Question

In: Operations Management

For the following provide (a) algebraic formulation, (b) optimized model using Excel-Solver, and (c) statement of...

For the following provide (a) algebraic formulation, (b) optimized model using Excel-Solver, and (c) statement of the optimal solution.

Paper Company plant produces rolls of paper of various types for its customers. One product type is rolls of wrapping paper in several different standard widths, as follow: 12, 15, 20, 24, 30, or 40 inches. The various-width rolls are produced by slicing 60-inch wide rolls in plant. For a given week, company waits for all its customer orders to come in and then decides how to slice its 60-inch rolls to satisfy that week’s orders, to minimize the waste (i.e., the part of the rolls sliced that’s not used for customers’ orders that week). [For example if customer orders in a particular week totaled six 15-inch wide rolls and two 40-inch wide rolls, the orders could be satisfied by appropriately slicing three 60-inch wide rolls, leaving only two 5-inch waste rolls.]

company wants to use the minimum number of 60-inch rolls to meet each week’s customer orders, minimizing waste – with waste being defined as any part of rolls that is not being shipped out to meet that week’s customer orders for which rolls were sliced.

company needs to determine how many 60-inch rolls are to be used to meet this week’s customer orders, totaling 48 12-inch wide rolls, 19 15-inch wide rolls, 22 20-inch wide rolls, 32 24-inch wide rolls, 14 30-inch wide rolls, and seven 40-inch wide rolls

Solutions

Expert Solution

Solution:

the various cutting alternatives for given types of output rolls:

Cutting Alternative

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Rolls (inches)

12

1

1

1

0

1

1

2

3

1

2

3

5

15

1

2

1

1

0

1

2

1

4

3

2

1

20

1

1

1

1

3

2

2

1

1

1

24

1

2

1

1

30

2

1

1

1

1

40

1

1

1

Waste

0

5

8

0

6

10

0

3

0

1

4

0

5

8

10

1

4

0

3

6

9

0

Decision Variable

X1

X2

X3

X4

X5

X6

X7

X8

X9

X10

X11

X12

X13

X14

X15

X16

X17

X18

X19

X20

X21

X22

Decision Variable:

xi be number of 60 inch rolls cut using cutting alternatives i, where i = 1, 2, 3, 4, 5, … , 22

Objective Function:

The objective is to minimize waste from 60-inch rolls to be produced by alternative cutting methods.

Objective function is formulated as:

Min Z. = 0x1 + 5x2 + 8x3 + 0x4 + x5 + … + 9x21 + 0x22

Subject to:

Minimum requirement of 12, 15, 20, 24, 32, and 40 inch rolls are 48, 19, 22, 32, 14, and 7 respectively.

Total units of 12 inch roll produced by cutting alternatives should be at least 48 units:

X8 + x9 + x11 + x14 + 2x16 + 3x17 + x19 + 2x20 + 3x21 + 5x22 48

Similarly, for other types of rolls.

All Xi are integers.

Excel Model:

Total number of 60” rolls required = 47

Total waste = 51”


