In: Finance
A new machine will cost $150,000 to place into operation. It is expected to have yearly cash flows of $50,000 for the first five years. The company required rate of return is 9%.
1. Compute the Project's NPV.
2. Compute the Project's IRR.
3. How long is the project's payback period?
4. How long is the project's discounted payback period?
Answer =1 | |||||||||
Years | Cash Flows | PVF @ 9% | Present Value | ||||||
0 | -$1,50,000 | 1 | -$1,50,000.00 | ||||||
1 | $50,000 | 0.9174 | $45,871.56 | ||||||
2 | $50,000 | 0.8417 | $42,084.00 | ||||||
3 | $50,000 | 0.7722 | $38,609.17 | ||||||
4 | $50,000 | 0.7084 | $35,421.26 | ||||||
5 | $50,000 | 0.6499 | $32,496.57 | ||||||
Total | $1,00,000 | $44,483 | |||||||
Answer =3) | |||||||||
CALCULATION OF THE PAYBACK PERIOD OF THE PROJECT | |||||||||
Years | Cash Flows | Cumulative Cash Flow | |||||||
0 | -$1,50,000 | -$1,50,000.00 | |||||||
1 | $50,000 | -$1,00,000.00 | |||||||
2 | $50,000 | -$50,000.00 | |||||||
3 | $50,000 | $0.00 | |||||||
4 | $50,000 | $50,000.00 | |||||||
5 | $50,000 | $1,00,000.00 | |||||||
Total | $1,00,000 | ||||||||
All the money invested is came full in the 3rd year so payback period is 3 years | |||||||||
Answer = 4 years | |||||||||
Years | Cash Flows | PVF @ 9% | Present Value | Cumulative Value | |||||
0 | -$1,50,000 | 1 | -$1,50,000.00 | -$1,50,000.00 | |||||
1 | $50,000 | 0.9174 | $45,871.56 | -$1,04,128.44 | |||||
2 | $50,000 | 0.8417 | $42,084.00 | -$62,044.44 | |||||
3 | $50,000 | 0.7722 | $38,609.17 | -$23,435.27 | |||||
4 | $50,000 | 0.7084 | $35,421.26 | $11,985.99 | |||||
5 | $50,000 | 0.6499 | $32,496.57 | $44,482.56 | |||||
Total | $1,00,000 | $44,483 | |||||||
In the 4th year all the money is recovered , but not full year is required, | |||||||||
So Payback period = 3 Years + $ 23,435.27 / $ 35,421.26 | |||||||||
So Payback period = 3 Years + 0.66 Years | |||||||||
So Payback period = 3.66 Years | |||||||||
Answer = 1 | |||||||||
IRR : IRR Means with a particular Percentage rate , At that point the present value become the zero | |||||||||
CALCULATION OF THE IRR OF THE PROJECT | |||||||||
First we calculate randomly present value with @ 19% discounting rate | |||||||||
Years | Cash Flows | PVF @19% | Present Value | ||||||
0 | -$1,50,000 | 1 | -$1,50,000.00 | ||||||
1 | $50,000 | 0.8403 | $42,016.81 | ||||||
2 | $50,000 | 0.7062 | $35,308.24 | ||||||
3 | $50,000 | 0.5934 | $29,670.79 | ||||||
4 | $50,000 | 0.4987 | $24,933.44 | ||||||
5 | $50,000 | 0.4190 | $20,952.47 | ||||||
Net Present Value = | $2,881.74 | ||||||||
With PVF of 19% we are getting positive = | $2,881.74 | ||||||||
Secondly we calculate randomly present value @ 20 % discounting rate | |||||||||
Years | Cash Flows | PVF @ 20% | Present Value | ||||||
0 | -$1,50,000 | 1 | -$1,50,000.00 | ||||||
1 | $50,000 | 0.8333 | $41,666.67 | ||||||
2 | $50,000 | 0.6944 | $34,722.22 | ||||||
3 | $50,000 | 0.5787 | $28,935.19 | ||||||
4 | $50,000 | 0.4823 | $24,112.65 | ||||||
5 | $50,000 | 0.4019 | $20,093.88 | ||||||
Net Present Value = | -$469.39 | ||||||||
With PVF of 20 % we are getting negative = | -469.39 | ||||||||
In the given case the pv with 19% is coming to postive means the present value is more | |||||||||
then 19 % but with 20 % Present value cash flow become negative so the present value | |||||||||
is between 19% and 20 % | |||||||||
So the differecne in both % net present value is = | $2,881.74 | - | -$469.39 | ||||||
Total is become = | $3,351.14 | ||||||||
So , the difference % = | $2,881.74 | "/"By | $3,351.14 | ||||||
So , the difference % = | 0.86 | ||||||||
So, the IRR = | 19.86% | ||||||||
Answer = IRR = | 19.86% | ||||||||