In: Operations Management
Microsoft Project Case:
Shoreline Stadium Case
The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 1, 2020, and be completed in time for the start of the 2023 season in April. A penalty clause of $250,000 per day of delay beyond April 1st is written into the contract.
Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.
Questions:
Given the information provided in Table 6.3, using any project network computer program available to you to construct a network schedule for the stadium project and answer the following questions:
TABLE 6.3 Shoreline Stadium Case
ID |
Activity |
Duration |
Predecessor(s) |
1 |
Baseball Stadium |
||
2 |
Clear stadium site |
70 days |
— |
3 |
Demolish building |
30 days |
2 |
4 |
Set up construction site |
70 days |
3 |
5 |
Drive support piling |
120 days |
4 |
6 |
Pour lower concrete bowl |
120 days |
5 |
7 |
Pour main concourse |
120 days |
6 |
8 |
Install playing field |
90 days |
6 |
9 |
Construct upper steel bowl |
120 days |
6 |
10 |
Install seats |
140 days |
9 |
11 |
Build luxury boxes |
90 days |
9 |
12 |
Install jumbotron |
30 days |
9 |
13 |
Stadium infrastructure |
120 days |
9 |
14 |
Construct steel canopy |
75 days |
10 |
15 |
Light installation |
30 days |
10 |
16 |
Build roof supports |
90 days |
4 |
17 |
Construct roof |
180 days |
16 |
18 |
Install roof tracks |
90 days |
14 |
19 |
Install roof |
90 days |
17, 18 |
20 |
Inspection |
20 days |
8, 11, 13, 15, 19 |
Attach the Microsoft Project file or a screenshot of the
Gantt chart.
Thank you, I will give you thumbs up!
Before entering anything, make the following two changes:
Go to Project --> Projet Information and change the start date and current date:
Make all tasks auto-scheduled by default by clicking in the left bottom corner:
After this make the entries as follows:
Go to Go to Project --> Projet Information --> Statistics to note the completion date:
Go to the 'Detailed Gantt' view to develop the Gatt chart. The critical path will be in 'red' color.
So,
the critical path is 2-3-4-5-6-9-10-14-18-19-20
Case-1: The working time is standard S-Su off i.e. 5 days a week
The completion date is 13-02-24 and the target date was 01-04-23. So, there is a delay of 318 days.
Total penalty will be 318 * $250,000 = $79,500,000
The return from the project is only $3,000,000. So, the project is not worthy if the standard calendar of S-Su off is followed throughout.
Case-2: The working is 24 x 7. So, the 945 days competition time will lead to competition date = 01-Feb-2023
In this case, there will be no penalty and hence the project will be viable.