Question

In: Accounting

At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that...

At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that had the following costs assigned from previous months:

Job Number Direct Labor Applied Overhead
SY-400 $ 23,340 ?
SY-403 15,420 ?

During the month, Jobs SY-400 and SY-403 were completed but not billed to customers. The completion costs for SY-400 required $25,800 in direct labor. For SY-403, $75,000 in labor was used.

During the month, the only new job, SY-404, was started but not finished. Total direct labor costs for all jobs amounted to $149,220 for the month. Overhead in this company refers to the cost of work that is not directly traced to particular jobs, including copying, printing, and travel costs to meet with clients. Overhead is applied at a rate of 60 percent of direct labor costs for this and previous periods. Actual overhead for the month was $92,000.

Required:

a. What are the costs of Jobs SY-400 and SY-403 at the beginning of the month and when completed?

b. What is the cost of Job SY-404 at the end of the month?

c. How much was under- or overapplied service overhead for the month?

Solutions

Expert Solution


Related Solutions

At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that...
At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that had the following costs assigned from previous months: Job Number Direct Labor Applied Overhead SY-400 $ 23,990 ? SY-403 16,070 ? During the month, Jobs SY-400 and SY-403 were completed but not billed to customers. The completion costs for SY-400 required $27,100 in direct labor. For SY-403, $81,500 in labor was used. During the month, the only new job, SY-404, was started but not...
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1,125 2,475 Balance, June 1 $7,875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...
Pincus Corporation, which uses a job-costing system, had two jobs in process at the start of...
Pincus Corporation, which uses a job-costing system, had two jobs in process at the start of 20x1: job no. 59 ($95,000) and job no. 60 ($39,500). The following information is available: • The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $720,000 and 20,000 hours, respectively. • The company worked on three jobs during the first quarter. Direct materials used, direct labor incurred, and machine hours...
At the start of the month, Oak Inc. had 58,000 units of beginning work in process...
At the start of the month, Oak Inc. had 58,000 units of beginning work in process that were 65% complete. Over the course of the month, the firm completed and transferred out 208,900 units, and at the end of the month, it had 59,400 units in ending work in process that were 70% complete. In comparison, Maple Inc. began the month with 61,200 units of beginning work in process that were 60% complete. Over the course of the month, the...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning ofMarch and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March):MoldingFabricationTotalEstimated total machine-hours used2,5001,5004,000Estimated total fixed manufacturing overhead$14,500$17,700$32,200Estimated variable manufacturing overhead per machine-hour$3.20$4.00Job PJob QDirect...
Sweeten Company had no jobs in progress at the beginning ofMarch and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March):MoldingFabricationTotalEstimated total machine-hours used2,5001,5004,000Estimated total fixed manufacturing overhead$11,250$15,750$27,000Estimated variable manufacturing overhead per machine-hour$1.90$2.70Job PJob QDirect...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT