Question

In: Operations Management

1. Assignment/Research: a. Preparation of bids for a project b. Contracts of projects or other works

1. Assignment/Research:

a. Preparation of bids for a project

b. Contracts of projects or other works

Solutions

Expert Solution

1.

a. Preparation of bids for a project

Bid is the price quotation or offer set by the individual or organisation for something like resources, assets, securities etc.

The bid is prepared by following steps:

1. Research and planning- This is the beginning of the bid preparation process in which the data and information is collected for the bid preparation. For example, what is the vision, mission, and objectives of the organisation need to be fulfil the bid. Research for the Qualification of company to prepare a bid and also its critical resources as well as experience for viability of the project after bidding.

2. Preparing the bid- A kind of feasibility analysis is done while preparing a bid as how organisation is able to fulfil the bid request. For example, cost of material, time frame, and labour feasibility with the availability of these with the company.

3. Bid submission- Now the bid documentation process has been done so company needs to apply for the bid. In case of government as well as private firms, online portals are available to submit a bid. Adhere with the rules of the organisation professionalism should be followed.

4. Present the bid- If all the bidding documentation process goes fine then the company representative may have opportunity to meet with the reviewing team. Due to digitalisation the meeting opportunities are also going online. Here the questions can be asked by the reviewing team so the company representative should be prepared for it.

5. Getting the contract- The contract award dates are decided by the agency and the company representatives should be in touch with the agency to know the dates and time of award a contract.

b. Contracts of projects or other works

Contract of projects or other works is a legal agreement between two or more parties in order to accomplish the desired goals of company.

These contracts can be of different types –

1. Fixed Price Contract- Agreement between two parties is on fixed price. So here the risk associated with both the parties i.e. buyer and seller is divided or less.

2. Cost reimbursement contract- These kind of contracts works when the scope of project is not clear. So, after finishing the units or sub-processes of projects one party claims with the bill or cost expend on it during fixed time duration. Hence, these contracts are agreed on completion of partial work by one party. So, here risk is more with one party and other party enjoyed with guaranteed benefits.

3. Unit price Contract- These type of contracts are based on the unit price in case of material or labor price in case of work. So the risk is more associated with one party only.


Related Solutions

What is the typical approach in the contracts to shift the project risk to the other...
What is the typical approach in the contracts to shift the project risk to the other contracting party? What are the usual consequences of this inequitable risk assignment? Provide an example of contract provisions that are typically used to shift the project risk to other parties (Max 200 words).
A computer consulting firm presently has bids out on three projects. Let Ai = {awarded project...
A computer consulting firm presently has bids out on three projects. Let Ai = {awarded project i}, for i = 1, 2, 3, and suppose that P(A1) = 0.22, P(A2) = 0.25, P(A3) = 0.28, P(A1 ∩ A2) = 0.13, P(A1 ∩ A3) = 0.03, P(A2 ∩ A3) = 0.06, P(A1 ∩ A2 ∩ A3) = 0.01. Express in words each of the following events, and compute the probability of each event. (a) A1 ∪ A2 Express in words the...
There are two projects: Project A and Project B a. Project A: CF0 = -6000; CF1-5...
There are two projects: Project A and Project B a. Project A: CF0 = -6000; CF1-5 = 2000; I/YR = 14. Calculate NPV, IRR, MIRR, Payback period, and discounted payback period for Project A. Project B: CF0 = -18000; CF1-5 = 5600; I/YR = 14. Calculate NPV, IRR, MIRR, Payback period, and discounted payback period for Project B. b. If the two projects are independent, which project(s) would be accepted? c. If the two projects are mutually exclusive, which project...
Lump sum contracts: A. Are negotiated between the owner and contractor on competitively bid projects. B....
Lump sum contracts: A. Are negotiated between the owner and contractor on competitively bid projects. B. Are where the contractor is reimbursed for actual costs of labor and materials. C. Are typically used on engineering projects. D. Are the simplest method of stating the cost of an entire contract.
1.) A company is considering two projects.   Project A Project B Initial investment $300,000 $300,000 Cash...
1.) A company is considering two projects.   Project A Project B Initial investment $300,000 $300,000 Cash inflow Year 1 $60,000 $90,000 Cash inflow Year 2 $60,000 $80,000 Cash inflow Year 3 $60,000 $80,000 Cash inflow Year 4 $60,000 $50,000 Cash inflow Year 5 $60,000 $70,000 What is the payback period for Project B? Select one: a. 2 years b. 5 years c. 3.5 years d. 4 years e. 3 years 2.) Ace Inc. produces custom widgets. The cost structure for...
The following are the cash flows of two projects: Year    Project A    Project B...
The following are the cash flows of two projects: Year    Project A    Project B 0 -250    -250 1    130    150 2    130    150 3    130    150 4    130 If the opportunity cost is 10%, what is the profitability index for each project? Project Profitability Index A B   
Projects A and B are mutually exclusive projects. Project A requires an initial investment today of...
Projects A and B are mutually exclusive projects. Project A requires an initial investment today of $300 and generates expected cash flows of $100 at the end of each of the next 5 years. Project B requires an initial investment today of $130 and generates expected cash flows of $55 at the end of each of the next 5 years. a. If you plotted the NPV profiles, what would be the "crossover rate" in the graph? (Note you are not...
Research relationship between contracts and promises, and write, 1) summarizing whether you believe that contracts are...
Research relationship between contracts and promises, and write, 1) summarizing whether you believe that contracts are promises; 2) analyzing whether and why contracts and promises should be treated the same or differently; and 3) in your analysis, consider the potential economic, legal, and moral consequences of your answers. You may wish to review this article along with other resources from Westlaw or JSTOR before beginning to write your answer.
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT