Functions of production planning and controlling is classified
into:
- Pre-planning function
- Planning function
- Control function
PRE-PLANNING FUNCTION
Pre-planning is a macro level planning based upon the forecasted
demand, market analysis and product design and development. It
deals with analysis of data. This stage is concerned with process
design such as new processes and developments, workflow (Plant
layout).
PLANNING FUNCTION
The planning function starts once the task to be accomplished is
specified, with the analysis of four M’s,
i.e., Machines, Methods, Materials and Manpower.
Standardization, simplification of products and
processes are given due consideration.
CONTROL FUNCTION
Control phase is effected by dispatching,
inspection and expediting materials control, analysis of
work-in-process. Finally, evaluation makes the PPC cycle complete
and corrective actions are taken through a feedback from analysis.
A good communication, and feedback system is essential to enhance
and ensure effectiveness of PPC.
Parameters for PPC
The functions of PPC can be explained with the following
parameters:
- Materials: Raw
materials, finished parts and bought out components should be made
available in required quantities and at required time to ensure the
correct start and end for each operation resulting in uninterrupted
production. The function includes the specification of materials
(quality and quantity) delivery dates, variety reduction
(standardization) procurement and make or buy decisions.
- Machines and equipment: This function
is related with the detailed analysis of available production
facilities, equipment down time, maintenance policy procedure and
schedules.
- Process planning (Routing):
It is concerned with selection of path or route which the raw
material should follow to get transformed into finished product.
The duties include:
- Fixation of path of travel giving due consideration to
layout.
- Breaking down of operations to define each operation in
detail.
- Deciding the set up time and process time for each
operation.
- Estimating:
Once the overall method and sequence of operations is fixed and
process sheet for each operation is available, then the operations
times are estimated. This function is carried out using extensive
analysis of operations along with methods and routing and a
standard time for operation are established using work measurement
techniques.
- Loading and scheduling:
Scheduling is concerned with preparation of machine loads and
fixation of starting and completion dates for each of the
operations. Machines have to be loaded according to their
capability of performing the given task and according to their
capacity.
- Loading, the machines as per their capability and
capacity.
- Determining the start and completion times for each
operation.
- To coordinate with sales department regarding delivery
schedules.
- Dispatching:
This is the execution phase of planning. It is the process of
setting production activities in motion through release of orders
and instructions. It authorizes the start of production activities
by releasing materials, components, tools, fixtures and instruction
sheets to the operator. The activities involved are:
- To assign definite work to definite machines, work centres and
men.
- To issue required materials from stores.
- To issue jigs, fixtures and make them available at correct
point of use.
- Release necessary work orders, time tickets, etc., to authorize
timely start of operations.
- To record start and finish time of each job on each machine or
by each man.
- Expediting:
It is logical step after dispatching
which is called ‘follow-up’. It coordinates extensively to execute
the production plan. Progressing function can be divided into three
parts, i.e., follow up of materials, follow up of
work-in-process and follow up of assembly.
- Inspection:
This forms the basis for knowing the limitations with respects to
methods, processes, etc., which is very much useful for evaluation
phase.
- Evaluation:
A thorough analysis of all the factors influencing the production
planning and control helps to identify the weak spots and the
corrective action with respect to pre-planning and planning will be
effected by a feedback.