Question

In: Accounting

Abc inc. is planning the production schedule for the next 8 weeks. the forecasted demand for...

Abc inc. is planning the production schedule for the next 8 weeks. the forecasted demand for the next 8 weeks is 700, 800, 900, 500, 1100, 1000, 800, and 900 respectively. abc can produce 800 units per week in regular time and 200 more in overtime. the regular time production cost is $10.00 per unit which takes into account $4.00 for materials, $1.00 for utilities, and $5.00 for manpower. the manpower cost for overtime is twice the regular rate. holding a unit in inventory costs $1 per unit per week. there is also a cost for been late, at $2.00 per unit per week. the maximum lateness allowed is 2 weeks. it is the company's policy not to have any item in inventory for more than 3 weeks. how much should abc produce each week?

Solutions

Expert Solution

There are two options for the company to produce:

  1. To produce 800 units per week,
  2. To produce as required number of units.

First option:

Produce 800 units per week:

Particulars

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

  1. Demand

700

800

900

500

1100

1000

800

900

  1. Production

800

800

800

800

800

800

800

800

  1. Excess production/Holding

100

-

-

(since earlier excess utilized after 2 weeks)

300

-

(since utilised excess 300 units after 1 week)

200

-

-

(since utilised excess 100 units after 2 weeks)

  1. Production cost per unit

$10

$10

$10

$10

$10

$10

$10

$10

  1. Total production cost= (d*b)

$8,000

$8,000

$8,000

$8,000

$8,000

$8,000

$8,000

$8,000

f.)Overtime cost

-

-

-

-

-

-

-

-

g.)Inventory Holding

cost

1

1

1

1

1

1

1

1

h.)Total Holding cost

(g*c)

(100*2)= $200

-

-

(300*1)=$300

-

-

-

(200*2)=$400

i.)Total All cost

= (e+h)

8200

8000

8000

8300

8000

8000

8000

8400

Therefore, total cost of Regular production= $(8200+8000+8000+8300+8000+8000+8000+8400)= $64,900

Second option:

Produce as required units per week:

Particulars

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

  1. Demand

700

800

900

500

1100

1000

800

900

  1. Production

700

800

900

500

1100

1000

800

900

  1. Overtime production

-

-

100

-

300

200

-

100

  1. Production cost per unit

$10

$10

$10

$10

$10

$10

$10

$10

  1. Total production cost= (d*b)

$7,000

$8,000

$9,000

$5,000

$11,000

$10,000

$8,000

$9,000

f.) Extra Overtime production cost

15

15

15

15

15

15

15

15

g.)Total overtime production cost= f*c

-

-

1500

-

4500

3000

-

1500

h.)Total All cost

= (e+g)

7000

8000

10,500

5000

15500

13000

8000

10,500

Therefore, total cost of Regular production= $(7000+8000+10500+5000+15500+13000+8000+10500)= $77500

First option to produce 800 units per week is the best.


Related Solutions

A company is planning its production schedule over the next six months (it is currently the...
A company is planning its production schedule over the next six months (it is currently the end of month 2). The demand (in units) for its product over that timescale is as shown below: Month 3 4 5 6 7 8 Demand 5000 6000 6500 7000 8000 9500 The company currently has in stock: 1000 units which were produced in month 2; 2000 units which were produced in month 1; 500 units which were produced in month 0. The company...
A manufacturer of integrated circuits is planning production for the next four months. The forecast demand...
A manufacturer of integrated circuits is planning production for the next four months. The forecast demand for the circuits is shown in the following table. Circuit September October November December IC341 650 875 790 1100 IC256 900 350 1200 1300 At the beginning of September, the warehouse is expected to be completely empty. There is room for no more than 1,800 integrated circuits to be stored. Holding costs for both types is $0.05 per unit per month. Because workers are...
An end item’s demand forecasts for the next 6 weeks are 30units, followed by forecasts...
An end item’s demand forecasts for the next 6 weeks are 30 units, followed by forecasts of 25 units for weeks 7 through 10. The current on-hand inventory is 60 units. The order policy is to produce in lots of 80. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 11, 0, 0, 9, 0, 0, and 0 units. The lead time is 2 weeks.Develop an MPS for this end item. (50 points)The marketing...
A production manager needs to develop a production schedule to meet the following demand: Period 1...
A production manager needs to develop a production schedule to meet the following demand: Period 1 2 3 4 5 6 Demand 600 600 800 1000 1200 600 Productions costs are as follows: (a) regular time: $3 per unit. (b) over-time: $5 per unit. (c) subcontract: $7 per unit. (d) Inventory carrying cost = $2 per unit per period (e) Back-order costs = $5 per unit per period. Suppose some workers have retired, and the regular production rate can be...
1. A company producing toy trucks is working to create the production schedule for the next...
1. A company producing toy trucks is working to create the production schedule for the next few months. Its current inventory level is 5,000 toy trucks and, at its current workforce level of 100 employees, is capable of producing 50,000 trucks. The company pays its employees $2,500 per month. The company expects demand during the next three months will be: Month 1 2 3 Demand 48,000 44,000 52,000 Management has decided to maintain a minimum inventory level (measured at the...
An end item’s demand forecasts for the next 6 weeks are 30 units, followed by forecasts...
An end item’s demand forecasts for the next 6 weeks are 30 units, followed by forecasts of 25 units for weeks 7 through 10. The current on-hand inventory is 60 units. The order policy is to produce in lots of 80. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 11, 0, 0, 9, 0, 0, and 0 units. The lead time is 2 weeks. Develop an MPS for this end item. The marketing...
We are preparing a master production schedule for a given item. For this item the demand...
We are preparing a master production schedule for a given item. For this item the demand forecast and booked orders are as follows: Week 1 2 3 4 5 6 Demand Forecast 60 60 80 80 80 50 Booked Orders 58 63 52 20 4 0 Our Week 0 projected on-hand is 132 units. Lead time for this item is 2 weeks, and the order policy for this item is a fixed quantity of 180 units. When this master schedule...
Problem 8-14 Develop a production schedule to produce the exact production requirements by varying the workforce...
Problem 8-14 Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem.      The monthly forecasts for Product X for January, February, and March are 1,010, 1,490, and 1,240, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 550 units.      Manufacturing cost is $200 per unit,...
1. Problems and Applications Q1 A publisher faces the following demand schedule for the next novel...
1. Problems and Applications Q1 A publisher faces the following demand schedule for the next novel from one of its popular authors: Price Quantity Demanded (Dollars) (Copies) 40 0 36 50,000 32 100,000 28 150,000 24 200,000 20 250,000 16 300,000 12 350,000 8 400,000 4 450,000 0 500,000 The author is paid $800,000 to write the novel, and the marginal cost of publishing the novel is a constant $4 per copy. Complete the second, fourth, and fifth columns of...
1. A publisher faces the following demand schedule for the next novel from one of its...
1. A publisher faces the following demand schedule for the next novel from one of its popular authors: The author is paid $2 million to write the book, Price 100 90 80 70 60 50 40 30 20 10 0 QD(1000s) 0 100 200 300 400 500 600 700 800 900 1000 and the marginal cost of publishing the book is a constant $10 per book. a. Compute the total revenue, total cost, and profit at each quantity. What quantity...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT