TRP 631: HIGHWAY TRAFFIC OPERATIONS
An older four-lane freeway has the following characteristics:
The present peak-hour demand on the facility is 2,100 veh/h, and anticipated growth is expected to be 3% per year. What is the present LOS? What is the expected LOS in 5 years? 10 years? 20 years?. To avoid breakdown (LOS F), when will substantial improvements be needed to this facility, and/or alternative routes created? Good weather, no incidents, no work zones, and regular drivers may be assumed.