In: Accounting
Entity A is a local construction company, which provides construction services to different types of customers. On 16 December 2017, Entity A ordered a concrete plant from Entity B. The listed price of the plant is $650,000 for general customers. However, Entity B offers a 10% trade discount to Entity A because it is one of its loyal customers. The plant was delivered to Entity A on 1 January 2018. According to the contract, Entity B provides a 2-month credit period to Entity A. Finally, Entity A fully settled the outstanding amount on 1 February 2018.
Installation and testing services are required to make the plant ready for use. On 1 January 2018, Entity C, the installation and testing service provider completed the concrete plant installation and testing services and certified the plant was really for use by Entity A. The cost of installation and testing services are $5,000 and it was settled with Entity C by cheque on 1 January 2018. At the inception stage, Entity A expected the useful life of the concrete plant is 5 years.
According to the local environmental protection regulation, Entity A is required to remove the concrete plant at the end of the reporting period in the Year 2022. The removal cost of $5,100 and the plant residual value of $4,013 was estimated at the inception of the contract respectively.
Finally, on 31 December 2022, the removal cost incurred was the same as the estimated amount and it will be paid in the first week of the Year 2023. However, the residual of the concrete plant can be sold by $1,900 only. A cheque was received on the same date.
Entity A always applies to discount with a rate of 8.05%.
REQUIRED:
According to relevant accounting standards, prepare journal entries to record the transactions of Entity A on 16 December 2017, 31 December 2017, 1 January 2018, 1 February 2018, 31 December 2018, 1 January 2020 and 31 December 2020, 1 January 2022 and 31 December 2022.
ACCOUNT NAMES FOR INPUT:
| PPE | Bank | Inventory | Revenue | Cost of sales | Payable | Receivable |
| Restoration liability | Interest expense | Interest revenue | Depreciation | Accum. depreciation |
| Loss on disposal | Gain on disposal | Share capital | Retained earnings | No entry |
ANSWERS:
Journal Entries:
Date | Account Name | Debit ($) | Credit ($) | Hints For Items If Necessary |
16-Dec-17 | Blank 1 | Blank 2 | ||
Blank 3 | Blank 4 | |||
31-Dec-17 | Blank 5 | Blank 6 | ||
Blank 7 | Blank 8 | |||
1-Jan-18 | Blank 9 | Blank 10 | ||
Blank 11 | Blank 12 | Purchase price. Judge Dr/Cr side. | ||
Blank 13 | Blank 14 | Directly attributable cost. Judge Dr/Cr side. | ||
Blank 15 | Blank 16 | Dismantling cost. Judge Dr/Cr side. | ||
1-Feb-18 | Blank 17 | Blank 18 | ||
Blank 19 | Blank 20 | |||
31-Dec-18 | Blank 21 | Blank 22 | An interest created due to the dismantling cost. | |
Blank 23 | Blank 24 | |||
31-Dec-18 | Blank 25 | Blank 26 | ||
Blank 27 | Blank 28 | |||
1-Jan-20 | Blank 29 | Blank 30 | ||
Blank 31 | Blank 32 | |||
31-Dec-20 | Blank 33 | Blank 34 | An interest created due to the dismantling cost. | |
Blank 35 | Blank 36 | |||
31- Dec-20 | Blank 37 | Blank 38 | ||
Blank 39 | Blank 40 | |||
1-Jan-22 | Blank 41 | Blank 42 | ||
Blank 43 | Blank 44 | |||
31-Dec-22 | Blank 45 | Blank 46 | An interest created due to the dismantling cost. | |
Blank 47 | Blank 48 | |||
31-Dec-22 | Blank 49 | Blank 50 | ||
Blank 51 | Blank 52 | |||
31-Dec-22 | Blank 53 | Blank 54 | The settlement of dismantling cost. | |
Blank 55 | Blank 56 | |||
31-Dec-22 | Blank 57 | Blank 58 | The disposal of the concrete plant. | |
Blank 59 | Blank 60 | |||
Blank 61 | Blank 62 | |||
Blank 63 | Blank 64 | The gain or loss on disposal. Judge Dr/Cr side. |
Date | Account Name | Debit ($) | Credit ($) | Hints For Items If Necessary |
16-Dec-17 | - | - | No entry required as only order has been raised | |
- | - | |||
31-Dec-17 | - | - | No entry required as only order has been raised, even at the end of year | |
- | - | |||
01-Jan-18 | PPE | 593,462.95 | ||
Payable to B | 585,000.00 | Purchase price. Judge Dr/Cr side. | ||
Bank (Payable to C) | 5,000.00 | Directly attributable cost. Judge Dr/Cr side. | ||
Restoration Liability (5100*.067901) | 3,462.95 | Dismantling cost. Judge Dr/Cr side. | ||
01-Feb-18 | Payable to B | 585,000.00 | ||
Bank | 585,000.00 | |||
31-Dec-18 | Interest expense | 278.77 | An interest created due to the dismantling cost. | |
Restoration Liability | 278.77 | |||
31-Dec-18 | Depreciation expense | 117,889.99 | ||
Accumulated depreciation | 117,889.99 | |||
01-Jan-20 | - | - | No entry | |
- | - | |||
31-Dec-20 | Interest expense | 325.46 | An interest created due to the dismantling cost. | |
Restoration Liability | 325.46 | |||
31-Dec-20 | Depreciation expense | 117,889.99 | ||
Accumulated depreciation | 117,889.99 | |||
01-Jan-22 | - | - | No entry | |
- | - | |||
31-Dec-22 | Interest expense | 351.65 | An interest created due to the dismantling cost. | |
Restoration Liability | 351.65 | |||
31-Dec-22 | Depreciation expense | 117,889.99 | ||
Accumulated depreciation | 117,889.99 | |||
31-Dec-22 | Restoration liability | 5,100.00 | The settlement of dismantling cost. | |
Bank | 5,100.00 | |||
31-Dec-22 | Accumulated Depr. | 589,449.95 | The disposal of the concrete plant. | |
PPE | 593,462.95 | |||
Bank | 1,900 | |||
Loss on disposal | 2,113 | The gain or loss on disposal. Judge Dr/Cr side. |