​: LOADING...​(Click the icon to view the​ data.) Donation Co. uses a​ normal-costing system and allocates overhead to work in process at a rate of $2.80 per direct manufacturing labor dollar. Indirect materials are insignificant so there is no inventory account for indirect materials. Costs incurred: Purchases of direct materials (net) on credit $124,000 Direct manufacturing labor cost 83,000 Indirect labor 54,100...
The following information relates to Burgundy for July 2020: Actual direct labour costs $50,000 Actual direct...
The following information relates to Burgundy for July 2020: Actual direct labour costs $50,000 Actual direct labour rate per hour $10 Factory overhead rate per direct labour hour $15 Factory overhead incurred $80,000 As part of the cost planning and cost control of operations and activities, management is concerned regarding the applied overhead rate used. Required a) Identify whether there is an underapplied or overapplied overhead. Assuming underapplied or overapplied overhead is transferred to cost of goods sold at the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT