Suppose that the specification limits for a production process are LSL = 0.02 and USL = 0.10, with the nominal specification being 0.06.

a)_____________ What is the sigma level if the process standard deviation is 0.01.

b)_____________ If the process is centered, what is the DPMO?

Solutions

Expert Solution

Please find the attached answer..


Related Solutions

A process has a Cpk = 1.35 and is centered between the specification limits. (a) What...
A process has a Cpk = 1.35 and is centered between the specification limits. (a) What is the DPM of the process? (b) If the mean of the process increases by 1.5σ the DPM would be?
What is the difference between control limits and specification limits?
What is the difference between control limits and specification limits?
Briefly discuss control limits versus specification limits.
Briefly discuss control limits versus specification limits.
What is the difference between a prescriptive specification and a performance standard for the production of...
What is the difference between a prescriptive specification and a performance standard for the production of wood structural panels?
Determine the process capability performance metrics using Minitab of a process that had a lower specification...
Determine the process capability performance metrics using Minitab of a process that had a lower specification of 2 and an upper specification of 16 with the following responses:
Suppose the current exchange rate between Euro and YEN is 0.02.
Suppose the current exchange rate between Euro and YEN is 0.02. The euro-denominated annual continuously compounded risk-free rate is 4% and the yen-dominated annual continuously compounded risk- free rate is 1%. What are the 6-month euro/yen and yen/euro forward prices?
Statistical process control charts: A. display upper and lower limits for process variables or attributes and...
Statistical process control charts: A. display upper and lower limits for process variables or attributes and signal when a process is no longer in control. B. display the measurements on every item being produced. C. are a graphic way of classifying problems by their level of importance, often referred to as the 80-20 rule. D. indicate to the process operator the average outgoing quality of each lot. E. indicate to the operator the true quality of material leaving the process.
A process is in control and normally distributed with ? control chart limits of 45 and...
A process is in control and normally distributed with ? control chart limits of 45 and 15. The subgroup size is 4. Suppose the process variance suddenly triples while process mean remains unchanged. What is the probability that the first subsequent subgroup average will fall outside the control limits? What are the ? probability and ARL? Suppose the process variance suddenly triples while process mean shifts downward to 10. What are the β probability and ARL now?
a process in statistical control has a mean of .3119 and specification limit of .307 to...
a process in statistical control has a mean of .3119 and specification limit of .307 to .317. if the standard deviation of the process is .0013, what percent of the process output is expected to be below the specification limit?
The weight specification for packets of noodles is 150±10 grams. The packet-filling process is in a...
The weight specification for packets of noodles is 150±10 grams. The packet-filling process is in a state of statistical control and the packet weights are normally distributed with a standard deviation of 1.5 grams. However, the process is not centered at 150 grams. a)Find the value for process mean so that only 4 packets in 1000 fall below the lower specification. b)For the value of the process mean you found in part (i), what percent of the packets will be...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT