Question

In: Finance

Find MIRR for the project with a cost of -$20,000 and subsequent cash flows of 10,000;...

Find MIRR for the project with a cost of -$20,000 and subsequent cash flows of 10,000; $40,000; - $5,000; -$30,000. Use WACC of 6%. Will you proceed with this project? Why or why not?

Solutions

Expert Solution

Combination approach
All negative cash flows are discounted back to the present and all positive cash flows are compounded out to the end of the project’s life
Thus year 4 modified cash flow=(11910.16)+(44944)
=56854.16
Thus year 0 modified cash flow=-20000-4198.1-23762.81
=-47960.91
Discount rate 6.000%
Year 0 1 2 3 4 5
Cash flow stream -20000.000 10000.000 40000.000 -5000.000 -30000.000 0.000
Discount factor 1.000 1.060 1.124 1.191 1.262 1.338
Compound factor 1.000 1.191 1.124 1.060 1.000 0.943
Discounted cash flows -20000.000 0 0 -4198.1 -23762.81 0
Compounded cash flows 0.000 11910.16 44944 0 0 0
Modified cash flow -47960.910 0 0 0 56854.160 0
Discounting factor (using MIRR) 1.000 1.043 1.089 1.136 1.185 1.237
Discounted cash flows -47960.910 0.000 0.000 0.000 47960.910 0.000
NPV = Sum of discounted cash flows
NPV= 0.00
MIRR is the rate at which NPV = 0
MIRR= 4.34%
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Compounding factor = (1 + reinvestment rate)^(time of last CF-Corresponding period in years)
Compounded Cashflow= Cash flow stream*compounding factor

Donot proceeds with the project as MIRR is less than WACC


Related Solutions

find MIRR for a project with a cost of -$20,000 and subsequent cash flows of 10,000;...
find MIRR for a project with a cost of -$20,000 and subsequent cash flows of 10,000; $40,000, -$5,000; -$30,000. use wacc of 6%. will you proceed with this project? why or why not ?
Xcel is considering a project that has a cost of $12mi, and subsequent cash flows of...
Xcel is considering a project that has a cost of $12mi, and subsequent cash flows of 3.9mi. for the next 5 years. The firm recognizes that if it waits 1 year, it would have more information about the project, but the cost can go up to $13 mi. There is a 70% chance that market conditions will be favorable if Xcel waits a year, in which case the project will generate net cash flow of $4.6mi. for 5 years. There...
What is the MIRR of project with the following cash flows? The discounting rate is 14%....
What is the MIRR of project with the following cash flows? The discounting rate is 14%. Year Cash Flow 0 -1,200,000 1 400,000 2 500,000 3 500,000 4 500,000 5 500,000 6 500,000
What is NPV, IRR, PI, MIRR of a project with the following cash flows if the...
What is NPV, IRR, PI, MIRR of a project with the following cash flows if the discount rate is 14 percent? Year CF 0 -18,000    1 5000 2 7500 3 8400 4 2100 Also upload your excel files showing your work.
If a project has a cost of $10,000, expected net cash flows of $1500 a year...
If a project has a cost of $10,000, expected net cash flows of $1500 a year for 12 years and you use a discount rate of 6%, what is the following: Payback period (no application of discount rate) Payback period (using discount rate) NPV IRR Should the project be accepted? If another project has a cost of $10,000 and has expected life of 8 years and it will generate $3000 a year should you accept the project if your boss...
8. Project R has a cost of $ 10,000 and in expected to produce cash flows...
8. Project R has a cost of $ 10,000 and in expected to produce cash flows per year of $ 4,000 for 3 years. Project S has a cost of $20,000 and in expected to produce cash flows of $ 7,000 per year for 4 years. Calculate the 2 projects' NPVs, IRRs, MIRRs, and PIs, assuming a cost of capital of 11%. Which project should be selected ?
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they are mutually exclusive?...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $4,000 per year for 5 years. Project L costs $21,000 and is expected to produce cash flows of $8,000 per year for 5 years. Calculate the two projects’ NPVs, IRRs, MIRRs, PIs, and Pay Back Period assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they are mutually exclusive?...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' PIs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to three decimal places. Project S:   Project L:  
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT