In: Finance
A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $9.33 million at Year 0 to mitigate the environmental Problem, but it would not be required to do so. Developing the mine (without mitigation) would require an initial outlay of $54 million, and the expected cash inflows would be $18 million per year for 5 years. If the firm does invest in mitigation, the annual inflows would be $19 million. The risk-adjusted WACC is 12%.
Calculate the NPV and IRR with mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Do not round intermediate calculations. Round your answers to two decimal places.
NPV: $ million
IRR: %
Calculate the NPV and IRR without mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Do not round intermediate calculations. Round your answers to two decimal places.
NPV: $ million
IRR: %
How should the environmental effects be dealt with when this project is evaluated?
-Select-IIIIIIIVVItem 5
Should this project be undertaken?
(-Select-The project should not be undertaken under the "no mitigation" assumption.The project should be undertaken only under the "no mitigation" assumption.The project should not be undertaken under the "mitigation" assumption.Even when mitigation is considered the project has a positive NPV, so it should be undertaken.Even when mitigation is considered the project has a positive IRR, so it should be undertaken)
If so, should the firm do the mitigation?
-Select-IIIIIIIVV
please write easily read answers! thank you.
With Mitigation
Initial Investment with mitigation =54+9.33 =63.33
Cash Inflows =19
Rate =12%
Number of Periods =5
NPV =PV of Cash Flows -Investment =19*((1-(1+12%)^-5)/12%)-63.33
=5.16
IRR Using Financial Calculator
CF0=-63.33;CF1 =19;CF2=19;CF3=19;CF4=19;CF5=19;CPT IRR
=15.24%
Without Mitigation
Initial Investment without mitigation =54
Cash Inflows =18
Rate =12%
Number of Periods =5
NPV =PV of Cash Flows -Investment
=18*((1-(1+12%)^-5)/12%)-54=10.89
IRR Using Financial Calculator
CF0=-54;CF1 =18;CF2=18;CF3=18;CF4=18;CF5=18;CPT IRR
=19.86%
b. Option I is correct option
c. Option V is correct option. NPV is positive even under
mitigation
d. Option II is correct Under the assumption that all costs have
been considered, the company would not mitigate for the
environmental impact of the project since its NPV without
mitigation is greater than its NPV when mitigation costs are
included in the analysis