Question

In: Finance

14. Following is project A's cash flow table Year Cash Flow 0 -26,000 1 6,200 2...

14.

Following is project A's cash flow table

Year

Cash Flow

0

-26,000

1

6,200

2

6,200

3

6,200

4

6,200

5

9,700

Assuming that the project is found by 40% of equity and 60% of debt. The required rate of return of equity is 10%. The yield of debt is 6% and the tax rate is 30%.

Using the above information to answer Q1 - Q4.

Q1) What is the WACC of this project?

a)6.52%

b)4%

c)7.43%

d)5%

Q2) What is the NPV of this project?

a) 2303.50

b) 2823.21

c) 2795.86

d) 2187.62

Q3) What is the IRR of this project?

a) 10.27%

b) 9.54%

c) 8.78%

d) 9.23%

Q4) Should we invest in this project?

a) No, because the project payback year is too long

b) No, because the IRR is too low

c) Yes, because the project NPV is greater than 0

d) Not sure

Solutions

Expert Solution

1

Weight of equity = 1-D/A
Weight of equity = 1-0.6
W(E)=0.4
Weight of debt = D/A
Weight of debt = 0.6
W(D)=0.6
After tax cost of debt = cost of debt*(1-tax rate)
After tax cost of debt = 6*(1-0.3)
= 4.2
WACC=after tax cost of debt*W(D)+cost of equity*W(E)
WACC=4.2*0.6+10*0.4
WACC =6.52%

2

Project
Discount rate 6.520%
Year 0 1 2 3 4 5
Cash flow stream -26000 6200 6200 6200 6200 9700
Discounting factor 1.000 1.065 1.135 1.209 1.287 1.371
Discounted cash flows project -26000.000 5820.503 5464.235 5129.774 4815.785 7073.200
NPV = Sum of discounted cash flows
NPV Project = 2303.50
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

3

IRR is the rate at which NPV =0
IRR 9.54%
Year 0 1 2 3 4 5
Cash flow stream -26000.000 6200.000 6200.000 6200.000 6200.000 9700.000
Discounting factor 1.000 1.095 1.200 1.314 1.440 1.577
Discounted cash flows project -26000.000 5659.965 5166.968 4716.913 4306.058 6150.097
NPV = Sum of discounted cash flows
NPV Project = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 9.54%

4


Related Solutions

A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000...
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000 2 – 37,000 What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR % What is the NPV of this project, if the required return is 12 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2 Cash Flow Year 3 Cash Flow Year 4 Cash Flow Discount Rate A -100 40 50 60 N/A .15 B -73 30 30 30 30 .15 Assume that projects A and B are mutually exclusive. The correct investment decision and the best rational for that decision is to: Group of answer choices a.invest in project A since NPVB < NPVA. b.invest in project B...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2 8,100 3 6,600 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the NPV...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2 –27,600 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2 –48,100    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 11.5 percent?    c. NPV at 0 percent?    d. NPV at 23 percent?
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2 7,600 3 6,100     What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)      NPV $       What is the NPV at a discount rate of 9 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      NPV $   ...
There is a project with the following cash flows : Year Cash Flow 0 −$21,800 1...
There is a project with the following cash flows : Year Cash Flow 0 −$21,800 1 6,300 2 7,350 3 6,750 4 4,400 What is the payback period? Multiple Choice a. 4.00 years b. 3.32 years c. 3.74 years d. 3.56 years e. 2.79 years
There is a project with the following cash flows : Year Cash Flow 0 −$23,700 1...
There is a project with the following cash flows : Year Cash Flow 0 −$23,700 1 7,000 2 7,700 3 7,100 4 5,100 What is the payback period? Multiple Choice 2.73 years 4.00 years 3.81 years 3.63 years 3.37 years
4. A project has the following cash flows Year Cash Flow 0 58000 1 -34000 2...
4. A project has the following cash flows Year Cash Flow 0 58000 1 -34000 2 -45000 a) What is the IRR for this project? If the required rate of return is 12%, should the firm accept the project? b) What is the NPV for this project? What is the NPV for the project if the required rate of return is 0%? 24%? What is going on here? Sketch the NPV profile to help with your answer
A project has the following cash flows:    Year Cash Flow 0 $ 43,500 1 –  ...
A project has the following cash flows:    Year Cash Flow 0 $ 43,500 1 –   22,500 2 –   33,500    a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project, if the required return is 12 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT