In: Accounting
Job B
Beg Balance $1,500
Direct Material 800
Direct Labor 2,300
The company applies overhead at 120% of direct labor cost. During September Job B was completed and sold in October. If Job B sold for $8,000, what was the amount of gross profit for this job? (Ignore any consideration of over/under applied overhead)
--All working forms part of the answer
--Answer #1
A | Sale price per chair | $ 40.00 |
B | Variable cost per chair | $ 15.00 |
C = A - B | Contribution margin per chair | $ 25.00 |
D | Machine hours used per chair | 2 |
E = C/D | Contribution margin per machine hour | $ 12.50 |
Correct Answer | Option 'a' $ 12.50 |
--Answer #2
A | Beginning Bal | $1,500.00 |
B | Direct material | $800.00 |
C | Direct Labor | $2,300.00 |
D = C x 120% | Manufacturing Overheads applied | $2,760.00 |
E = A+B+C+D | Total Cost of the job | $7,360.00 |
F | Job Sold for | $8,000.00 |
G = F - E | Gross Profits | $640.00 |
Correct Answer | Option 'D' $ 640 |