Question

In: Civil Engineering

What is the typical approach in the contracts to shift the project risk to the other...

What is the typical approach in the contracts to shift the project risk to the other contracting party? What are the usual consequences of this inequitable risk assignment? Provide an example of contract provisions that are typically used to shift the project risk to other parties (Max 200 words).

Solutions

Expert Solution

In contracts owner usually tries to shift the risk to the contracting agency by adding some disclaimer clause in the contract. Mainly following disclaimer clause are incoorporated in the contract.

(1) Uncertainty of work conditions:- As per this clause all the uncertainity in the work conditions are to handled by contractor without extra payment. Consequency of this clause is loss to the contractor some times when any unexpected thing comes into picture which increase cost of contractor for carrying out the job.

(2) Delaying events:- As per this clause in case of any delay on any account will cause penalty on the contractor. Delay can be on any excusable account in that case penalty will not be justified.

(3) Indemnification:- As per this clause a indemnified bond is signed between owner and contractor to accept all type of risk by contractor.

(4) Liquidated damages:- As per this clause in case of delay in project. Then loss of owner due to delay in completion will be borne by the contractor.

What are the usual consequences of this inequitable risk assignment?

1. Decrease in competition of bidders:- Such clause of ineuitable risk will demoralize the bidders to participate and there will be restricted participation.

2. More disputes and claims in court:- In case of such clause incorporated in contract and contractor get loss in the project due to these clauses, then he have no way other than going to court.

3. Adverse contractor owner relation:- These clause will lead to dispute between conttactor and owner, which will lead to harm to project at the end i.e. or either delay or bad quality.


Related Solutions

what are the typical types of risk faced by a firm
what are the typical types of risk faced by a firm
what are the typical constraints of a project with examples
what are the typical constraints of a project with examples
1. Assignment/Research: a. Preparation of bids for a project b. Contracts of projects or other works
1. Assignment/Research: a. Preparation of bids for a project b. Contracts of projects or other works
discuss the code's approach to the requirement that certain contracts must be in writting and the...
discuss the code's approach to the requirement that certain contracts must be in writting and the alternative methods of compliance
What are the four basic types of contracts or instruments used in financial risk management?
What are the four basic types of contracts or instruments used in financial risk management?
Options contracts are an alternative to futures and forwards contracts to hedge FX risk. Why would...
Options contracts are an alternative to futures and forwards contracts to hedge FX risk. Why would investors prefer to use options rather than futures or forwards? Under which future outcomes do options provide an advantage relative to forwards or futures contracts? Why might managers choose not to enter into options contracts?
What is The Scenario Approach?    What is a project? What do Encryption and Firewalls mean?...
What is The Scenario Approach?    What is a project? What do Encryption and Firewalls mean? Discuss the role of Business/IT Planning and its major components.
1. What is the typical characteristic of patients at moderate risk for exercise participation (from the...
1. What is the typical characteristic of patients at moderate risk for exercise participation (from the risk stratification criteria for patients with cardiovascular disease)? a.) Absence of complicated ventricular dysrhythmias at rest. b.) Presence of abnormal hemodynamics with exercise testing (e.g., severe postexercise hypotension) c.) High level of silent ischemia during exercise testing d.) Functional capacity <5 METs with exercise testing 2. _____ cerebral palsy is a type of cerebral palsy with damage to the basal ganglia with inability to...
Describe the UCC’s approach to requiring that certain contracts be in writing and identify the alternative...
Describe the UCC’s approach to requiring that certain contracts be in writing and identify the alternative methods of compliance under the code.
3. After May 2020, what are the prospects of futures contracts as a significant risk management...
3. After May 2020, what are the prospects of futures contracts as a significant risk management tool for firms? Discuss critically.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT