Question

In: Finance

As the financial manager of the firm, you are given 6 future projects with their expected cost and yearly profits.

 

Problem 1:

As the financial manager of the firm, you are given 6 future projects with their expected cost and yearly profits.

Year

Project A

Project B

Project C

Project D

Project E

0

-$500,000.00

-$400,000.00

-$300,000.00

-$200,000.00

-$100,000.00

1

$135,000.00

$112,500.00

$90,000.00

$57,500.00

$30,000.00

2

$145,000.00

$125,000.00

$90,000.00

$62,500.00

$32,000.00

3

$155,000.00

$130,000.00

$90,000.00

$67,500.00

$34,000.00

4

$165,000.00

$135,000.00

$90,000.00

$70,000.00

$36,000.00

5

$175,000.00

$140,000.00

$90,000.00

$72,500.00

$38,000.00

  1. Calculate the NPV for each project if the company has a 10% discount rate
  2. Calculate the IRR for each project if you can finance and reinvest at 10%
  3. Your firm has a budget constraint of $800,000. Based on this constraint, which projects should the company implement?

Solutions

Expert Solution

Using excel formula to calculate NPV and IRR

A B C D E
Year Project A Project B Project C Project D Project E
1 0 ($500,000.00) ($400,000.00) ($300,000.00) ($200,000.00) ($100,000.00)
2 1 $135,000.00 $112,500.00 $90,000.00 $57,500.00 $30,000.00
3 2 $145,000.00 $125,000.00 $90,000.00 $62,500.00 $32,000.00
4 3 $155,000.00 $130,000.00 $90,000.00 $67,500.00 $34,000.00
5 4 $165,000.00 $135,000.00 $90,000.00 $70,000.00 $36,000.00
6 5 $175,000.00 $140,000.00 $90,000.00 $72,500.00 $38,000.00
NPV $80,374.23 $82,385.24 $41,170.81 $47,467.11 $27,447.21
EXCEL FORMULA A1+NPV(0.1,A2:A6) B1+NPV(0.1,B2:B6) C1+NPV(0.1,C2:C6) D1+NPV(0.1,D2:D6) E1+NPV(0.1,A2:A6)
IRR 15.83% 17.47% 15.24% 18.53% 19.80%
EXCEL FORMULA IRR(A1:A6) IRR(B1:B6) IRR(C1:C6) IRR(D1:D6) IRR(E1:E6)

C. Based on NPV projects should be selected. Selecting Project B,D and E would give highest NPV  


Related Solutions

A risk neutral firm (seeking to maximize expected profits) can choose between two mutually exclusive projects....
A risk neutral firm (seeking to maximize expected profits) can choose between two mutually exclusive projects. One project yields a profit of 10 with certainty. The other project is risky, and yields a profit of 40 and a loss of 10, each with 50 percent chance. The government is levying a tax on profits, denoted by 0<t<1. In case the firm suffers from losses (negative profits), the (negative) tax is neither refundable nor can the losses be carried forward and...
2. Given the following expected cash flows for two projects, and an opportunity cost of capital...
2. Given the following expected cash flows for two projects, and an opportunity cost of capital of 10%, which project is better and why? (10 points)             Expected Net Cash Flows Year    Project A         Project B 0          -$10,000          -$10,000 1          $5000              $0 2          $5000              $0 3          $5000              $8,000 4          $5000              $2,000 3. Given the following expected cash flows for two projects, and an opportunity cost of capital of 8%, which project is better and why? (10 points)             Expected Net...
A new machine will cost $150,000 to place into operation. It is expected to have yearly...
A new machine will cost $150,000 to place into operation. It is expected to have yearly cash flows of $50,000 for the first five years. The company required rate of return is 9%. 1. Compute the Project's NPV. 2. Compute the Project's IRR. 3. How long is the project's payback period? 4. How long is the project's discounted payback period?
Should a financial manager pursue projects whose expected returns are less than the firm’s weighted average...
Should a financial manager pursue projects whose expected returns are less than the firm’s weighted average cost of capital (WACC)? Explain your answer.
The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have a 12% cost of capital.
                                                                                 Expected Net Cash Flows                                             Year                    Project T                               Project F                                                0                      ($100,000)                            ($100,000)                                                1                           75,000                                  40,000                                                2                           65,000                                  42,000                                                3                              —                                      44,000                                                4                              —                                      46,000 The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have a 12% cost of capital. a.   What is each project’s initial NPV without replication? b.   What is each project’s equivalent annual annuity? c.   Suppose you replicate Project T so...
You are the chief financial officer of a firm. The firm has an expected liability (cash...
You are the chief financial officer of a firm. The firm has an expected liability (cash outflow) of $2 million in ten years at a discount rate of 5%. Calculate the amount the firm would need on the present date as savings to cover the expected liability. Calculate the amount the firm would need to set aside at the end of each year for the next ten years to cover the expected liability. Explain the specific business decision that management...
You are a manager of a monopoly, and your demand and cost functions are given by...
You are a manager of a monopoly, and your demand and cost functions are given by P =220 -2Q and C(Q) = 2000 + 10 Q2 What Price maximizes your profit
You are the financial manager of a firm manufacturing headphones. You just announced that this year’s...
You are the financial manager of a firm manufacturing headphones. You just announced that this year’s profits are $2 million. Analysts predict your profits will grow at 5% each year for the next three years and then profit growth will slow to 3%per year and will continue growing at 3%in perpetuity. Assuming an opportunity cost of capital of 5%per year, what is the present value of your future (not counting this year) projected profits? what is the present of your...
You are the financial manager for a firm and the product development team has proposed the...
You are the financial manager for a firm and the product development team has proposed the development of a software product that will cost $1,000,000 currently to produce but will bring in cashflows of $200,000 for the next 6 years. You know that the firm can invest the firm’s retained earnings in the stock market and earn 6% over the same period. Should you greenlight the development of the new product or not? If you only expect to earn 5%...
Over the next three years, a firm is expected to earn economic profits of $60,000 in...
Over the next three years, a firm is expected to earn economic profits of $60,000 in the first year, $50,000 in the second year, and $20,000 in the third year. After the end of the third year, the firm will go out of business. a. If the risk-adjusted discount rate is 6 percent for each of the next three years, the value of the firm is $________. The firm can be sold today for a price of $________. b. If...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT