In: Finance
Problem 1:
As the financial manager of the firm, you are given 6 future projects with their expected cost and yearly profits.
Year |
Project A |
Project B |
Project C |
Project D |
Project E |
0 |
-$500,000.00 |
-$400,000.00 |
-$300,000.00 |
-$200,000.00 |
-$100,000.00 |
1 |
$135,000.00 |
$112,500.00 |
$90,000.00 |
$57,500.00 |
$30,000.00 |
2 |
$145,000.00 |
$125,000.00 |
$90,000.00 |
$62,500.00 |
$32,000.00 |
3 |
$155,000.00 |
$130,000.00 |
$90,000.00 |
$67,500.00 |
$34,000.00 |
4 |
$165,000.00 |
$135,000.00 |
$90,000.00 |
$70,000.00 |
$36,000.00 |
5 |
$175,000.00 |
$140,000.00 |
$90,000.00 |
$72,500.00 |
$38,000.00 |
Using excel formula to calculate NPV and IRR
A | B | C | D | E | ||
Year | Project A | Project B | Project C | Project D | Project E | |
1 | 0 | ($500,000.00) | ($400,000.00) | ($300,000.00) | ($200,000.00) | ($100,000.00) |
2 | 1 | $135,000.00 | $112,500.00 | $90,000.00 | $57,500.00 | $30,000.00 |
3 | 2 | $145,000.00 | $125,000.00 | $90,000.00 | $62,500.00 | $32,000.00 |
4 | 3 | $155,000.00 | $130,000.00 | $90,000.00 | $67,500.00 | $34,000.00 |
5 | 4 | $165,000.00 | $135,000.00 | $90,000.00 | $70,000.00 | $36,000.00 |
6 | 5 | $175,000.00 | $140,000.00 | $90,000.00 | $72,500.00 | $38,000.00 |
NPV | $80,374.23 | $82,385.24 | $41,170.81 | $47,467.11 | $27,447.21 | |
EXCEL FORMULA | A1+NPV(0.1,A2:A6) | B1+NPV(0.1,B2:B6) | C1+NPV(0.1,C2:C6) | D1+NPV(0.1,D2:D6) | E1+NPV(0.1,A2:A6) | |
IRR | 15.83% | 17.47% | 15.24% | 18.53% | 19.80% | |
EXCEL FORMULA | IRR(A1:A6) | IRR(B1:B6) | IRR(C1:C6) | IRR(D1:D6) | IRR(E1:E6) |
C. Based on NPV projects should be selected. Selecting Project B,D and E would give highest NPV