Related Solutions

1. Solve the following integer optimization model by using Excel Solver: Maximize Z = 5x1 +...
1. Solve the following integer optimization model by using Excel Solver: Maximize Z = 5x1 + 6x2 Subject to 3x1 + 4x2 < 10 4x1 + 2x2 < 15      x1, x2 > 0 and integer Please show how to use the excel solver as well as steps. :)
Can you provide solution in the Excel using Solver for the below problem ? On Monday...
Can you provide solution in the Excel using Solver for the below problem ? On Monday morning, you have $3000 in cash on hand. For the next seven days, the following cash requirements must be met: Monday, $5000; Tuesday, $6000; Wednesday, $9000; Thursday, $2000; Friday, $7000; Saturday, $2000; Sunday, $3000. At the beginning of each day, you must decide how much money (if any) to withdraw from the bank. It costs $10 to make a withdrawal of any size. You...
4.B Construct an Excel model with solver to solve for the profit maximizing levels of price...
4.B Construct an Excel model with solver to solve for the profit maximizing levels of price and quantity for the profit function, Z = qp - cf - qcv, where cf = 8000, cv = 6, and the demand function for the product is q = 2400 - 24p. Illustrate the solution with a graph of the profit function, showing the profit maximizing price level. For an oligopoly as described in the chapter, construct an Excel model to solve for...
using Solver of excel please dont miss this part Solver of excel 11-34 OPTIMAL PRODUCTION MIX....
using Solver of excel please dont miss this part Solver of excel 11-34 OPTIMAL PRODUCTION MIX. Della Simpson Inc. sells two popular brands of cookies, Della’s Delight and Bonnie’s Bourbon. Della’s Delight goes through the Mixing and Baking Departments, and Bonnie’s Bourbon, a filled cookie, goes through the Mixing, Filling, and Baking departments. LO 2, 3, 5                                                                              Maximize $300D + $250 B where D = Della’s Delight and B = Bonnie’s Bourbon                                                    Michael Shirra, vice-president of sales, believes that...
Create a model and use Excel Solver to answer the following: A computer company manufactures two...
Create a model and use Excel Solver to answer the following: A computer company manufactures two types of computers. Each type of computer will require assembly time, inspection time, and storage space. The amounts of each of these resources that can be devoted to the production of the computers is limited. The manager wants to determine the quantity of each computer to produce to maximize the profit generated by sales of these computers. In order to develop a suitable model...
use Excel Solver to answer the following question.You must provide sufficient evidence that you did the...
use Excel Solver to answer the following question.You must provide sufficient evidence that you did the work on your own. For example, what equations did you use in your model? How was the excel spread sheet laid out? A student at a local university has just completed a decision modeling course. On her assignments, she has earned a 86 on the mid-term, a 94 on the final, a 93 on problem sets, and 85 for participation. She has a unique...
Solve the following LP problem using the Solver in MS Excel. A farmer wants to customize...
Solve the following LP problem using the Solver in MS Excel. A farmer wants to customize his fertilizer for his current crop. He can buy plant food mix A and plant food mix B. Each cubic yard of food A contains 20 pounds of phosphoric acid, 30 pounds of nitrogen and 5 pounds of potash. Each cubic yard of food B contains 10 pounds of phosphoric acid, 30 pounds of nitrogen and 10 pounds of potash. He requires a minimum...
Solve the following LP problem using the Solver in MS Excel.   A municipality has two incinerators...
Solve the following LP problem using the Solver in MS Excel.   A municipality has two incinerators for burning trash . Incinerator A costs $3 .80 per ton of trash to operate, and has a capacity of 28 tons per day . Incinerator B costs $4 .25 per ton to operate, and has a capacity of 30 tons per day . The municipality produces over 100 tons of trash per day, and all trash not burned in the incinerators must be...
SOLVE THE FOLLOWING 2 LINEAR PROGRAMMING PROBLEMS USING EXCEL AND THE SOLVER ADD-IN. PLEASE SHOW ME...
SOLVE THE FOLLOWING 2 LINEAR PROGRAMMING PROBLEMS USING EXCEL AND THE SOLVER ADD-IN. PLEASE SHOW ME ALL THE EXCEL STEPS. PROBLEM #1:   Maximize Z = $60X + $90Y                             Subject to:   60X + 30Y >= 1,500                                                     100X + 100Y <= 6,000                                                                              Y >= 30                                                                           X, Y >= 0 PROBLEM #2: Minimize Z = $3,000X + $1,000Y                              Subject to:   60X + 20Y >= 1,200                                                         10X + 10Y >= 400                                                     ...
How to solve using Excel Solver: This is an assignment problem with 10 applicants and 5...
How to solve using Excel Solver: This is an assignment problem with 10 applicants and 5 positions. Determine the optimal assignments that Brenda Last should make. Use the data to determine the optimal assignments, but do not complete questions in the last two paragraphs of the text Formulate a linear programming model for this problem. List the objective function (minimize or maximize) and all model constraints. Solve problem using MS Excel’s Solver Hint: Use the “integer” constraint Highlight the "winning"...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT