Question

In: Operations Management

Consider the process of manufacturing orange juice concentrates. The facility operated at capacity, with one 8-hour...

Consider the process of manufacturing orange juice concentrates. The facility operated at capacity, with one 8-hour shift per-day, six days a week, for a total of 36 weeks per year during the prime orange growing season. To simplify, capacity was measured in terms of the equivalent amount of finished juice concentrate. The key elements of the continuous production process are as follows:

(1) Storage: There are three sizes of oranges (small, medium and large) each stored separately in a bin with a capacity of 80,000 pounds.

(2) Juice Extraction: The extractor can process oranges of only one size at a time. The changeover time from one size to the other is 20 minutes. Irrespective of the size of the oranges, the extractor had the capacity to produce up to 20,000 pounds/hour of finished juice concentrate.

(3) Juice Filtration: Here seeds and small pieces of orange peel were filtered from the juice and discarded. The processing capacity of this step is 20,000 pounds/hour of finished concentrate. After it ran for 90 minutes, the machine’s filter had to be changed to clear the debris. The setup time (the time required to shut down the machine, change the filter, and restart the machine) is 30 minutes.

(4) Juice Concentration: Here, some of the water in the juice was removed as it flowed through the machine. No setups were required for this operation and had a capacity of up to 18,000 pounds of finished concentrate per hour. (5) Juice Testing and Storage: Here concentrated juice is tested for color and sugar content and separated into one of four large storage tanks. The total capacity of these four tanks is 250,000 pounds of concentrate. (6) Blending: The blending operation mixed juice concentrate from these four tanks (the proportion depended on each customer’s specification) at a rate of up to 22,000 pounds of finished product per hour. A 40-minute setup time was required to change from one blend to another.

The movement of oranges from delivery to storage bins and bins to extraction occurred with conveyer belts. Following extraction, the juice was pumped through pipes from one process step to another. The residue from extraction was removed and discarded continuously during the extraction. Assume that the production system was running only ONE size of oranges. Consider just the process steps two through four: extraction, filtration, and concentration.

Answer the following questions:

1. How much orange juice concentrate can be processed in one 8-hour workday?

2. Assume extraction had previously been setup for the size oranges being processed. How much idle time will there be in the extraction operation during one 8-hour workday?

3. If you could add storage capacity somewhere between steps two and four in this production line in order to increase daily output, where would you place it? How much storage would you add? Why?

4. If the cost of adding storage was $30/pound and the cost of reducing setup time by 50% using additional fixtures was $20,000 for the filter process and $10,000 for the extraction process, what action would you recommend in order to maximize the output of this production line?

5. How much will you recommend improvement(s) cost? How much additional capacity do you create?

Solutions

Expert Solution

  1. How much orange juice concentrate can be processed in one 8-hour workday?

       20,000 pounds/hour of finished juice concentrate

2. Assume extraction had previously been setup for the size oranges being processed. How much idle time will there be in the extraction operation during one 8-hour workday?

Since extraction had previously been set up for all size oranges to be processed the idle time in extraction operation during one -8 hour / work day will be zero

3 . If you could add storage capacity somewhere between steps two and four in this production line in order to increase daily output, where would you place it? How much storage would you add? Why?

In order to increase the daily output , Storage capacity can be setup in the step 3 using additional fixture that combines filter process and extraction process . storage bin of capacity 60000 pounds can be added because the initial storage capacity of oranges of any size 80000 pounds has been crushed and squeezed in to 20000 pound juice concentrate    

4. 4. If the cost of adding storage was $30/pound and the cost of reducing setup time by 50% using additional fixtures was $20,000 for the filter process and $10,000 for the extraction process, what action would you recommend in order to maximize the output of this production line?

Cost of adding a storage = $ 30/POUND

Cost of reducing setup time = 50% [ cost of additional fixture + cost of extraction process]

                                                  = [(50/100) ($ 20000+$10000)]

                                                  = $600

In order to maximize the output of a production line a new storage can be set up at a cost of $ 30 pound , since it reduce the setup time by $ 600


Related Solutions

Consider the statements below: Julia is indifferent between orange juice and guava juice but she cannot...
Consider the statements below: Julia is indifferent between orange juice and guava juice but she cannot decide how she feels about watermelon juice. Paul likes harmonica more than violin, violin more than flute, and flute more than harmonica. For both the statements, identify which consumer preference assumption is violated. Question 1 options: The completeness and rankability assumption is violated in statement I and the assumption that consumers like variety is violated in statement II. The transitivity assumption is violated in...
An orange juice producer buys only one kind of oranges. The amount of juice squeezed from...
An orange juice producer buys only one kind of oranges. The amount of juice squeezed from each of these oranges is approximately normally distributed with a mean of 4.2 ounces and a population standard deviation of 1 ounce. If a sample of 100 oranges is selected: (a) What is the probability that the average juice squeezed is less than 4.15 ounces? (b) What is the probability that the average juice squeezed is more than 4.3 ounces? (c) What is the...
An ice chest contains 6 cans of apple​ juice,8 cans of grape​ juice,7 cans of orange​...
An ice chest contains 6 cans of apple​ juice,8 cans of grape​ juice,7 cans of orange​ juice, and 4 cans of mango juice. Suppose that you reach into the container and randomly select three cans in succession. Find the probability of selecting three cans of grape juice.
An orange juice producer buys oranges from a large orange grove that has one variety of...
An orange juice producer buys oranges from a large orange grove that has one variety of orange. The amount of juice squeezed from these oranges is approximately normally​ distributed, with a mean of 4.40 ounces and a standard deviation of 0.32 ounce. Suppose that you select a sample of 16 oranges. a. What is the probability that the sample mean amount of juice will be at least 4.27 ​ounces? b. The probability is 72​% that the sample mean amount of...
A new paint process has been installed in a manufacturing facility. With this process, the facility...
A new paint process has been installed in a manufacturing facility. With this process, the facility has to wait only 58 minutes for drying before the next coat can be applied. That is, with the new process, the average dry time was 58 minutes and the standard deviation was 15.9 minutes for a sample of 30 automobiles. Compare this to the process that was replaced. This process (old process) was studied for 50 automobiles and the average dry time was...
One manufacturer has developed a quantitative index of the​ "sweetness" of orange juice.​ (The higher the​...
One manufacturer has developed a quantitative index of the​ "sweetness" of orange juice.​ (The higher the​ index, the sweeter the​ juice). Is there a relationship between the sweetness index and a chemical measure such as the amount of​water-soluble pectin​ (parts per​ million) in the orange​ juice? Data collected on these two variables for 24 production runs at a juice manufacturing plant are shown in the accompanying table. Suppose a manufacturer wants to use simple linear regression to predict the sweetness​...
Consider the market for orange juice. Draw a correctly labeled set of axes. Draw a market...
Consider the market for orange juice. Draw a correctly labeled set of axes. Draw a market supply curve and a market demand curve. On the axes, label the equilibrium price P0 and the equilibrium quantity Q0. A new study is released that states folic acid in orange juice reduces the risk of cancer, Show what happens to the demand curve or the supply curve for orange juice . On the axes, label the new equilibrium price P1 and the new...
A can company reports that the number of breakdowns per 8-hour shift on its machine operated...
A can company reports that the number of breakdowns per 8-hour shift on its machine operated assembly line follows a Poisson distribution with a mean of 1.5. What is the probability of exactly three breakdowns on the midnight shift? What is the probability of greater than two breakdowns in one hour? What is the probability that the time between two successive breakdowns is at most three hours? If two hours have gone by without a breakdown, what is the probability...
A feed manufacturing company is faced with a capacity decision.  Their present production facility is running at...
A feed manufacturing company is faced with a capacity decision.  Their present production facility is running at nearly maximum capacity.  Management is considering the following three decision alternatives: No expansion Add on the present facility Build a new facility What option would be recommended under the optimistic approach? What option would be recommended under the conservative approach? What option would be recommended under the opportunity (minimax) regret approach? PLEASE EXPLAIN WHAT THESE TERMS MEAN WHEN SOLVING THE QUESTION State of demand Option:...
Customers arrive at a service facility according to a Poisson process of rate 5 /hour Let...
Customers arrive at a service facility according to a Poisson process of rate 5 /hour Let N(t) be the number of customers that have arrived up to time t hours). a. What is the probability that there is at least 2 customer walked in 30 mins? b.If there was no customer in the first30 minutes, what is the probability that you have to wait in total of more than 1 hours for the 1 st customer to show up? c.For...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT