In: Accounting
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 21,000 16,800 Work in process units, July 31 3,150 525 Work in process percent complete 60 80 Cost Data—July Work in process, July 1 $0 $0 Materials 399,000 302,400 Labor 246,120 115,500 Overhead 109,200 110,040 Total $754,320 $527,940 (a1) Your answer is correct. For each plant compute the physical units of production. T12 Tables C10 Chairs Units to be accounted for Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Attempts: 1 of 3 used (a2) Your answer is correct. For each plant compute equivalent units of production for materials and for conversion costs. Materials Conversion Costs T12 Tables C10 Chairs Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Attempts: 1 of 3 used (a3) Your answer is correct. For each plant determine the unit costs of production. (Round unit costs to 2 decimal places, e.g. 5.25.) Materials Conversion Costs Total Costs Unit costs-T12 Tables $ $ $ Unit costs-C10 Chairs $ $ $ Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Attempts: 1 of 3 used (a4) For each plant show the assignment of costs to units transferred out and in process. T12 Tables Costs accounted for: Transferred out $ Work in process Materials $ Conversion costs Total costs $ C10 Chairs Costs accounted for: Transferred out $ Work in process Materials $ Conversion costs Total costs $
a(4) | ||||
T12 Tables | ||||
Costs accounted for: | ||||
Transferred out | 660450 | =17850*37 | ||
Work in process | ||||
Materials | 59850 | =(3150*19) | ||
Conversion costs | 34020 | 93870 | =1890*18 | |
Total costs | 754320 | |||
C10 Chairs | ||||
Costs accounted for: | ||||
Transferred out | 512825.25 | =16275*31.51 | ||
Work in process | ||||
Materials | 9450.00 | =525*18 | ||
Conversion costs | 5674.20 | 15124.20 | =420*13.51 | |
Total costs | 527949.45 | |||
Alternatively: | ||||
C10 Chairs | ||||
Costs accounted for: | ||||
Transferred out | 512825 | |||
Work in process | ||||
Materials | 9450 | |||
Conversion costs | 5674 | 15124 | ||
Total costs | 527949 | |||
Workings: | ||||
T12 Tables | C10 Chairs | |||
Materials | Conversion Costs | Materials | Conversion Costs | |
Units completed and transferred out | 17850 | 17850 | 16275 | 16275 |
Work in process units, July 31 | 3150 | 1890 | 525 | 420 |
Equivalent units of production | 21000 | 19740 | 16800 | 16695 |
T12 Tables | C10 Chairs | |||
Materials | Conversion Costs | Materials | Conversion Costs | |
Total costs | 399000 | 355320 | 302400 | 225540 |
Divide by Equivalent units of production | 21000 | 19740 | 16800 | 16695 |
Unit costs of production | 19.00 | 18.00 | 18.00 | 13.51 |