how to solve this question step by step.
Calculate the number of workers that should have been available to process the July claims, and show all work.
Standard time for processing per claim (simple claim)=36 minutes
Standard time for processing per claim (complex claim)=1.25 hours
Expected work hours per day 7.5 hours
Compensation cost per employee= $135 per day
Total working days=20
The number of July processed claims (simple)=3000
The number of July processed claims (complex)=960