In: Accounting
Abc inc. is planning the production schedule for the next 8 weeks. the forecasted demand for the next 8 weeks is 700, 800, 900, 500, 1100, 1000, 800, and 900 respectively. abc can produce 800 units per week in regular time and 200 more in overtime. the regular time production cost is $10.00 per unit which takes into account $4.00 for materials, $1.00 for utilities, and $5.00 for manpower. the manpower cost for overtime is twice the regular rate. holding a unit in inventory costs $1 per unit per week. there is also a cost for been late, at $2.00 per unit per week. the maximum lateness allowed is 2 weeks. it is the company's policy not to have any item in inventory for more than 3 weeks. how much should abc produce each week?
There are two options for the company to produce:
First option:
Produce 800 units per week:
Particulars |
Week 1 |
Week 2 |
Week 3 |
Week 4 |
Week 5 |
Week 6 |
Week 7 |
Week 8 |
|
700 |
800 |
900 |
500 |
1100 |
1000 |
800 |
900 |
|
800 |
800 |
800 |
800 |
800 |
800 |
800 |
800 |
|
100 |
- |
- (since earlier excess utilized after 2 weeks) |
300 |
- (since utilised excess 300 units after 1 week) |
200 |
- |
- (since utilised excess 100 units after 2 weeks) |
|
$10 |
$10 |
$10 |
$10 |
$10 |
$10 |
$10 |
$10 |
|
$8,000 |
$8,000 |
$8,000 |
$8,000 |
$8,000 |
$8,000 |
$8,000 |
$8,000 |
f.)Overtime cost |
- |
- |
- |
- |
- |
- |
- |
- |
g.)Inventory Holding cost |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
h.)Total Holding cost (g*c) |
(100*2)= $200 |
- |
- |
(300*1)=$300 |
- |
- |
- |
(200*2)=$400 |
i.)Total All cost = (e+h) |
8200 |
8000 |
8000 |
8300 |
8000 |
8000 |
8000 |
8400 |
Therefore, total cost of Regular production= $(8200+8000+8000+8300+8000+8000+8000+8400)= $64,900
Second option:
Produce as required units per week:
Particulars |
Week 1 |
Week 2 |
Week 3 |
Week 4 |
Week 5 |
Week 6 |
Week 7 |
Week 8 |
|
700 |
800 |
900 |
500 |
1100 |
1000 |
800 |
900 |
|
700 |
800 |
900 |
500 |
1100 |
1000 |
800 |
900 |
|
- |
- |
100 |
- |
300 |
200 |
- |
100 |
|
$10 |
$10 |
$10 |
$10 |
$10 |
$10 |
$10 |
$10 |
|
$7,000 |
$8,000 |
$9,000 |
$5,000 |
$11,000 |
$10,000 |
$8,000 |
$9,000 |
f.) Extra Overtime production cost |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
g.)Total overtime production cost= f*c |
- |
- |
1500 |
- |
4500 |
3000 |
- |
1500 |
h.)Total All cost = (e+g) |
7000 |
8000 |
10,500 |
5000 |
15500 |
13000 |
8000 |
10,500 |
Therefore, total cost of Regular production= $(7000+8000+10500+5000+15500+13000+8000+10500)= $77500
First option to produce 800 units per week is the best.