Question

In: Accounting

At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information:

Job 44 Job 45
Direct materials $5,250 $1,600
Direct labor 1,500 3,300
Applied overhead 1,125 2,475
Balance, June 1 $7,875 $7,375

During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June:

Job 44 Job 45 Job 46 Job 47
Direct materials $2,300 $7,110 $1,750 $1,700
Direct labor 720 6,320 900 500

At the end of June, Jobs 44, 45, and 47 were completed. Only Job 45 was sold. On June 1, the balance in Finished Goods was zero.

Rhone Company

Job-Order Cost Sheets

For the Month of June

1

Job 44

Job 45

Job 46

Job 47

2

Beginning balance, June 1

7875

7375

0

0

3

Direct materials

2300

7110

1750

1750

4

Direct labor

720

6320

900

5

Applied overhead

6

Total, June 30

Calculate the ending balances of Work in Process and Finished Goods as of June 30.

Work in Process:
Finished Goods:

4. Calculate the Cost of Goods Sold for June.

Cost of Goods Sold:

Solutions

Expert Solution


Related Solutions

Everbuilt Company had no jobs in progress at the beginning of June and no beginning inventories....
Everbuilt Company had no jobs in progress at the beginning of June and no beginning inventories. It started only two jobs during June—Job L and Job W. Job L was completed and sold by the end of June and Job W was incomplete at the end of June. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs L and W (all data...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q.
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that...
At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that had the following costs assigned from previous months: Job Number Direct Labor Applied Overhead SY-400 $ 23,990 ? SY-403 16,070 ? During the month, Jobs SY-400 and SY-403 were completed but not billed to customers. The completion costs for SY-400 required $27,100 in direct labor. For SY-403, $81,500 in labor was used. During the month, the only new job, SY-404, was started but not...
At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that...
At the beginning of the month, Arthur's Olde Consulting Corporation had two jobs in process that had the following costs assigned from previous months: Job Number Direct Labor Applied Overhead SY-400 $ 23,340 ? SY-403 15,420 ? During the month, Jobs SY-400 and SY-403 were completed but not billed to customers. The completion costs for SY-400 required $25,800 in direct labor. For SY-403, $75,000 in labor was used. During the month, the only new job, SY-404, was started but not...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job Cost Sheets are placed on the Answers Sheets. Company applies factory overhead using activity based costing. The predetermined overhead rates for activities are as follows:                                                                                           Machine Setup Activity                      Inspection Activity Overhead Rate                                                                 $120 per machine setup                    $75 per inspection    On the space provided on the answer sheet, provide journal entries for the following transactions. Complete Job Cost Sheets as needed. If you wish, you may...
ABC Company uses a job order costing system and had three jobs in process at the...
ABC Company uses a job order costing system and had three jobs in process at the beginning of the month. The beginning balance in the WIP account was $145,400, made up of $42,400, $65,100, and $37,900 as shown on the cost sheets for Jobs 921, 922, and 923 respectively. During the month, ABC added the following materials and labor costs to each job. Inventory Materials used for Month Labor Dollars used for Month Job 921 12,200 30,000 Job 922 13,400...
Pincus Corporation, which uses a job-costing system, had two jobs in process at the start of...
Pincus Corporation, which uses a job-costing system, had two jobs in process at the start of 20x1: job no. 59 ($95,000) and job no. 60 ($39,500). The following information is available: • The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $720,000 and 20,000 hours, respectively. • The company worked on three jobs during the first quarter. Direct materials used, direct labor incurred, and machine hours...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning ofMarch and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March):MoldingFabricationTotalEstimated total machine-hours used2,5001,5004,000Estimated total fixed manufacturing overhead$14,500$17,700$32,200Estimated variable manufacturing overhead per machine-hour$3.20$4.00Job PJob QDirect...
Sweeten Company had no jobs in progress at the beginning ofMarch and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March):MoldingFabricationTotalEstimated total machine-hours used2,5001,5004,000Estimated total fixed manufacturing overhead$11,250$15,750$27,000Estimated variable manufacturing overhead per machine-hour$1.90$2.70Job PJob QDirect...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT