In: Finance
A mining company is considering a new project. Because the mine
has received a permit, the project would be legal; but it would
cause significant harm to a nearby river. The company could spend
an additional R10 million at Year 0 to mitigate the environmental
problem, however it would not be required to do so. Developing the
mine (without mitigation) would cost R60 million, and the expected
cash inflows would be R20 million per year for 5 years. If the
company does invest in mitigation, the annual inflows would be R21
million. The risk-adjusted WACC is 12%.
Required:
2.1 Calculate the NPV and IRR without mitigation. (5)
2.2 How should the environmental effects be dealt with when
evaluating this project? (5)
2.3 Should this project be undertaken? If so, should the company do
mitigation? Why or why not? (5)
Answer 2.1:
Without mitigation
Development cost = R60 million = R60,000,000
Annual cash flow = R20 million = R20,000,000
Project life = 5 years
WACC = 12%.
NPV = Annual cash flow * PV of $1 annuity for 5 year at 12% rate - Development cost
= 20000000 * (1 - 1 / (1 + 12%) 5) / 12% - 60000000
= R12,095,524.05
To calculate IRR we will use RATE function of excel
IRR = RATE(nper, pmt, pv, fv, type)
= RATE (5, 20000000, -60000000, 0, 0)
= 19.86%
Hence:
NPV = R12,095,524.05
IRR = 19.86%
Answer 2.2:
As a good corporate citizen the mining company should evaluate the environmental effects. Although company has got permission and it is not legally required, in future it will create issues and a good company has to think long term and do what is required to remain sustainable.
It should evaluate the project with mitigation measures in place and if financials result positive NPV, it should rather mitigate environmental effects.
Answer 2.3:
Let us evaluate the financials with mitigation:
Development cost = R60 million + R10 million = R70,000,000
Annual cash flow = R21 million = R21,000,000
NPV = 21000000 * (1 - 1 / (1 + 12%) 5) / 12% - 70000000
= R5,700,300.24
IRR = RATE (5, 21000000, -70000000, 0, 0) = 15.24%
As such with mitigation also we have:
NPV = R5,700,300.24
IRR = 15.24%
With mitigation also the project has positive NPV and has IRR greater than WACC. The project is acceptable with mitigation also.
Although NPV will lesser with mitigation as compared to NPV without mitigation, considering factors as stated in answer 2.2 above, company should do mitigation and implement the project.